Justia Energy, Oil & Gas Law Opinion Summaries

Articles Posted in Government & Administrative Law
by
A group of Nantucket residents, organized as Nantucket Residents Against Turbines, challenged the approval of the Vineyard Wind project by the U.S. Bureau of Ocean Energy Management (BOEM). The project involves the construction of a wind power facility off the coast of Massachusetts. The residents alleged that the federal agencies violated the Endangered Species Act by concluding that the project's construction would not jeopardize the critically endangered North Atlantic right whale. They also claimed that BOEM violated the National Environmental Policy Act by relying on a flawed analysis by the National Marine Fisheries Service (NMFS).The case was initially heard in the United States District Court for the District of Massachusetts, which granted summary judgment in favor of the federal agencies. The court found that NMFS and BOEM had followed the law in analyzing the right whale's current status and environmental baseline, the likely effects of the Vineyard Wind project on the right whale, and the efficacy of measures to mitigate those effects. The court also found that the agencies' analyses rationally supported their conclusion that Vineyard Wind would not likely jeopardize the continued existence of the right whale.On appeal, the United States Court of Appeals for the First Circuit affirmed the judgment of the district court. The appellate court found that the lower court had correctly interpreted the law and that the federal agencies had not violated the Endangered Species Act or the National Environmental Policy Act. The court concluded that the agencies' analyses were rational and that their conclusion that the Vineyard Wind project would not likely jeopardize the continued existence of the right whale was supported by the evidence. View "Nantucket Residents Against Turbines v. U.S. Bureau of Ocean Energy Management" on Justia Law

by
The case involves a dispute over the approval of a site certificate for the construction of a wind energy facility in Umatilla County, Oregon. The Energy Facility Siting Council granted the certificate to Nolin Hills Wind, LLC, despite the proposed facility not complying with a local siting criterion requiring a two-mile setback between any turbine and a rural residence. Umatilla County sought judicial review of the council's decision, arguing that the council should have required Nolin Hills to comply with the two-mile setback rule.The case was reviewed by the Supreme Court of the State of Oregon. The court noted that the council had the authority to approve the proposed energy facility despite its failure to comply with the two-mile setback rule. The court also noted that the council had the authority to approve the proposed facility even if it did not pass through more than three land use zones and even if it did not comply with all of the county’s recommended substantive criteria.The Supreme Court of the State of Oregon affirmed the council's decision, concluding that the council was authorized to issue a site certificate for the proposed wind facility notwithstanding the failure of the proposed facility to comply with the two-mile setback rule. The court found that the council was not required to reject a proposed facility simply because it did not comply with a local criterion. The court also rejected the county's argument that the council erred in concluding that the proposed facility "does otherwise comply with the applicable statewide planning goals." View "Umatilla County v. Dept. of Energy" on Justia Law

by
The case involves a request for calendar entries of the Governor's former senior advisor for energy, Alice Reynolds, under the California Public Records Act (PRA). The request was made by the Energy and Policy Institute (EPI) and sought entries reflecting meetings with 10 specified entities, including the California Public Utilities Commission (CPUC), electric utilities, and unions representing energy workers, during the year prior to Reynolds' appointment to the presidency of the CPUC. The Governor's office denied the request, citing the deliberative process privilege, which protects the decision-making process of government agencies from public scrutiny.The trial court ruled in favor of EPI, finding that the public interest in access to these calendar entries outweighed the deliberative process privilege. The Governor appealed this decision to the Court of Appeal of the State of California, Second Appellate District, Division One.The appellate court upheld the trial court's decision, concluding that EPI's request was sufficiently specific, focused, and limited, and the public interest in disclosure was sufficiently compelling when measured against the minimal impact on government decision-making, to override the deliberative process privilege. The court found that the entities specified in EPI's request were entities with which the Governor's senior energy advisor would be expected to meet regardless of the Governor's particular policy priorities. Therefore, disclosure of records that those meetings took place, without any information as to the substance of those meetings, would reveal little if anything about the Governor's or his senior advisor's policy positions or thought processes. The court also concluded that the public has a substantial interest in knowing the extent to which the current CPUC president interacted with the CPUC and the entities the CPUC regulates when she was the Governor's senior advisor for energy. View "State v. Superior Court" on Justia Law

by
The case involves Mojalaki Holdings, LLC and GSSG New Hampshire, LLC (the plaintiffs) who appealed a decision by the City of Franklin Planning Board (the Board) that denied their site plan application to install a solar panel array on a piece of land owned by Mojalaki. The proposed solar panel array required the installation of new utility poles and the removal of mature trees to ensure sufficient sunlight. The land, which was mostly open space and was once a golf course, did not have any specific ordinance language addressing solar panel arrays. The Board, after multiple hearings and a site visit, denied the application based on concerns raised by neighbors about the project's potential impact on the scenery, property values, and previous negative experiences with other solar projects in the city.The Board's decision was upheld by the Superior Court, which agreed with the Board's first and third reasons for denial, namely that the installation of new utility poles would create an industrial look out of place in the neighborhood, and that cutting down mature trees contradicted the purpose provisions. However, the Superior Court did not uphold the Board's second basis, that the solar panel array endangered or adversely impacted the residents, due to lack of supporting facts.The Supreme Court of New Hampshire reversed the lower court's decision, ruling that the Board could not rely solely on the purpose provisions to deny the application. The court found that the purpose provisions lacked sufficient specificity for site plan review and left the proposed project to be judged by the subjective views of the Board through ad hoc decision making. The court granted the plaintiffs a builder's remedy, allowing them to proceed with their development provided they comply with all other applicable regulations. View "Mojalaki Holdings v. City of Franklin" on Justia Law

by
The case involves two separate petitions for review of decisions made by the Federal Energy Regulatory Commission (FERC) to grant extensions of time for the completion of natural gas pipeline projects. The petitioners are Sierra Club and Public Citizen, and the respondents are FERC and the project developers, National Fuel Gas Supply Corporation, Empire Pipeline Inc., Cheniere Corpus Christi Pipeline L.P, and Corpus Christi Liquefaction LLC.The petitions primarily contend that FERC was overly generous in finding "good cause" to grant extensions for the completion of the pipeline projects. The petitioners argue that due to changes in circumstances, such as the introduction of New York's 2019 Climate Act, FERC was obliged to reconsider its original findings of market need for the projects.The court upheld FERC's decisions, finding that it exercised its broad discretion reasonably in both cases. It concluded that FERC's determinations of "good cause" were supported by the record, including National Fuel's litigation over water-quality certification and Cheniere's disrupted investment decision due to the COVID-19 pandemic. The court also found that FERC appropriately decided not to reevaluate its prior findings of market need for the pipeline projects. The court ruled that the petitioners' proposed stricter approach to assessing extension requests was unsupported by the Natural Gas Act and the Administrative Procedure Act. Therefore, the petitions for review were denied. View "Sierra Club v. FERC" on Justia Law

by
In this case, a group of electricity providers challenged orders by the Federal Energy Regulatory Commission (FERC), arguing that FERC allowed a new auction rule to apply retroactively to a pending auction. The auction was overseen by PJM Interconnection L.L.C., a FERC-regulated wholesale market operator. PJM had halted the auction upon realizing that the results could lead to a high clearing price for a particular region due to a faulty assumption regarding the participation of certain resources. PJM sought and received permission from FERC to amend the tariff to allow it to adjust the Locational Deliverability Area (LDA) Reliability Requirement downward, reflecting the lack of participation of certain resources.The petitioners argued that this violated the filed rate doctrine, which prohibits retroactive rates. The court agreed, finding that the tariff amendment was retroactive because it altered the legal consequence attached to a past action: it allowed for the use of a different LDA Reliability Requirement than the one PJM had calculated and posted. The court noted that equitable considerations did not factor into the application of the filed rate doctrine, emphasizing the importance of predictability in the electricity markets.The court granted the petitions and vacated the orders in relevant part, specifically the portion of FERC’s orders that permitted PJM to apply the tariff amendment to the 2024/25 capacity auction. View "Constellation Energy Generation LLC v. FERC" on Justia Law

by
The case involves a dispute over the Federal Energy Regulatory Commission (FERC) allowing a new auction rule to apply retroactively to a pending auction. This auction was administered by PJM Interconnection L.L.C., an entity responsible for running the auction. The petitioners, electric suppliers and their trade associations, contended that FERC's orders violated the filed rate doctrine, which forbids retroactive rates.The United States Court of Appeals for the Third Circuit found that the Tariff Amendment was retroactive because it altered the legal consequence attached to a past action when it allowed PJM to use a different Locational Deliverability Area (LDA) Reliability Requirement than the one it had calculated and posted. The court noted that the Tariff Amendment, therefore, violated the filed rate doctrine.The court ruled that the doctrine's predictability is crucial because electricity markets depend on it. FERC’s disregard of the filed rate doctrine created unpredictability in the markets, potentially eroding confidence in the markets and ultimately harming consumers who buy electricity in those markets.The court granted the petitions for review and vacated the portion of FERC’s orders that allowed PJM to apply the Tariff Amendment to the 2024/25 capacity auction. View "Constellation Energy Generation LLC v. FERC" on Justia Law

by
A group of power providers contested orders from the Federal Energy Regulatory Commission (FERC) that permitted a new auction rule to retroactively apply to a pending auction. The petitioners argued that this violated the filed rate doctrine, which forbids retroactive rates. The auction, administered by the PJM Interconnection LLC (PJM), aimed to ensure reliable electric supply at competitive prices. PJM halted the auction, seeking FERC's permission to amend certain auction parameters it had already posted, which, if left uncorrected, might have led to a high clearing price for a specific region. FERC approved the amendment and allowed it to apply to the halted auction, which the petitioners challenged. The United States Court of Appeals for the Third Circuit agreed with the petitioners, stating that the amendment was retroactive as it altered the legal consequence attached to PJM's past action in the auction. The court granted the petitions and vacated the portion of FERC's orders that allowed the amendment to apply to the auction in question. View "NRG Power Marketing v. FERC" on Justia Law

by
Several power providers and their associations challenged orders from the Federal Energy Regulatory Commission (FERC) that retroactively permitted a new auction rule to apply to a pending auction. The rule was implemented by PJM Interconnection L.L.C., the entity responsible for the auction, to determine the auction's results. The petitioners claimed FERC's orders violated the filed rate doctrine, which prohibits retroactive rates. The case background involves the Federal Power Act (FPA), which grants FERC exclusive jurisdiction over rates for the transmission and wholesale of electric energy in interstate commerce. The FPA requires all related rates, rules, and regulations to be "just and reasonable" and not unduly preferential.The petitioners and FERC agreed that the filed rate was the PJM Open Access Transmission Tariff, which sets the procedures governing PJM’s capacity auctions. PJM administered a capacity auction in December 2022 for capacity in the June 2024 – May 2025 period. A dispute arose when PJM sought to adjust the Locational Deliverability Area (LDA) Reliability Requirement due to perceived anomalies in the auction results, which would have resulted in a high clearing price for a certain region. FERC approved the proposed adjustment, which was challenged by the petitioners.The court agreed with the petitioners and held that the orders of FERC were retroactive and thus violated the filed rate doctrine. The court granted the petitions and vacated the orders in the relevant part. The court emphasized that the equities play no role in the application of the filed rate doctrine and that predictability is of paramount importance in electricity markets. It concluded that FERC’s disregard of the filed rate doctrine creates unpredictability in the markets and may ultimately harm consumers who buy electricity in those markets. View "Electric Power Supply Association v. FERC" on Justia Law

by
In this case, a group of electricity suppliers and their trade associations challenged orders of the Federal Energy Regulatory Commission (FERC) that permitted PJM Interconnection L.L.C., a wholesale market operator, to apply a new auction rule retroactively to a pending auction. The petitioners argued that FERC's orders violated the filed rate doctrine, which prohibits retroactive rates. The United States Court of Appeals for the Third Circuit agreed and granted the petitions, vacating the relevant parts of the orders.The central issue revolved around the Locational Deliverability Area (LDA) Reliability Requirement, a key parameter in PJM's auction process. Prior to the auction, PJM had miscalculated the LDA Reliability Requirement, which led to a potential price increase for a specific region. To correct this, PJM sought FERC's permission to amend the tariff to allow for a downward adjustment of the LDA Reliability Requirement. FERC granted this permission, allowing the new rule to apply to the ongoing auction, which the petitioners argued was a retroactive change in violation of the filed rate doctrine.The court found that the tariff amendment was indeed retroactive as it altered the legal consequence attached to a past action, specifically, PJM's calculation and posting of the LDA Reliability Requirement. The court held that the filed rate doctrine did not yield to equities and that the tariff amendment's retroactivity created instability in the electricity market. Consequently, the court vacated the portion of FERC's orders that allowed PJM to apply the tariff amendment to the 2024/25 capacity auction. View "NRG Business Marketing LLC v. FERC" on Justia Law