Duke Energy Corp. v. FERC

by
The DC Circuit denied Duke's petition for review of the Commission's denial of Duke's complaint against PJM under the Federal Power Act (FPA), 16 U.S.C. 825e. To prepare for a bitterly cold day during the January 2014 polar vortex, Duke purchased expensive natural gas which it ended up not needing. Duke then claimed that PJM, its regional transmission organization, directed it to purchase the gas and that the governing tariff provided for indemnification. The court held that the Commission's finding that PJM never directed Duke to buy gas was supported by substantial evidence on the record. Therefore, the court had no need to address Duke's remaining argument that, had such a directive been issued, the tariff would have authorized indemnification. View "Duke Energy Corp. v. FERC" on Justia Law