San Diego Gas & Electric Co v. FERC

by
The DC Circuit denied SDG&E's petition for review of FERC's declaratory order applying FERC's cancelled or abandoned electricity transmission facilities incentive, 18 C.F.R. 35.35(d)(1)(vi) (Abandonment Incentive), only prospectively, to investments that had yet to occur. Determining that it had jurisdiction over the appeal, the court agreed with the Commission's finding that SDG&E failed to establish the requisite nexus between the Abandonment Incentive and costs it already incurred before it obtained the declaratory order. The court held that the Commission's finding was supported by substantial evidence and its approach comported with both the Federal Power Act and the Incentive Rule. Furthermore, the court found SDG&E's several objections unpersuasive. View "San Diego Gas & Electric Co v. FERC" on Justia Law