Missouri River Energy Services v. FERC

by
The DC Circuit denied a petition for review of FERC's decision upholding charges assessed by the Southwest Power Pool. The court held that FERC's decision was not arbitrary and capricious and rejected Missouri River's argument that the tariff unambiguously confers carve-out eligibility on its transmission reservation under the 1977 Contract; rejected Missouri River's argument that FERC improperly changed course by relying on extrinsic evidence in this case; and rejected Missouri River's undue discrimination claim. The court also held that there was no reason to reject FERC's conclusion that the congestion and marginal loss charges paid for new services not provided for in the 1977 Contract. Finally, the court rejected Missouri River's argument, to the extent it was not forfeited, that the Pool should be equitably estopped from imposing congestion and marginal loss charges against Missouri River. View "Missouri River Energy Services v. FERC" on Justia Law