Rockies Express Pipeline, LLC v. Salazar
In connection with construction of a pipeline to ship natural gas from Wyoming to Eastern Ohio, Rockies Express and Minerals Management Service (MMS), within the Department of the Interior, entered into contracts containing Royalty-in-Kind (RIK) provisions. Under the RIK program, the government receives its royalty for mineral resources extracted under federal leases “in kind,” i.e., in natural gas, rather than in cash, 30 U.S.C. 192; 42 U.S.C. 15902(b). In exchange, the government makes monthly payments to ensure that a certain quantity of the mineral resources is made available for its purposes. The government then enters into processing and transportation contracts to sell the mineral royalties, often at a substantial profit over royalties received in cash. The Civilian Board of Contract Appeals determined that MMS had materially breached the contract, but that Rockies Express was only entitled to damages that had accrued before the Secretary of the Interior announced a decision to phase-out RIK contracts. The Federal Circuit affirmed that MMS materially breached the contract, but reversed the decision to limit damages. Rockies Express is entitled to compensatory damages to put it in as good a position as that in which it would have been put by full performance of the contract. View "Rockies Express Pipeline, LLC v. Salazar" on Justia Law
Town of Smyrna, TN v. Mun. Gas Auth. of GA
The Authority was formed under Ga. Code 46-4-82(a) to provide member municipalities with natural gas. It operates as a non-profit, distributing profits and losses to member municipalities: 64 in Georgia, two in Tennessee, 12 in other states. It pays its own operating expenses and judgments; it is exempt from state laws on financing and investment for state entities and has discretion over accumulation, investment, and management of its funds. It sets its governance rules; members elect leaders from among member municipalities. Smyrna, Tennessee has obtained gas from the Authority since 2000, using a pipeline that does not run through Georgia. The Authority entered a multi-year “hedge” contract for gas acquisition, setting price and volume through 2014, and passed the costs on. The market price of natural gas then fell due to increased hydraulic fracturing (fracking), but Smyrna was still paying the higher price. Smyrna sued for breach of contract, violations of the Tennessee Consumer Protection Act, breach of fiduciary duty, and unjust enrichment. The district court denied the Authority’s motion to dismiss based on sovereign immunity under Georgia law and the Eleventh Amendment. The Sixth Circuit affirmed, stating that the Authority’s claim that any entity referred to as a state “instrumentality” in a Georgia statute is entitled to state-law sovereign immunity “requires quite a stretch of the imagination.”
View "Town of Smyrna, TN v. Mun. Gas Auth. of GA" on Justia Law
Anadarko Petroleum Corp. v. Williams Alaska Petroleum, Inc.
Anadarko appealed the district court's grant of summary judgment in favor of Williams Alaska, arguing that Williams Alaska ignored the parties' agreements to pass through shipping credits on purchased oil. The court, construing the effect of the agreements in light of the contract and the parties' course of performance, concluded that the judgment for Williams Alaska could not stand; the agreements required Williams Alaska to remit any Quality Bank credits it received for the crude oil purchased under the contract; the court rejected Williams Alaska's contention that the obligation to remit the credits expired upon the termination of the agreement; Anadarko filed suit within the four-year statute of limitations and its suit was not time-barred; and Anadarko was entitled to interest on the unpaid Quality Bank credits from the time of breach. Accordingly, the court reversed and rendered judgment in favor of Anadarko, remanding for further proceedings. View "Anadarko Petroleum Corp. v. Williams Alaska Petroleum, Inc." on Justia Law
Engle v. Elm Ridge Exploration Co.
A dispute arose between Elm Ridge Exploration Company, LLC, an operator of oil and gas leases in New Mexico, and Fred Engle, who owned a majority of those leases. Elm Ridge sought to recover drilling expenses by foreclosing on Engle's lease interests. Engle counterclaimed, arguing that Elm Ridge had no authority to operate, and broadly that Elm Ridge breached its contractual and fiduciary duties. Engle also filed a third-party complaint against the previous operators, Central Resources, Inc. and Giant Exploration & Production Company. The district court dismissed two counts on Engle's counterclaim against Elm Ridge and the third-party complaint on statute of limitations grounds. After a trial on Engle's remaining counterclaim count (breach of contractual and fiduciary duties), a jury found that Elm Ridge breached the Operating Agreement and could not recover drilling expenses. The jury found that Engle still owed Elm Ridge for other drilling costs. The district court calculated Engle's share of the costs not attributable to the breach, and held Elm Ridge was entitled to a foreclosure order. Both parties appealed. Finding no error in the district court's calculation or ultimate disposition of the case, the Tenth Circuit affirmed.
View "Engle v. Elm Ridge Exploration Co." on Justia Law
Wallace B. Roderick Revocable Trust v. XTO Energy
Defendant-Appellant XTO Energy, Inc. appealed a district court's certification of a class of Kansas royalty owners who sought recovery for its alleged underpayment of royalties. Specifically, the class claimed XTO violated Kansas law by improperly deducting costs for placing gas into a "marketable condition." After careful consideration, the Tenth Circuit concluded that the class did not meet Rule 23(a)'s commonality, typicality and adequacy requirements or Rule 23(b)(3)'s predominance requirement. Furthermore, the Court found the class' argument in favor of certification through collateral or judicial estoppel unavailing. The class certification order was vacated and the matter remanded for further proceedings.
View "Wallace B. Roderick Revocable Trust v. XTO Energy" on Justia Law
Doe Run Resources Corp. v. Lexington Ins. Co.
Doe Run commenced a declaratory action seeking to enforce Lexington's contractual duty to defend Doe Run per its Commercial General Liability (CGL) policies in two underlying lawsuits (the Briley Lawsuit and the McSpadden Lawsuit). These underlying lawsuits sought damages arising out of Doe Run's operation of a five-hundred-acre waste pile (Leadwood Pile). The court concluded that the pollution exclusions in the CGL policies precluded a duty to defend Doe Run in the Briley Lawsuit. The court concluded, however, that the McSpadden Lawsuit included allegations and claims that were not unambiguously barred from coverage by the pollution exclusions in the policies. The McSpadden Lawsuit alleged that the distribution of toxic materials harmed plaintiffs, without specifying how that harm occurred. The McSpadden complaint also alleged that Doe Run caused bodily injury or property damage when it left the Leadwood Pile open and available for use by the public without posting warning signs. Accordingly, the court affirmed in part, reversed in part, and remanded. View "Doe Run Resources Corp. v. Lexington Ins. Co." on Justia Law
Doe Run Resources Corp. v. Lexington Ins. Co.
Doe Run commenced a declaratory judgment action seeking to enforce Lexington's contractual duty to defend Doe Run per its Commercial General Liability (CGL) policies in an underlying lawsuit. The underlying lawsuit alleged environmental property damage resulting from Doe Run's mine and mill operations. The court affirmed the district court's conclusion that Lexington had no duty to defend because the policies' absolute pollution exclusions unambiguously barred coverage of all claims asserted in the underlying lawsuit. View "Doe Run Resources Corp. v. Lexington Ins. Co." on Justia Law
Lutz v. Chesapeake Appalachia, L.L.C.
Plaintiffs, the owners and lessors of royalty rights to natural gas produced in Trumbull and Mahoning Counties in Ohio, filed a putative class-action lawsuit, alleging that three interrelated energy companies that entered into oil and gas leases with plaintiffs deliberately and fraudulently underpaid gas royalties over more than a decade. Plaintiffs asserted breach of contract and five additional tort and quasi-contract claims and sought compensatory and punitive damages. The district court dismissed, holding that the contract claim was time-barred by Ohio’s four-year statute of limitations and that none of the tort and quasi-contract claims were separate and distinct from the underlying contract action because they did not allege any obligations apart from those imposed by the leases. The Sixth Circuit reversed in part, finding that the district court failed to consider plaintiffs’ fraudulent concealment argument and that allegations regarding due diligence were sufficient to require further analysis. View "Lutz v. Chesapeake Appalachia, L.L.C." on Justia Law
Entergy Nuclear Fitzpatrick, LLC v. United States
In 1983, the Nuclear Waste Policy Act established a plan for spent nuclear fuel (SNF) generated by nuclear power plants, 42 U.S.C. 10101–10270. The Act made utilities responsible for SNF storage until the U.S. Department of Energy (DOE) accepts the material. The Secretary of Energy entered into contracts with nuclear utilities to accept SNF in return for payment of fees. The Act provided that the Nuclear Regulatory Commission “shall not issue or renew a license” to any nuclear utility unless the utility has entered into a contract with DOE or DOE certifies ongoing negotiations. Nuclear utilities, including the owner of the Entergy nuclear power stations, entered into contracts and began making payments, which have continued. By 1994, DOE knew it would be unable to accept SNF by the Act’s January 31, 1998 deadline. In 1995, DOE issued a “Final Interpretation” that took the position that it did not have an unconditional obligation to begin performance on that date. Entergy sued, asserting that DOE’s partial breach caused it to incur additional costs for SNF storage. The claims court struck an unavoidable delay defense, based on a prior decision rejecting DOE’s argument that its failure was “unavoidable” under the contract. The Federal Circuit affirmed. View "Entergy Nuclear Fitzpatrick, LLC v. United States" on Justia Law
Total E&P USA, Inc. v. Kerr-McGee Oil and Gas Corp, et al
This case involved a contractual interpretation dispute over whether overriding royalties were payable out of the initial oil and gas production from a tract of land on the outer continental shelf (OCS) adjacent to Louisiana. The court concluded, under applicable Louisiana law, that the "calculate and pay" clauses in the overriding royalty interests assignment contracts did not clearly and explicitly express the intent that overriding royalty payments shall be suspended whenever the U.S. landowner royalties were suspended under the OCS Deepwater Royalty Relief Act, 43 U.S.C. 1337(a); and that the "calculate and pay" clauses must be interpreted further in search of the common intent of the parties to the assignment contracts. Accordingly, the court reversed the district court's summary judgment and remanded for further proceedings. View "Total E&P USA, Inc. v. Kerr-McGee Oil and Gas Corp, et al" on Justia Law