Justia Energy, Oil & Gas Law Opinion Summaries
Articles Posted in Energy, Oil & Gas Law
NextEra Energy Resources, LLC v. FERC
NextEra Energy Resources, LLC and NextEra Energy Seabrook, LLC (collectively, "Seabrook") own a nuclear power plant in Seabrook, New Hampshire. Avangrid, Inc. and NECEC Transmission LLC (collectively, "Avangrid") sought to connect their New England Clean Energy Connect (NECEC) project to the regional transmission grid. The connection required Seabrook to upgrade its circuit breaker to handle the increased power flow. Seabrook and Avangrid agreed on the necessity of the upgrade and that Avangrid would cover the direct costs, but they disagreed on whether Seabrook should be compensated for indirect costs and whether Seabrook was obligated to upgrade the breaker without full compensation.The Federal Energy Regulatory Commission (FERC) ruled that Seabrook must upgrade the circuit breaker under the Large Generator Interconnection Agreement (LGIA) and that Avangrid was not required to reimburse Seabrook for indirect costs such as legal expenses and lost profits. Seabrook petitioned for review, arguing that FERC lacked statutory authority to require the upgrade and that the LGIA did not obligate them to upgrade the breaker without full compensation.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. The court held that FERC had statutory authority to require the upgrade because it directly affected the transmission of electricity in interstate commerce. The court also found that FERC correctly interpreted the LGIA to require Seabrook to maintain an adequate circuit breaker in light of changing grid conditions, including the interconnection of new generators like Avangrid. Additionally, the court upheld FERC's decision to deny compensation for indirect costs, reasoning that the tariff did not clearly and specifically cover such costs and that FERC's precedent generally did not allow for recovery of opportunity costs during interconnection outages.The court denied Seabrook's petitions for review, affirming FERC's orders. View "NextEra Energy Resources, LLC v. FERC" on Justia Law
In re Letter of Notification Application of Columbia Gas of Ohio, Inc. for the Ford Street Pipeline Project
Columbia Gas of Ohio, Inc. applied to the Ohio Power Siting Board for approval to construct a 3.7-mile natural-gas-distribution pipeline in Maumee, Ohio. The application was submitted under an accelerated review process for pipelines less than five miles long. Yorktown Management, L.L.C., which owns property adjacent to the proposed pipeline route, raised concerns about the safety and environmental impact of the pipeline, particularly its proximity to their commercial office building.The Ohio Power Siting Board approved Columbia's application under the accelerated review process, finding that the project met the necessary criteria. Yorktown filed a motion to intervene and later a motion to suspend the review, arguing that the board had not adequately addressed their safety concerns. The board denied Yorktown's motion to suspend and subsequently denied their application for rehearing, leading Yorktown to appeal the decision.The Supreme Court of Ohio reviewed the case and affirmed the board's decision. The court found that Columbia's application did not require a 50-foot-wide permanent easement along the entire pipeline route, as Yorktown claimed. The court also determined that Yorktown had waived its right to challenge the board's rejection of testimony from a different pipeline project. Additionally, the court held that the board did not err in refusing to suspend its review of the accelerated application, as Yorktown failed to demonstrate good cause for suspension. The court concluded that the board did not improperly defer to Columbia and had appropriately conditioned the approval on compliance with relevant safety regulations. View "In re Letter of Notification Application of Columbia Gas of Ohio, Inc. for the Ford Street Pipeline Project" on Justia Law
ACE American Insurance Company v. Hetsco, Inc.
In June 2016, an explosion damaged a gas processing plant in Moss Point, owned by Enterprise Gas Processing LLC. Enterprise alleged that the explosion was caused by Hetsco Inc.'s negligent repair of a heat exchanger. Hetsco argued that a Proposal for Services between it and the plant's prior owner, BP, entitled it to summary judgment. The circuit court agreed, granting summary judgment in favor of Hetsco.The Jackson County Circuit Court found that BP's employee, Hayes, had apparent authority to bind BP to the Proposal for Services, which included a forum-selection clause and a two-year statute of limitations. The court concluded that the Proposal for Services was a valid and enforceable contract, and thus, Enterprise's claims were barred by the forum-selection clause and the statute of limitations.The Supreme Court of Mississippi reviewed the case and found that genuine issues of material fact remained regarding Hayes's apparent authority to bind BP to the Proposal for Services. The court noted that the evidence did not conclusively show that Hayes had the authority to agree to the legal terms of the Proposal for Services. Additionally, the court found that there were factual disputes about whether BP ratified the Proposal for Services and whether Enterprise could be bound by it as BP's successor.The Supreme Court of Mississippi reversed the circuit court's grant of summary judgment and remanded the case for further proceedings. The court held that the contractually shortened two-year statute of limitations in the Proposal for Services was unenforceable under Mississippi law. The court did not address the enforceability of the forum-selection clause, leaving that issue for the circuit court to consider on remand. View "ACE American Insurance Company v. Hetsco, Inc." on Justia Law
Liberty Petroleum Corp. v. NDIC
Liberty Petroleum Corporation appealed a judgment affirming North Dakota Industrial Commission (NDIC) orders approving a plan of unitization for the Haystack Butte (Bakken Pool) Unit (HBU) in McKenzie County, North Dakota. Burlington Resources Oil & Gas Co. LP petitioned NDIC for unitized management of the HBU, which would allow drilling without regard to spacing unit boundaries. Liberty, holding federal oil and gas leases and working interests in the HBU, objected to the plan, particularly Article 11.8, which provided for the payment of pre-unitization risk penalty balances from unit production proceeds. Liberty argued this would unfairly take revenue from wells it participated in to satisfy penalties on non-consent wells.The District Court of McKenzie County affirmed NDIC's orders, finding that the plan of unitization was in the public interest, protective of correlative rights, and necessary to increase oil and gas recovery and prevent waste. NDIC concluded that production from the unit area would be distributed to each tract within the unit area, regardless of where it was produced, and rejected Liberty's objections to Article 11.8.The North Dakota Supreme Court reviewed the case and upheld the lower court's decision. The Court found that NDIC did not exceed its authority, misapply the law, or authorize an unconstitutional taking. It held that NDIC's approval of Article 11.8 was consistent with the unitization statutes, which allow for the recovery of risk penalties from unit production. The Court also concluded that NDIC's findings were supported by substantial and credible evidence, including expert testimony from Burlington. The judgment was affirmed, and NDIC's orders were upheld. View "Liberty Petroleum Corp. v. NDIC" on Justia Law
D’Augusta v. American Petroleum Institute
Gasoline consumers alleged that various oil producers colluded with the U.S. government, including then-President Trump, to negotiate with Russia and Saudi Arabia to cut oil production, limit future oil exploration, and end a price war on oil. Plaintiffs claimed this agreement fixed gas prices in violation of Sherman Act § 1, suppressed competition in violation of Sherman Act § 2, and involved anticompetitive mergers in violation of Clayton Act § 7.The United States District Court for the Northern District of California dismissed the case, finding it lacked subject-matter jurisdiction under the political question and act of state doctrines. The court also found that Plaintiffs failed to adequately plead an antitrust conspiracy. Additionally, the court dismissed Defendant Energy Transfer for lack of personal jurisdiction and denied Plaintiffs leave to amend their complaint, as well as requests for additional discovery and oral argument.The United States Court of Appeals for the Ninth Circuit affirmed the district court’s dismissal. The court held that the political question doctrine barred judicial review of the President’s foreign policy decisions, as these decisions are committed to the political branches of government. The court also found no judicially manageable standards to resolve the claims under antitrust laws. Additionally, the act of state doctrine barred the claims because they involved evaluating the petroleum policies of foreign nations. The court further held that Plaintiffs failed to state a plausible antitrust conspiracy claim regarding Defendants’ private conduct. Finally, the court found no abuse of discretion in the district court’s procedural rulings. View "D'Augusta v. American Petroleum Institute" on Justia Law
Conservation Law Foundation v. Energy Facilities Siting Board
The case involves a proposed electric substation in East Boston by NSTAR Electric Company, doing business as Eversource Energy. The Energy Facilities Siting Board (the board) granted a certificate of environmental impact and public interest to Eversource for the substation. The petitioners, Conservation Law Foundation and GreenRoots, Inc., challenged this decision, arguing that Eversource failed to show "undue delay" by two city agencies, and that the board did not properly consider environmental justice principles, among other issues.Previously, Eversource's petition to build the substation was approved by the board in 2017, with a project change approved in 2018. The petitioners intervened in the proceedings, and the board issued a decision in November 2022, granting the certificate. The petitioners then filed for judicial review in the Supreme Judicial Court for the county of Suffolk.The Supreme Judicial Court of Massachusetts reviewed the case and upheld the board's decision. The court found that the board's determination of "undue delay" by the city agencies was supported by substantial evidence. The court also concluded that the board properly considered environmental justice principles, including the equitable distribution of energy benefits and burdens. Additionally, the court found that the board's decision to issue the equivalent of a G. L. c. 91 tidelands license was lawful and supported by substantial evidence. The court affirmed the board's findings on the need for the substation, its compatibility with environmental protection, public health, and safety, and its alignment with the public interest. The decision of the board was affirmed. View "Conservation Law Foundation v. Energy Facilities Siting Board" on Justia Law
Sunvestment Energy Group NY 64 LLC v. National Grid USA Services Co., Inc.
The case involves a dispute over fees related to contracts between independent solar generators (the plaintiffs) and National Grid USA Services Co., Inc. and its affiliate Niagara Mohawk Power Corporation (the defendants). The plaintiffs are required to pay costs for interconnecting their solar energy projects to the defendants' electric distribution grid, which includes a "tax gross-up adder" to offset the defendants' federal income tax liability. The plaintiffs sought a declaratory judgment that these interconnection payments are not taxable income and also sought to recover the allegedly unlawful tax-related fees through state-law claims for damages.The United States District Court for the Northern District of New York dismissed the case, finding that it lacked subject-matter jurisdiction. The court concluded that the plaintiffs' request for a declaratory judgment was barred by the Declaratory Judgment Act because the federal tax issue would only arise as a defense to a state-law breach of contract claim. The court also found that the plaintiffs' state-law claims did not raise a substantial federal question, as the federal tax issue was not significant to the federal system as a whole.The United States Court of Appeals for the Second Circuit affirmed the district court's judgment. The appellate court agreed that the plaintiffs' request for declaratory relief did not meet the threshold requirement for federal subject-matter jurisdiction, as the federal tax issue would only arise as a defense in a hypothetical state-law breach of contract claim. The court also found that the federal issue in the plaintiffs' state-law claims was not substantial, as it was fact-bound and situation-specific, and did not have broader significance for the federal government. Therefore, the district court's dismissal for lack of subject-matter jurisdiction was upheld. View "Sunvestment Energy Group NY 64 LLC v. National Grid USA Services Co., Inc." on Justia Law
Beyond Nuclear, Inc. v. NRC
Holtec International applied to the Nuclear Regulatory Commission (NRC) for a license to construct and operate a spent nuclear fuel storage facility in New Mexico. The NRC denied multiple requests for intervention and a hearing from various petitioners, including Beyond Nuclear, Sierra Club, and Fasken Land and Minerals. These petitioners argued that the NRC acted unreasonably and contrary to law in denying their requests.The Atomic Safety and Licensing Board (Board) found the petitioners' contentions inadmissible and denied their petitions to intervene. The NRC affirmed the Board’s decisions. Beyond Nuclear, Environmental Petitioners (including Sierra Club), and Fasken each petitioned for review of the orders denying intervention. The case was held in abeyance until the NRC issued Holtec a license, after which the case was removed from abeyance for review by the United States Court of Appeals for the District of Columbia Circuit.The United States Court of Appeals for the District of Columbia Circuit reviewed the petitions and found that the NRC reasonably declined to admit the petitioners' factual contentions and complied with statutory and regulatory requirements. The court held that Beyond Nuclear did not raise a genuine dispute of law or fact regarding the NRC’s authority to consider Holtec’s application. The court also found that Environmental Petitioners failed to demonstrate any genuine disputes of material fact or law in their contentions related to statutory authority, alleged misrepresentations by Holtec, and compliance with the National Environmental Policy Act (NEPA). Additionally, the court determined that Fasken’s late-filed contentions were procedurally defective, untimely, and immaterial.The court denied all the petitions for review, affirming the NRC’s decisions to deny the requests for intervention. View "Beyond Nuclear, Inc. v. NRC" on Justia Law
In re: VIRTUAL CITADEL, INC.
The case involves the valuation of a bitcoin mining property owned by Michael Oken, who had invested millions in infrastructure upgrades to support bitcoin mining. The property, located in College Park, Georgia, included a Power Sales Agreement with the city for low-cost electricity, which was crucial for the mining operation. After Oken's death in 2019, his businesses filed for Chapter 11 bankruptcy, and the property was sold along with an adjacent data center for $4.9 million. The deeds indicated a $2.45 million value for each property based on transfer taxes. Two creditors, Thomas Switch Holding and Bay Point Capital, sought to recover on liens against the property.The bankruptcy court held a bench trial to determine the property's value. Switch's appraiser, Michael Easterwood, valued the property at $830,000 using the cost approach, considering the infrastructure improvements. Bay Point's appraiser, Jeff Miller, valued it at $48,000 using the sales comparison approach, comparing it to other light industrial properties. The bankruptcy court adopted Easterwood's valuation, finding the property to be a special purpose property with bitcoin mining as its highest and best use. The court valued the property at over $700,000, awarding the full escrow amount to Switch.The United States District Court for the Northern District of Georgia affirmed the bankruptcy court's decision. On appeal, the United States Court of Appeals for the Eleventh Circuit reviewed the case. The appellate court upheld the bankruptcy court's findings, agreeing that the property was a special purpose property with bitcoin mining as its highest and best use. The court also affirmed the use of the cost approach for valuation and found no clear error in considering the tax stamp value as supporting evidence. The judgment of the lower courts was affirmed. View "In re: VIRTUAL CITADEL, INC." on Justia Law
Pacific Gas and Electric Company v. FERC
Pacific Gas and Electric Company (PG&E) and the San Francisco Public Utilities Commission (SFPUC) have a longstanding dispute over PG&E's obligation to wheel energy to SFPUC's customers. SFPUC generates power and sells it to end users in San Francisco but relies on PG&E to distribute this energy. The disagreement centers on which consumers are entitled to wheeled service under a grandfathering clause in PG&E's 2015 Tariff, which incorporates a statutory provision allowing wheeling for consumers served by SFPUC as of October 24, 1992.Initially, the Federal Energy Regulatory Commission (FERC) rejected SFPUC's class-based approach, which argued that PG&E should wheel energy to the same types of customers served in 1992. FERC's 2019 order was vacated by the United States Court of Appeals for the District of Columbia Circuit, which remanded the case for FERC to provide a reasoned analysis of the statutory requirements. On remand, FERC adopted a class-based interpretation, allowing wheeling to all customers of the same class served in 1992, not just specific end users.The United States Court of Appeals for the District of Columbia Circuit reviewed FERC's orders and found them contrary to law. The court held that the plain meaning of "ultimate consumer" in the statutory provision refers to specific end users, not classes of consumers. The court emphasized that the statutory text does not support a class-based interpretation and that such an interpretation would undermine the primary restriction against FERC-ordered wheeling. Consequently, the court vacated FERC's orders and remanded the case for FERC to apply the plain meaning of the statute and determine which of SFPUC's consumers qualify for wheeled service under the 2015 Tariff. View "Pacific Gas and Electric Company v. FERC" on Justia Law