Justia Energy, Oil & Gas Law Opinion Summaries

Articles Posted in Environmental Law
by
This case arose from actions taken by the Commission approving an application by Southern for combined licenses to construct and operate new Units 3 and 4 of the Vogtle Nuclear Plant and an application by Westinghouse for an amendment to its already-approved reactor design on which the Vogtle application relied. After the close of the combined-license hearing record, petitioners sought to reopen the hearing to litigate contentions relating to the nuclear accident at the Fukushima Dai-ichi complex in Japan. The court held that the Commission acted reasonably in denying petitioners' contentions where the Task Force Report, studying the implications of the Fukushima accident for the United States, alone was not a "new and significant" circumstance requiring a supplemental environmental impact statement and petitioners' contentions lacked specific links between the Fukushima Accident and the Vogtle Site. Accordingly, the court denied the petitions for review. View "Blue Ridge Env. Defense League, et al v. Nuclear Regulatory Commission, et al" on Justia Law

by
Mingo Logan applied to the Corps for a permit under section 404 of the Clean Water Act (CWA), 33 U.S.C. 1344, to discharge dredged or fill material from a mountain-top coal mine in West Virginia into three streams and their tributaries. The Corps issued the permit to Mingo Logan, approving the requested disposal sites for the discharged materials. Four years later, the EPA invoked its subsection 404(c) authority to "withdraw" the specifications of two of the streams as disposal sites, thereby prohibiting Mingo Logan from discharging them. Mingo Logan then filed this action challenging the EPA's withdrawal of the specified sites. The court reversed the district court's grant of summary judgment to Mingo Logan and concluded that the EPA had post-permit withdrawal authority. Accordingly, the court remanded for further proceedings. View "Mingo Logan Coal Co. v. EPA" on Justia Law

by
Defenders sued the EPA based on the EPA's alleged failure to promptly promulgate revisions to certain effluent limitations and effluent limitations guidelines under the Clean Water Act (CWA), 33 U.S.C. 1251 et seq. UWAG, an association of energy companies and three national trade associations of energy companies, appealed the denial of intervention and also asserted that the court should vacate the district court's order entering a consent decree between Defenders and the EPA because the district court lacked subject matter jurisdiction. The court affirmed the denial of intervention because UWAG lacked Article III standing and, as there was no appellant with standing, dismissed the remainder of the appeal. View "Defenders of Wildlife, et al v. Jackson" on Justia Law

by
In 2007, the Army Corps of Engineers issued two nationwide general permits that authorized surface and underground coalmining operations to discharge dredged and fill material into waters of the United States. The Corps conducted a public notice-and-comment period and completed a cumulative-impacts analysis that projected the permits’ respective environmental impacts before determining that compensatory mitigation would reduce adverse impacts to a minimal level. The Corps disclosed its analyses and findings in each permit’s Environmental Assessment in lieu of an environmental impact statement. Riverkeeper sued, alleging violations of the Clean Water Act, 33 U.S.C. 1344(e), the National Environmental Protection Act, 42 U.S.C. 4332(2)(C), and the Administrative Procedure Act, 5 U.S.C. 706, during the Corps’ issuance of two nationwide coal-mining waste-discharge permits in 2007. The district court granted summary judgment to the Corps. During Riverkeeper’s appeal, the permits at issue expired. The Sixth Circuit concluded that the case remains in controversy and reversed in part. Although the Corps repeatedly objected to the feasibility of Riverkeeper’s demands, in taking the “easier path” of preparing an environmental assessment instead of an environmental impact statement the Corps failed to follow CWA and NEPA regulations by documenting its assessment of environmental impacts and examining past impacts. View "KY Riverkeeper, Inc. v. Rowlette" on Justia Law

by
Seven affiliated debtors are entities that conducted deep and strip coal mining and operated coal prep plants and loading facilities in three states. The bankruptcy court authorized joint procedural administration, but not substantive consolidation. The administrative expense claims at issue arise from environmental damage. The land and the coal were subject to leases that terminated before commencement of bankruptcy proceedings. The West Virginia Department of Environmental Protection (WVDEP) issued mining permits and National Pollutant Discharge Elimination System permits to the debtors and affiliated entities for the operations. The bankruptcy court denied WVDEP’s application for administrative expenses against two debtors. The Sixth Circuit Bankruptcy Appellate Panel held that the court failed to properly analyze the debtors’ potential liability for reclamation obligations associated with permits owned by their affiliate. WVDEP’s administrative expense claims were properly denied to the extent they were based on derivative liability for the debts of the affiliate, either based on veil piercing or substantive consolidation. The court abused its discretion in denying the claims that were based on direct liability for reclamation obligations associated with the permits owned by the affiliate and in denying claims that were independent of the threshold question of joint and several liability for reclamation obligations associated with the permits owned by an affiliate. View "In re: Appalachian Fuels, LLC" on Justia Law

by
The Clean Air Act New Source Review program forbids construction of new pollution sources without a permit, 42 U.S.C. 7475. Operators of major pollutant-emitting sources who plan construction must make a preconstruction projection of the increase in emissions following construction, to determine whether the project constitutes a “major modification,” requiring a permit. DTE planned on replacing 2,000 square feet of tubing, the economizer, and large sections of reheater piping; installing a new nine-ton device that provides voltage that creates the electromagnetic field needed for the rotor to produce electricity; and refurbishing boiler feedwater pumps at its power plant. The project required 83 days and $65 million. DTE performed required calculations and projected an emissions increase of 3,701 tons per year of sulfur dioxide and 4,096 tons per year of nitrogen oxides. Under the regulations, an increase of 40 tons per year of either substance is significant. DTE determined that the increase fell under the demand growth exclusion. The Michigan Department of Environmental Quality took no action and construction began. The U.S. EPA filed notice of violation. The district court granted DTE summary judgment. The Sixth Circuit reversed. While the regulations allow operators to undertake projects without having EPA second-guess their projections, EPA is not categorically prevented from challenging blatant violations until after modifications are made. View "United States v. DTE Energy Co." on Justia Law

by
This case stemmed from Chevron's involvement in litigation over the alleged environmental contamination of oil fields in Ecuador. Ecuador sought discovery from John Connor and GSI Environmental, his company, for use in a foreign arbitration against Chevron. During the course of extended litigation with Ecuador, Chevron, an intervenor in the district court, benefited repeatedly by arguing against Ecuador and others that the arbitration was a "foreign or international tribunal." Because Chevron's previous positions were inconsistent with its current argument, judicial estoppel was appropriate to make discovery under 28 U.S.C. 1782 available for Ecuador. Accordingly, the court reversed and remanded for determination of the scope of discovery. View "Republic of Ecuador, et al v. Connor, et al" on Justia Law

by
This case stemmed from Congress's amendment of the Clean Air Act, 42 U.S.C. 7545(o), to establish a renewable fuel standard (RFS) program. API objected to the EPA's 2012 projection for cellulosic biofuel and to its refusal to reduce the applicable advanced biofuels volume for 2012. The court rejected API's argument that the EPA failed to justify its determination not to reduce the applicable advanced biofuels volume for 2012. However, because the EPA's methodology for making its cellulosic biofuel projection did not take neutral aim at accuracy, the court held that it was an unreasonable exercise of agency discretion. Accordingly, the court vacated the 2012 RFS rule and remanded for further proceedings. View "American Petroleum Institute v. EPA" on Justia Law

by
This case stemmed from the multi-district litigation involving the Deepwater Horizon drilling rig oil spill. Plaintiff appealed from the district court's dismissal of its action brought under the citizen-suit provisions of the Clean Water Act (CWA), 33 U.S.C. 1365(a)(1), the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), 42 U.S.C. 9659(a), and the Emergency Planning and Community Right-to-Know Act (EPCRA), 42 U.S.C. 11046(a). The court concluded, with one exception, that the district court did not err by dismissing plaintiff's claims as moot because the Macondo well had been capped and sealed; on the present state of the record, plaintiff had standing to assert its claim for relief based on defendants' alleged failure to comply with the reporting requirements of EPCRA; and the EPCRA claim was not moot. Accordingly, the court affirmed in part, reversed in part, and remanded for further proceedings. View "In Re: Deepwater Horizon" on Justia Law

by
NextEra Energy Seabrook, LLC, which operated a nuclear power plant in Seabrook, New Hampshire, applied to renew its operating license. NextEra submitted a required environmental report that concluded that offshore wind electric generation was not a reasonable alternative to the extended licensing of Seabrook. Several environmental groups (collectively, Petitioners) questioned and sought a hearing on NextEra's environmental report. The Atomic Safety and Licensing Board admitted the contention, but the Nuclear Regulatory Commission (NRC) denied the admission of the contention, which resulted in Petitioners not being entitled to have a hearing on the merits about their contention that generation of electricity from offshore wind was a reasonable alternative source of baseload energy to the relicensing of Seabrook. The First Circuit Court of Appeals denied Petitioners' petition for review, holding (1) the NRC did not misapply case law interpreting the National Environmental Policy Act in formulating its contention-admissibility standard; and (2) NRC's conclusion that the contention was inadmissible was not arbitrary or capricious, and there was no basis in law to set it aside. View "Beyond Nuclear v. U.S. Nuclear Regulatory Comm'n" on Justia Law