Taylor Energy Co., L.L.C. v. Department of the Interior
Taylor Energy leased and operated Gulf of Mexico oil and gas properties, on the Outer Continental Shelf, offshore Louisiana. In 2004, Hurricane Ivan destroyed those operations, causing oil leaks. The Outer Continental Shelf Lands Act, the Clean Water Act, and the Oil Pollution Act required Taylor to decommission the site and stop the leaks. Taylor and the Department of the Interior developed a plan. Interior approved Taylor’s assignments of its leases to third parties with conditions requiring financial assurances. Three agreements addressed how Taylor would fund a trust account and how Interior would disburse payments. Taylor began decommissioning work. In 2009, Taylor proposed that Taylor “make the full final deposit into the trust account,” without any offsets, and retain all insurance proceeds. Interior rejected Taylor’s proposal. Taylor continued the work. In 2011, Taylor requested reimbursement from the trust account for rig downtime costs. Interior denied the request. In 2018, the Interior Board of Land Appeals (IBLA) affirmed Interior’s 2009 and 2011 Decisions.Taylor filed suit in the Claims Court, asserting contract claims. The Federal Circuit affirmed the dismissal of the suit, rejecting “Taylor’s attempt to disguise its regulatory obligations as contractual ones,” and stating an IBLA decision must be appealed to a district court.In 2018, Taylor filed suit in a Louisiana district court, seeking review of the IBLA’s 2018 decision and filed a second complaint in the Claims Court, alleging breach of contract. On Taylor's motion, the district court transferred the case, citing the Tucker Act. The Federal Circuit reversed. The Claims Court does not have subject matter jurisdiction over this case. Taylor is challenging the IBLA Decision and must do so in district court under the APA. View "Taylor Energy Co., L.L.C. v. Department of the Interior" on Justia Law
Standing Rock Sioux Tribe v. United States Army Corps of Engineers
The DC Circuit held that the Corps violated the National Environmental Policy Act (EPA) by issuing an easement allowing the Dakota Access Pipeline to transport crude oil through federally owned land at the Lake Oahe crossing site without preparing an environmental impact statement despite substantial criticisms from the Tribes.The court rejected the Corps' and Dakota Access' contention that the district court applied the wrong standard by relying on National Parks Conservation Association v. Semonite, 916 F.3d at 1083, which emphasized the important role played by entities other than the federal government. The court explained that the Tribes' unique role and their government-to-government relationship with the United States demand that their criticisms be treated with appropriate solicitude. The court concluded that several serious scientific disputes in this case means that the effects of the Corps' easement decision are likely to be "highly controversial." The court also noted that, although the risk of a pipeline leak may be low, that risk is sufficient that a person of ordinary prudence would take it into account in reaching a decision to approve the pipeline's placement, and its potential consequences are therefore properly considered. The court affirmed the district court's order vacating the easement while the Corps prepares an environmental impact statement. However, the court reversed the district court's order to the extent it directed that the pipeline be shut down and emptied of oil. View "Standing Rock Sioux Tribe v. United States Army Corps of Engineers" on Justia Law
Sierra Club v. U. S. Army Corps of Engineers
MVP asked two Army Corps districts to verify that, pursuant to the Clean Water Act, MVP's proposed discharge of dredged and/or fill material into waters of the United States in furtherance of construction of a natural gas pipeline in those districts could be governed by the Army Corps' 2017 nationwide permit (NWP) referred to as NWP 12. The Huntington District issued a verification, determining that the Pipeline project met the criteria for operation under the NWP 12, excusing the project from the individual permitting process (the "Verification"). The Norfolk District did the same, issuing a reinstatement of its prior verification allowing MVP to use NWP 12 in that district (the "Reinstatement"). Petitioners filed petitions for agency review of the Verification and Reinstatement pursuant to the Natural Gas Act (NGA) and filed the instant motions to stay.The Fourth Circuit concluded that petitioners are likely to succeed on the merits of their petitions for review, and other equitable factors weigh in favor of granting the motions for stay. The court explained that the Verification was likely issued in contravention of applicable law because the Army Corps impermissibly incorporated into NWP 12 a modified permit condition from the West Virginia Department of Environmental Protection (WVDEP). Furthermore, because the Verification was likely issued in contravention of law, the Reinstatement (which necessarily depends on the validity of the Verification) is likely defective as well. Therefore, the court granted petitioners' motions for a stay of the Huntington District's Verification and the Norfolk District's Reinstatement until such time as the court may consider the petitions for review on their merits. However, the court concluded that petitioners are not likely to succeed on the merits of their challenges to the Army Corps' 2017 issuance of NWP 12 itself because the court likely lacks jurisdiction to entertain such challenges. View "Sierra Club v. U. S. Army Corps of Engineers" on Justia Law
Communities for a Better Environment v. Energy Resources Conservation & Development Commission
Environmental groups challenged the constitutionality of Public Resources Code section 25531, which limits judicial review of decisions by the Energy Resources Conservation and Development Commission on the siting of thermal power plants. Section 25531(a) provides that an Energy Commission siting decision is “subject to judicial review by the Supreme Court of California.” The plaintiffs contend this provision abridges the original jurisdiction of the superior courts and courts of appeal over mandate petitions, as conferred by California Constitution Article VI, section 10. Section 25531(b) provides that findings of fact in support of a Commission siting determination “are final,” allegedly violating the separation of powers doctrine by depriving courts of their essential power to review administrative agency findings (Cal. Const., Art. III, section 3; Art. VI, section 1).The court of appeal affirmed summary judgment in favor of the plaintiffs. The Article VI grant of original jurisdiction includes the superior courts and courts of appeal and may not be circumscribed by statute, absent some other constitutional provision. Legislative amendments to section 25531 have broken the once-tight link between the regulatory authority of the Public Utilities Commission (PUC) and Energy Commission power plant siting decisions, such that the plenary power Article XII grants the Legislature over PUC activities no longer authorizes section 25531(a). Section 25531(b) violates the judicial powers clause by preventing courts from reviewing whether substantial evidence supports the Commission’s factual findings. View "Communities for a Better Environment v. Energy Resources Conservation & Development Commission" on Justia Law
Ergon-West Virginia, Inc. v. Environmental Protection Agency
The Fourth Circuit granted Ergon's petition for review of the EPA's decision denying Ergon's petition to be exempt from the EPA's administration of a renewable fuel standard program. The court previously vacated and remanded the EPA's denial as arbitrary and capricious. On remand, the EPA denied Ergon's petition again. In this appeal, Ergon argues that the EPA repeated the errors the court previously identified in Ergon I by again relying on the DOE's facially deficient scoring metrics to deny the petition.The court reviewed the record and concluded that, although the EPA's post-remand decision largely cured the problems the court previously identified, Ergon has provided sufficient evidence undermining one aspect of the EPA's decision. In this case, part of the EPA's basis for accepting the DOE's reasoning as to Section 1(b) of the DOE's Scoring Matrix has been reliably called into question, and thus the EPA's decision was arbitrary and capricious. Because of the threshold problem with the rationale provided for the Section 1(b) scoring, the court did not reach the secondary issue regarding the apparently contradictory definitions of "refinery" used in Section 1(b) and 2(a). Accordingly, the court vacated and remanded for further proceedings. View "Ergon-West Virginia, Inc. v. Environmental Protection Agency" on Justia Law
State of Rhode Island v. Shell Oil Products Co., LLC
The First Circuit affirmed the order of the federal district court allowing Rhode Island's motion to return to state court its state court complaint against several oil and gas companies for damage caused by fossil fuels, holding that the allegations in Rhode Island's complaint did not give rise to federal-officer jurisdiction.In 2018, faced with rising sea levels and other property damage from extreme weather events caused by climate change, Rhode Island sued, in state court, several oil and gas companies for damage caused by fossil fuels while those companies misled the public about their products' true risks. The oil companies removed the case to federal district court. Rhode Island moved for the case to be remanded to state court. The district court granted the motion and ordered the case remanded to state court. The First Circuit affirmed, holding that the district court did not err in finding that there was no subject matter jurisdiction under the federal-officer removal statute. View "State of Rhode Island v. Shell Oil Products Co., LLC" on Justia Law
Environmental Law & Policy Center, et al. v. N.D. Public Svc. Commission, et al.
Environmental Law and Policy Center and Dakota Resource Council (“Appellants”) appealed from a district court judgment affirming the Public Service Commission’s order dismissing Appellants’ formal complaint on the basis of a lack of subject matter jurisdiction. This appeal arose from Meridian Energy Group, Inc.’s construction of a new oil refinery (“Davis Refinery”) in Billings County, North Dakota. In June 2018, Appellants filed a formal complaint with the Commission, alleging: Meridian was required to obtain a certificate of site compatibility from the Commission under N.D.C.C. ch. 49-22.1; and Meridian’s planned facility would have a capacity of refining 50,000 or more barrels per day (bpd). Appellants filed their complaint after the North Dakota Department of Health, now Department of Environmental Quality, granted Meridian a construction permit for a “55,000 bpd” oil refinery. The complaint sought a declaration that Meridian’s refinery was subject to N.D.C.C. ch. 49-22.1 and to the statutory siting process. The Commission determined the complaint stated a “prima facie case” under its pleading rule, and the Commission formally served the complaint on Meridian. Meridian asserted it was constructing a refinery with a capacity of 49,500 bpd, falling outside the Commission’s statutory jurisdictional threshold of 50,000 bpd. Meridian argued, as a result, the Commission did not have jurisdiction over this matter and the complaint must be dismissed. After review, the North Dakota Supreme Court concluded the Commission did not err when it dismissed Appellants’ complaint. The Court affirmed the district court’s judgment and the Commission’s order of dismissal. View "Environmental Law & Policy Center, et al. v. N.D. Public Svc. Commission, et al." on Justia Law
Taylor Energy Co. LLC v. United States
Taylor's leases for the Outer Continental Shelf (OCS), set to expire in 2007, incorporated Outer Continental Shelf Lands Act (OCSLA), 43 U.S.C. 1301, regulations. They required Taylor to leave the leased area “in a manner satisfactory to the [Regional] Director.” Taylor drilled 28 wells, each connected to an oil platform. In 2004, Hurricane Ivan toppled Taylor’s platform, rendering the wells inoperable. Taylor discovered leaking oil but took no action. In 2007, Taylor was ordered to decommission the wells within one year. Taylor sought extensions. The government required Taylor to set aside funds for its decommissioning obligations. For Taylor to receive reimbursement, the government must confirm the work was conducted “in material compliance with all applicable federal laws and . . . regulations" and with the Leases. The resulting Trust Agreement states that it “shall be governed by and construed in accordance with the laws of" Louisiana. Taylor attempted to fulfill its obligations. The government approved a departure from certain standards but ultimately refused to relieve Taylor of its responsibilities.Taylor filed claims involving Louisiana state law: breach of the Trust Agreement; request for dissolution of the trust account based on impossibility of performance; request for reformation for mutual error; and breach of the duty of good faith and fair dealing. The Federal Circuit affirmed the dismissal of the complaint. OCSLA makes federal law exclusive in its regulation of the OCS. To the extent federal law applies to a particular issue, state law is inapplicable. OCSLA regulations address the arguments underlying Taylor’s contract claims, so Louisiana state law cannot be adopted as surrogate law. View "Taylor Energy Co. LLC v. United States" on Justia Law
In re: Sealed Case
The DC Circuit denied the Refinery's motion to proceed under a pseudonym. The court weighed the markedly thin showing of potential injury by the Refinery against the substantial public interest in transparency and openness in cases involving the government's administration of an important statutory and regulatory scheme, holding that the Refinery has not overcome the customary and constitutionally-impeded presumption of openness in judicial proceedings.In this case, the Refinery has failed to demonstrate that requiring it to proceed in its own name will risk the disclosure of sensitive and highly personal information; the Refinery itself faces no risk of physical or mental harm; and the Refinery has chosen to sue a government agency regarding the operation of a statutory program and, in particular, applications for special exemptions from the law's obligations. The court held that none of the factors commonly involved in analyzing a request to proceed anonymously weigh in the Refinery's favor. Furthermore, the Refinery's additional arguments add nothing to its side of the scale either. View "In re: Sealed Case" on Justia Law
POET Biorefining, LLC v. Environmental Protection Agency
The EPA issued a regulation known as the Pathways II Rule, allowing renewable-fuel producers to use a measurement method "certified by a voluntary consensus standards body" (VCSB), or a method "that would produce reasonably accurate results as demonstrated through peer reviewed references." EPA then issued the Cellulosic Guidance to explain its interpretation of the applicable regulatory requirements and clarify the types of analyses and demonstrations that might meet them.The DC Circuit dismissed in part and denied in part POET's petition for review of the Cellulosic Guidance. The court held that POET's challenge to the Guidance's treatment of VCSB-certified methods is unripe because no such method yet exists and POET's registration efforts rely on the peer-reviewed alternative. In regard to POET's challenge to the Guidance's discussion of peer-reviewed methods, the court held that the Guidance announces a final, interpretive rule that lawfully construes the underlying regulation. View "POET Biorefining, LLC v. Environmental Protection Agency" on Justia Law