Justia Energy, Oil & Gas Law Opinion Summaries
Articles Posted in Government & Administrative Law
Affirmed Energy, LLC v. FERC
A provider of energy efficient resources (EERs), which are projects that reduce electrical consumption, challenged a decision by the Federal Energy Regulatory Commission (FERC) approving a change to PJM Interconnection LLC’s tariff. PJM manages the electrical grid in parts of thirteen states and the District of Columbia, and it operates capacity auctions to ensure reliable electricity supply. Historically, EERs were allowed to bid in these auctions for up to four consecutive years to compensate for a lag in PJM’s statistical model (load forecast), which previously did not account for new EERs’ impact on energy consumption. In 2016, PJM updated its model to capture these effects in real time, removing the need for EERs to participate in the auctions.In 2024, PJM proposed a tariff amendment to exclude EERs from future capacity auctions, citing the improved accuracy of its load forecast and the unnecessary costs imposed on consumers by double-counting EERs’ effects. FERC approved this amendment, finding it would lower costs for consumers without compromising grid reliability. Affirmed Energy LLC, an EER aggregator, protested, arguing that the amendment was unlawfully retroactive and arbitrary and capricious, as it would disrupt settled expectations and reliance interests, particularly for projects that had already cleared prior auctions.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. It held that FERC’s orders were not retroactive because they only applied to future auctions and did not strip EER providers of entitlements to past payments or auction results. The court also found that FERC had reasonably evaluated PJM’s updated forecast, weighed the reliance interests at stake, and explained why the amendment was justified. The petition for review was denied. View "Affirmed Energy, LLC v. FERC" on Justia Law
Garaas v. NDIC
Several trusts owned by the Garaas family hold mineral interests in McKenzie County, North Dakota. Petro-Hunt, L.L.C. operates a well on these lands, which are subject to two distinct spacing units created by orders of the North Dakota Industrial Commission (NDIC): a base unit and an overlapping unit. NDIC issued an order allocating production from the well in the overlapping unit to Section 20, which is part of the base unit but not wholly contained within the overlapping unit. This allocation reduced the Trusts’ royalty interests, prompting them to seek declaratory relief and damages.The Trusts first brought their claims in the District Court of McKenzie County, but the court dismissed the case. The North Dakota Supreme Court affirmed the dismissal, holding that the Trusts were required to exhaust administrative remedies before the NDIC. Subsequently, Petro-Hunt applied to NDIC for clarification on production allocation, and NDIC issued Order No. 33453, allocating production from the overlapping unit to the base unit. The Trusts appealed NDIC’s order to the district court, which affirmed NDIC’s order. The Trusts then appealed to the North Dakota Supreme Court.The Supreme Court of North Dakota held that NDIC had legal authority under statute to allocate oil and gas production among spacing units. However, the court concluded that NDIC did not regularly pursue its authority because it failed to follow proper procedures, including providing notice and opportunity to participate to all affected interest owners. As a result, the Supreme Court reversed the district court’s judgment and vacated NDIC Order No. 33453. The request for attorney’s fees by the Trusts was denied, as the record did not show NDIC acted without substantial justification. View "Garaas v. NDIC" on Justia Law
Petro Star Inc. v. FERC
The case centers on the Trans Alaska Pipeline System (TAPS), which transports crude oil from Alaska’s North Slope, with oil from different shippers being commingled in the pipeline. To address variations in oil quality, a “Quality Bank” compensates shippers who inject higher-quality oil and charges those with lower-quality oil. The valuation of one particular oil component, Resid—the heaviest and least valuable cut—has been disputed for decades. Petro Star, a shipper whose refineries lack specialized units to further process Resid, argued that Resid was undervalued, while ConocoPhillips contended it was overvalued. The TAPS owners, who administer the Quality Bank, also challenged a Federal Energy Regulatory Commission (FERC) finding that the Bank’s administrator violated tariff provisions.Following a 2013 FERC investigation into the Resid valuation formula, both Petro Star and ConocoPhillips intervened, seeking changes. After initial FERC findings were remanded for further explanation by the United States Court of Appeals for the District of Columbia Circuit, FERC held additional hearings. An administrative law judge (ALJ) concluded the formula was just and reasonable, and FERC largely affirmed this result, also finding a tariff violation by the Quality Bank administrator for failing to update formula yields based on monthly Resid testing.On review, the United States Court of Appeals for the District of Columbia Circuit held that FERC’s formula for valuing Resid remains just and reasonable, as neither Petro Star nor ConocoPhillips demonstrated the formula to be unjust or unreasonable. The court also upheld FERC’s finding that the Quality Bank administrator violated the tariff by not updating formula yields with each test, but found FERC’s prospective remedy—requiring monthly testing and annual yield updates—was appropriate. The court denied all three petitions. View "Petro Star Inc. v. FERC" on Justia Law
Independent Market Monitor for PJM v. FERC
PJM Interconnection LLC manages an extensive electrical grid across thirteen states and the District of Columbia. To ensure competitive market conditions and compliance with regulatory standards, PJM employs Market Monitoring Analytics LLP as its independent market monitor (IMM). For several years, IMM attended meetings between PJM’s Board of Managers and the Liaison Committee, a nonvoting body designed to facilitate communication between PJM Members and the Board. However, PJM began enforcing the Liaison Committee’s charter provision, restricting attendance to end-use customers and regulated utilities, thereby excluding IMM from future meetings.After this exclusion, IMM filed a complaint with the Federal Energy Regulatory Commission (FERC), arguing that PJM’s action violated Section IV.G of its tariff, which IMM interpreted as granting it the right to participate in such stakeholder processes. FERC reviewed the complaint and dismissed it. The Commission determined that Section IV.G only applied to decision-making bodies within PJM that handle proposed revisions to tariffs or market rules, not to the Liaison Committee, which functions solely as a communication forum and does not engage in decision-making or voting.IMM subsequently petitioned the United States Court of Appeals for the District of Columbia Circuit for review of FERC’s decision. The Court, before addressing the merits, examined whether IMM had standing to challenge its exclusion. The Court held that IMM failed to demonstrate a concrete or particularized injury resulting from its inability to attend the Liaison Committee meetings, as IMM retained access to all market data required for its monitoring functions and had alternative avenues for communication with the Board. The Court further found that IMM had not shown any expenditure of resources to counteract the alleged harm. Consequently, the petition was dismissed for lack of jurisdiction due to IMM’s lack of standing. View "Independent Market Monitor for PJM v. FERC" on Justia Law
American Gas Association v. DOE
The case concerns a challenge to amended energy efficiency standards issued by the U.S. Department of Energy (DOE) for consumer furnaces (specifically, residential non-weatherized gas furnaces and mobile home gas furnaces) and certain commercial water heaters under the Energy Policy and Conservation Act (EPCA). Petitioners, including trade associations, manufacturers, and energy providers, argued that the new standards would effectively eliminate non-condensing appliances from the market, claiming these products offer unique features and performance characteristics not available in condensing models. They also contended that DOE failed to provide adequate economic justification for the new standards and did not comply with procedural requirements during rulemaking.Previously, DOE had issued a series of proposed rules and interpretive rules regarding whether non-condensing technology constituted a protected performance characteristic under EPCA. After public comment and a period of shifting interpretations, DOE ultimately concluded in its 2021 Interpretive Rule that non-condensing technology does not provide a unique performance-related feature compared to condensing appliances. DOE then promulgated final rules in 2023 amending the efficiency standards for both consumer furnaces and commercial water heaters. Petitioners sought review of these actions in the United States Court of Appeals for the District of Columbia Circuit.The United States Court of Appeals for the District of Columbia Circuit held that DOE’s interpretation—that non-condensing appliances do not offer performance characteristics or features substantially different from condensing appliances—was reasonable and supported by the record. The court also found that DOE’s economic justification for the amended standards was robust and supported by substantial evidence (and, for commercial water heaters, by clear and convincing evidence). Additionally, the court determined that DOE provided an adequate opportunity for public comment. Accordingly, the court denied the petitions for review, upholding DOE’s rules. View "American Gas Association v. DOE" on Justia Law
Gas Transmission Northwest v. Federal Energy Regulatory Commission
A natural gas pipeline company replaced three aging compressor units along its pipeline, which transports gas from Canada to the Pacific Northwest. The replacements used newer, higher-capacity compressors, but the company initially installed controls to limit their output to match the old units. After completing the replacements, the company sought federal approval to expand pipeline capacity by removing those restrictions and making other upgrades, securing long-term contracts for the added capacity with new customers. The company excluded the cost of the earlier compressor replacements from the expansion’s cost estimate, assuming those costs would remain allocated to existing customers.The Federal Energy Regulatory Commission (FERC) approved the compressor replacements under its automatic authorization regulation, finding no further environmental review was needed. Later, FERC issued a certificate for the expansion project under the Natural Gas Act, after preparing an environmental impact statement (EIS) as required by the National Environmental Policy Act (NEPA). FERC declined to treat the compressor replacements as part of the expansion for environmental or rate-setting purposes and denied the company’s request for a “predetermination” that expansion costs could be rolled into existing rates in future proceedings. Multiple parties, including two states and environmental groups, sought rehearing and then judicial review, challenging FERC’s decisions on environmental review, rate allocation, and public need.The United States Court of Appeals for the Fifth Circuit reviewed the consolidated petitions. The court held that the pipeline company had standing and its claims were ripe. On the merits, the court found FERC’s decisions were not arbitrary or capricious. FERC reasonably excluded the compressor replacements from the expansion’s environmental and rate analysis, applied its established policies for rate-setting and public need, and provided sufficient environmental review under NEPA. The court denied all petitions for review. View "Gas Transmission Northwest v. Federal Energy Regulatory Commission" on Justia Law
Helmerich & Payne International Drilling Co. v. Petroleos De Venezuela, S.A.
In 2010, the Venezuelan government expropriated assets belonging to a Venezuelan subsidiary of a U.S.-based energy company. The subsidiary had provided drilling services to a state-owned Venezuelan energy company, but after a breakdown in their business relationship and significant unpaid invoices, Venezuelan authorities blockaded the subsidiary’s operations, issued public statements about nationalization, and ultimately transferred the subsidiary’s assets to the state-owned company, which began operating them. The U.S. parent company claimed that this expropriation rendered its ownership interest in the subsidiary worthless and deprived it of its rights to control the subsidiary’s assets.The U.S. parent company and its Venezuelan subsidiary filed suit in the United States District Court for the District of Columbia against Venezuela and its state-owned energy company, alleging unlawful expropriation. The district court denied the defendants’ motion to dismiss, and the U.S. Court of Appeals for the District of Columbia Circuit initially affirmed. However, the Supreme Court vacated that decision, clarifying the standard for the Foreign Sovereign Immunities Act (FSIA) expropriation exception. On remand, the D.C. Circuit found that only the U.S. parent company had a valid claim under international law, as the domestic-takings rule barred the subsidiary’s claim. The district court later dismissed Venezuela as a defendant, leaving the state-owned company as the sole defendant.On appeal, the United States Court of Appeals for the District of Columbia Circuit affirmed the district court’s denial of the state-owned company’s motion to dismiss. The court held that the FSIA’s expropriation exception applied because Venezuela indirectly expropriated the U.S. company’s property, the state-owned company owns and operates the expropriated assets, and it engages in commercial activity in the United States. The court also held that personal jurisdiction was proper and that the act-of-state doctrine, as limited by the Second Hickenlooper Amendment, did not bar the claim. View "Helmerich & Payne International Drilling Co. v. Petroleos De Venezuela, S.A." on Justia Law
Antero Resources Corporation v. Federal Energy Regulatory Commission
An independent natural gas producer contracted with a pipeline operator to secure firm transportation capacity through an expansion project, which involved adding new compressor stations to an existing pipeline segment. The producer agreed to pay for the construction of these facilities and the applicable fuel and power charges. The pipeline operator recoups fuel costs through rates based on the amount of gas shipped, with costs increasing exponentially as more gas is transported. After the expansion, the pipeline operator implemented a two-tier fuel rate system: the producer was always charged the highest marginal fuel rate, as if its gas was the last and most expensive to move through the pipeline, while all other shippers paid an average rate.Initially, the Federal Energy Regulatory Commission (FERC) approved the pipeline operator’s tariff, including the two-tier rate structure, and later reaffirmed this approach when the producer protested after experiencing significantly higher fuel rates compared to other shippers. The producer argued that the rate structure was unduly discriminatory and not “just and reasonable” under the Natural Gas Act. An administrative law judge upheld the rates, and FERC affirmed, reasoning that the producer, as the “but for” cause of the expansion, should bear the highest marginal costs to prevent subsidization by other shippers.The United States Court of Appeals for the District of Columbia Circuit reviewed the case and held that FERC’s approval of the two-tier fuel rate was arbitrary and capricious. The court found that perpetually assigning the producer the highest marginal fuel rate was disconnected from the actual costs imposed by its use of the pipeline and violated the principle of cost causation. The court granted the producer’s petition for review, vacated FERC’s order, and remanded for further proceedings to establish a just and reasonable rate consistent with cost-causation principles. View "Antero Resources Corporation v. Federal Energy Regulatory Commission" on Justia Law
Sierra Club v. Federal Energy Regulatory Commission
The case concerns the approval of a 32-mile natural gas pipeline intended to supply fuel to a new natural-gas turbine that will replace one of two coal-fired units at the Cumberland Fossil Plant in Tennessee. The Tennessee Valley Authority (TVA), a federal agency, decided to retire the coal units and replace one with a gas turbine, which is expected to reduce greenhouse gas emissions. The Federal Energy Regulatory Commission (FERC) approved the pipeline after preparing a detailed environmental impact statement. The Sierra Club and Appalachian Voices challenged this approval, arguing that FERC’s decision violated the National Environmental Policy Act (NEPA) and the Natural Gas Act.Previously, FERC issued a certificate of public convenience and necessity for the pipeline, finding that market need was established by TVA’s long-term agreement to purchase all pipeline capacity and that the project’s benefits outweighed its harms. FERC also credited the pipeline with enabling a net reduction in emissions due to the coal-to-gas transition. After the Sierra Club requested rehearing, FERC clarified that only one coal unit would be replaced but maintained its approval. The Sierra Club then petitioned the United States Court of Appeals for the District of Columbia Circuit for review.The United States Court of Appeals for the District of Columbia Circuit denied the petitions. The court held that FERC’s approval complied with NEPA and the Natural Gas Act. It found that FERC reasonably analyzed downstream emissions, properly considered the no-action alternative, and was not required to analyze the pipeline and power plant as connected actions because FERC lacked regulatory authority over power generation. The court also held that FERC’s reliance on TVA’s precedent agreement established market need and that FERC’s public interest balancing was reasonable. The court emphasized that, following recent Supreme Court precedent, judicial review of NEPA compliance is highly deferential. View "Sierra Club v. Federal Energy Regulatory Commission" on Justia Law
State of Iowa v. Wright
The case concerns a challenge to a 2024 rule issued by the Department of Energy (DOE) that revised the method for calculating the “petroleum equivalency factor” (PEF), which is used to determine the fuel economy values of electric vehicles for regulatory purposes. The DOE had previously used a “fuel content factor” of 1/0.15, which significantly inflated the fuel economy ratings of electric vehicles. In its 2023 proposal, DOE suggested eliminating this factor, but in the final rule, it opted to phase it out gradually over several model years. The final rule also introduced a new method for calculating the PEF, using a “cumulative gasoline-equivalent fuel economy of electricity” based on the projected useful life of an electric vehicle fleet—a method not included in the proposed rule.Several states and the American Free Enterprise Chamber of Commerce petitioned for review in the United States Court of Appeals for the Eighth Circuit. They argued that the DOE exceeded its statutory authority by retaining the fuel content factor and violated notice-and-comment requirements by adopting a new calculation method not previously proposed. The petitioners asserted standing based on increased costs to maintain public roads due to heavier electric vehicles and environmental harms from increased greenhouse gas emissions.The Eighth Circuit found that the petitioners had standing and that the case was not moot, even in light of new EPA emissions standards. The court held that DOE exceeded its statutory authority by retaining the fuel content factor, as the relevant statute did not authorize such an approach. Additionally, the court determined that DOE violated notice-and-comment procedures by failing to provide adequate notice of the new cumulative calculation method. The court concluded that these deficiencies were not severable from the rest of the rule.Accordingly, the Eighth Circuit granted the petition for review, vacated the 2024 final rule, and remanded the matter to DOE. View "State of Iowa v. Wright" on Justia Law