Justia Energy, Oil & Gas Law Opinion Summaries

Articles Posted in Government & Administrative Law
by
A private company specializing in the disposal of wastewater from oil and gas fracking leased land in an urban area and constructed two saltwater-injection wells. After two earthquakes were recorded near the wells, the State of Ohio determined the company’s activities caused the seismic events and temporarily suspended operations at both wells. One well was later permitted to resume limited operations, but the suspension of the second well remained until 2021. The company had been aware of seismicity risks before acquiring its leasehold and warned investors of possible regulatory shutdowns.After the suspension, the company pursued administrative and judicial challenges, including an appeal to the Ohio Oil and Gas Commission and the Tenth District Court of Appeals, both of which upheld the State’s actions. The company then filed a petition for a writ of mandamus in the Eleventh District Court of Appeals, claiming a regulatory taking of its property. The Eleventh District initially denied relief, but following multiple remands from the Supreme Court of Ohio, it ultimately found no total taking but did find a compensable partial regulatory taking under the Penn Central analysis, ordering the State to initiate eminent-domain proceedings.On appeal, the Supreme Court of Ohio reviewed whether the suspension order constituted a total or partial regulatory taking. The court held that the company failed to prove it was deprived of all economically beneficial use, rejecting the total taking claim. The court further held that, under a proper balancing of the Penn Central factors, the State’s actions did not amount to a compensable partial taking. The Supreme Court of Ohio affirmed the Eleventh District’s denial of the total takings claim, reversed its partial takings finding, and denied the writ of mandamus. View "State ex rel. AWMS Water Solutions, L.L.C. v. Mertz" on Justia Law

by
Devon Energy Production Company, L.P. was engaged in gas production from two New Mexico units under a federal lease, which required payment of royalties to the federal government. State officials, acting under federal authority, audited Devon Energy’s operations and disallowed certain deductions related to the treatment and transportation of natural gas over a four-year period. The charges for these services were bundled, making it difficult to separate deductible from non-deductible costs. A related Devon entity had previously resolved a similar dispute with the government through a settlement agreement, which established formulas for calculating allowable deductions.The Office of Natural Resources Revenue, a federal agency, reviewed Devon Energy’s objections to the audit and upheld the disallowance, ordering payment of the contested royalties or further documentation. Devon Energy sought review in the United States District Court for the Western District of Oklahoma, arguing that the agency acted arbitrarily and capriciously by not considering the prior settlement agreement. The district court affirmed the agency’s decision, reasoning that the agreement did not cover all disputed royalties.The United States Court of Appeals for the Tenth Circuit reviewed the case de novo, applying the arbitrary-and-capricious standard. The Tenth Circuit found that the agency erred by failing to consider the prior settlement agreement, which may have had significant legal and factual implications for the calculation of deductions. The court also found that the record was insufficient to support the government’s alternative arguments for affirmance, such as the identity of the contracting entity and the expiration of the agreement’s terms. The Tenth Circuit reversed the district court’s judgment and remanded the case for the district court to determine the appropriate remedy—whether vacatur of the agency’s decision or a remand to the agency is warranted. View "Devon Energy Production Company v. DOI" on Justia Law

by
KC Transport, an independent trucking company, provides hauling services for mining and other companies. It operates a maintenance facility for its haul trucks about a mile from one of its primary client’s active mines. During an inspection, a Mine Safety and Health Administration (MSHA) inspector observed two KC Transport trucks at the facility undergoing maintenance in conditions that violated federal safety standards—specifically, the trucks were raised and unblocked, with one worker standing underneath. The inspector issued citations for these violations.In an administrative proceeding, KC Transport contested the citations, arguing that MSHA lacked jurisdiction over its facility and trucks since they were not located at an extraction site or on an appurtenant road. An administrative law judge (ALJ) found that MSHA had jurisdiction, reasoning that the facility and trucks were “used in” mining-related activities and thus constituted a “mine” under the Federal Mine Safety and Health Amendments Act. KC Transport appealed, and the Federal Mine Safety and Health Review Commission reversed the ALJ, holding that only facilities or equipment located at extraction sites or appurtenant roads qualify as “mines” under the Act and vacated the citations.The Secretary of Labor, acting through MSHA, petitioned the United States Court of Appeals for the District of Columbia Circuit for review. After an intervening Supreme Court decision overruled Chevron deference, the D.C. Circuit independently interpreted the relevant statutory provisions. The court held that a “facility” constitutes a “mine” under the Mine Act when it is necessarily connected with the use and operation of extracting, milling, or processing minerals, even if not located directly at an extraction site or appurtenant road. Concluding that KC Transport’s facility met this definition, the court vacated the Commission’s decision and affirmed the Secretary’s citations. View "Secretary of Labor v. KC Transport, Inc." on Justia Law

by
Several oil refineries with average daily crude oil throughput below 75,000 barrels in 2024 applied to the Environmental Protection Agency (EPA) in 2025 for exemptions from their obligations under the Renewable Fuel Standard (RFS) program for the 2024 compliance year. The RFS program, established under the Clean Air Act, requires refineries to blend renewable fuels into transportation fuels. The Act provides for a “small refinery” exemption for facilities that do not exceed the 75,000-barrel threshold in a calendar year. The petitioning refineries did not seek exemptions for 2023 and based their applications solely on their 2024 throughput.After the refineries submitted their applications, the EPA informed them that, under its 2014 regulation, eligibility required a refinery to meet the “small refinery” definition both for "the most recent full calendar year prior to seeking an extension" and for "the year or years for which an exemption is sought." The EPA interpreted this to mean petitioners needed to satisfy the throughput limit in both 2023 and 2024. Since the refineries exceeded the threshold in 2023, the EPA denied the exemption requests. The refineries then sought review in the United States Court of Appeals for the District of Columbia Circuit.The D.C. Circuit held that the EPA’s interpretation of its 2014 regulation was contrary to the regulation’s plain text. The court found that, because the applications were filed in 2025 for the 2024 compliance year, both the “most recent full calendar year prior to seeking an extension” and “the year for which an exemption is sought” referred to 2024. Since the petitioners met the threshold in 2024, they were eligible under the regulation. The court vacated the EPA’s denial orders and remanded for further proceedings. View "Alon Refining Krotz Springs, Inc. v. EPA" on Justia Law

by
Minority shareholders of an Argentine oil and gas company, previously privatized in 1993, became involved in litigation after the Argentine government expropriated a majority stake in the company in 2012. The government’s acquisition of shares was conducted without making a public tender offer to minority shareholders, a process that was explicitly required by the company’s bylaws to protect such shareholders in the event of a takeover. The plaintiffs, consisting of Spanish entities and a New York hedge fund, had acquired significant stakes in the company, and after the expropriation, they claimed that they suffered substantial financial losses due to the government’s failure to comply with the tender offer requirement.The plaintiffs sued in the United States District Court for the Southern District of New York, asserting breach of contract and promissory estoppel claims under Argentine law against both the Argentine Republic and the company. After extensive litigation, the district court found in favor of the plaintiffs on their breach of contract claims against the Argentine Republic, awarding over $16 billion in damages, but granted summary judgment to the company, finding it had no obligation to enforce the tender offer provision. The court also dismissed the promissory estoppel claims.On appeal, the United States Court of Appeals for the Second Circuit held that the plaintiffs' breach of contract damages claims against the Argentine Republic and the company were not cognizable under Argentine law, reasoning that the bylaws did not create enforceable bilateral obligations between shareholders and that Argentine public law governing expropriation precluded such claims. The court affirmed the dismissal of the promissory estoppel claims and judgment in favor of the company, but reversed the judgment against the Argentine Republic, remanding for further proceedings consistent with its opinion. View "Petersen Energía v. Argentine Republic" on Justia Law

by
A renewable energy developer was awarded a standard-offer contract in 2014 to build a solar facility in Bennington, Vermont, with a requirement to commission the project by 2016. The developer repeatedly sought and received extensions to this deadline, while simultaneously pursuing a certificate of public good (CPG), which is also required for construction. The Public Utility Commission (PUC) granted the CPG in 2018, but it was appealed, reversed, and ultimately denied on remand due to violations of local land conservation measures and adverse impacts on aesthetics. The Vermont Supreme Court affirmed the final CPG denial in 2023.While litigation over the CPG was ongoing, the developer continued to seek extensions of its standard-offer contract’s commissioning milestone. The fifth extension request, filed in 2021, asked for a deadline twelve months after the Supreme Court’s mandate in the CPG appeal. The hearing officer recommended granting it, but the PUC did not act on the request until 2024, by which time the developer’s CPG had been finally denied. The PUC dismissed the fifth extension request as moot, finding the contract had expired by its own terms. The PUC also denied the developer’s motion for reconsideration and a sixth extension request, on the same grounds.On appeal, the Vermont Supreme Court reviewed the PUC’s actions with deference, upholding its factual findings unless clearly erroneous and its discretionary decisions unless there was an abuse of discretion. The Court held that the PUC properly concluded the requested extension was moot, the contract was null and void by its terms, and there was no abuse of discretion. The Court also rejected arguments that the PUC’s actions were inconsistent with other cases or violated constitutional rights. The orders of the PUC were affirmed. View "In re Petition of Apple Hill Solar LLC" on Justia Law

by
California’s net energy metering (NEM) program has, for decades, allowed utility customers with renewable energy systems to receive credit for excess electricity sent to the grid. Concerns grew that this system resulted in a substantial subsidy for NEM customers, shifting costs to non-NEM ratepayers. In 2013, the Legislature enacted a law requiring the Public Utilities Commission (Commission) to create a successor tariff that balanced the costs and benefits of customer-sited renewable energy, ensured sustainable growth, and prevented cost-shifting. After years of study and rulemaking, the Commission adopted a new tariff in 2022, fundamentally changing how credits for exported power are calculated and introducing measures aimed at equity and system sustainability.Petitioners, which included environmental and community advocacy groups, challenged the new tariff before the Commission and, after rehearing was denied, sought review in the California Court of Appeal, First Appellate District. The court initially affirmed the Decision, applying a highly deferential standard of review. Petitioners then sought review in the California Supreme Court, which held that the standard used was too deferential and directed the appellate court to apply the standard articulated in Yamaha Corp. of America v. State Board of Equalization, which requires courts to independently assess whether the agency acted within its delegated authority and consistent with the law.On remand, the California Court of Appeal, First Appellate District, reviewed the tariff under this framework. The court concluded the Commission’s actions were within its delegated authority and that the successor tariff satisfied statutory requirements for sustainable growth, equitable treatment of disadvantaged communities, and balancing of costs and benefits. The court rejected petitioners’ arguments that the tariff failed to consider all relevant benefits or improperly disadvantaged certain groups. The court affirmed the Commission’s Decision and awarded costs to the Commission and real parties in interest. View "Center for Biological Diversity, Inc. v. Public Utilities Commission" on Justia Law

by
A provider of energy efficient resources (EERs), which are projects that reduce electrical consumption, challenged a decision by the Federal Energy Regulatory Commission (FERC) approving a change to PJM Interconnection LLC’s tariff. PJM manages the electrical grid in parts of thirteen states and the District of Columbia, and it operates capacity auctions to ensure reliable electricity supply. Historically, EERs were allowed to bid in these auctions for up to four consecutive years to compensate for a lag in PJM’s statistical model (load forecast), which previously did not account for new EERs’ impact on energy consumption. In 2016, PJM updated its model to capture these effects in real time, removing the need for EERs to participate in the auctions.In 2024, PJM proposed a tariff amendment to exclude EERs from future capacity auctions, citing the improved accuracy of its load forecast and the unnecessary costs imposed on consumers by double-counting EERs’ effects. FERC approved this amendment, finding it would lower costs for consumers without compromising grid reliability. Affirmed Energy LLC, an EER aggregator, protested, arguing that the amendment was unlawfully retroactive and arbitrary and capricious, as it would disrupt settled expectations and reliance interests, particularly for projects that had already cleared prior auctions.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. It held that FERC’s orders were not retroactive because they only applied to future auctions and did not strip EER providers of entitlements to past payments or auction results. The court also found that FERC had reasonably evaluated PJM’s updated forecast, weighed the reliance interests at stake, and explained why the amendment was justified. The petition for review was denied. View "Affirmed Energy, LLC v. FERC" on Justia Law

by
Several trusts owned by the Garaas family hold mineral interests in McKenzie County, North Dakota. Petro-Hunt, L.L.C. operates a well on these lands, which are subject to two distinct spacing units created by orders of the North Dakota Industrial Commission (NDIC): a base unit and an overlapping unit. NDIC issued an order allocating production from the well in the overlapping unit to Section 20, which is part of the base unit but not wholly contained within the overlapping unit. This allocation reduced the Trusts’ royalty interests, prompting them to seek declaratory relief and damages.The Trusts first brought their claims in the District Court of McKenzie County, but the court dismissed the case. The North Dakota Supreme Court affirmed the dismissal, holding that the Trusts were required to exhaust administrative remedies before the NDIC. Subsequently, Petro-Hunt applied to NDIC for clarification on production allocation, and NDIC issued Order No. 33453, allocating production from the overlapping unit to the base unit. The Trusts appealed NDIC’s order to the district court, which affirmed NDIC’s order. The Trusts then appealed to the North Dakota Supreme Court.The Supreme Court of North Dakota held that NDIC had legal authority under statute to allocate oil and gas production among spacing units. However, the court concluded that NDIC did not regularly pursue its authority because it failed to follow proper procedures, including providing notice and opportunity to participate to all affected interest owners. As a result, the Supreme Court reversed the district court’s judgment and vacated NDIC Order No. 33453. The request for attorney’s fees by the Trusts was denied, as the record did not show NDIC acted without substantial justification. View "Garaas v. NDIC" on Justia Law

by
The case centers on the Trans Alaska Pipeline System (TAPS), which transports crude oil from Alaska’s North Slope, with oil from different shippers being commingled in the pipeline. To address variations in oil quality, a “Quality Bank” compensates shippers who inject higher-quality oil and charges those with lower-quality oil. The valuation of one particular oil component, Resid—the heaviest and least valuable cut—has been disputed for decades. Petro Star, a shipper whose refineries lack specialized units to further process Resid, argued that Resid was undervalued, while ConocoPhillips contended it was overvalued. The TAPS owners, who administer the Quality Bank, also challenged a Federal Energy Regulatory Commission (FERC) finding that the Bank’s administrator violated tariff provisions.Following a 2013 FERC investigation into the Resid valuation formula, both Petro Star and ConocoPhillips intervened, seeking changes. After initial FERC findings were remanded for further explanation by the United States Court of Appeals for the District of Columbia Circuit, FERC held additional hearings. An administrative law judge (ALJ) concluded the formula was just and reasonable, and FERC largely affirmed this result, also finding a tariff violation by the Quality Bank administrator for failing to update formula yields based on monthly Resid testing.On review, the United States Court of Appeals for the District of Columbia Circuit held that FERC’s formula for valuing Resid remains just and reasonable, as neither Petro Star nor ConocoPhillips demonstrated the formula to be unjust or unreasonable. The court also upheld FERC’s finding that the Quality Bank administrator violated the tariff by not updating formula yields with each test, but found FERC’s prospective remedy—requiring monthly testing and annual yield updates—was appropriate. The court denied all three petitions. View "Petro Star Inc. v. FERC" on Justia Law