Justia Energy, Oil & Gas Law Opinion Summaries

Articles Posted in Government & Administrative Law
by
Tenaska Clear Creek Wind, LLC ("Clear Creek") sought to generate wind energy for sale in parts of Missouri, southeast Iowa, and northeast Oklahoma. Clear Creek challenged the Federal Energy Regulatory Commission's (FERC) decision to allow Southwest Power Pool, Inc. (SPP) to assign over $100 million in upgrade costs to Clear Creek for its wind turbine project. Clear Creek argued that FERC's decision was arbitrary, capricious, and contrary to precedent.Initially, Clear Creek submitted an interconnection request to Associated Electric Cooperative, Inc. (AECI) and requested Network Resource Interconnection Service (NRIS). AECI identified SPP and Midcontinent Independent System Operator, Inc. (MISO) as potentially affected systems. SPP conducted several studies, initially estimating upgrade costs at $31.2 million, which later fluctuated significantly. Clear Creek began construction based on initial studies but faced a restudy by SPP, which increased the estimated costs to $763 million, later adjusted to $102 million. Clear Creek filed a complaint with FERC, which partially granted and partially denied the complaint, requiring SPP to restudy the project using updated models. The restudy resulted in $88 million in upgrade costs.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. The court upheld FERC's orders, finding that SPP's methodology for assigning upgrade costs was consistent with the "but for" cost allocation principle and not arbitrary or capricious. The court also found that Clear Creek's downgrade to Energy Resource Interconnection Service (ERIS) did not moot the case, as Clear Creek retained the right to re-open the matter if it prevailed. The court concluded that FERC's decision was based on reasoned decision-making and substantial evidence, denying Clear Creek's petitions for review. View "Tenaska Clear Creek Wind, LLC v. FERC" on Justia Law

by
The Environmental Protection Agency (EPA) updated its regulations to ensure that the transportation fuel mix in the United States contains the required amounts of renewable fuel. The new regulations specifically address biogas-derived renewable fuel, implementing a more structured process to prevent fraud and error. The Coalition for Renewable Natural Gas, representing industry stakeholders, petitioned to overturn these changes, arguing that the new rules were too rigid and burdensome.The case was reviewed by the United States Court of Appeals for the District of Columbia Circuit. The Coalition argued that the EPA lacked authority to regulate biogas producers and that the new requirements were arbitrary and capricious. They also claimed procedural violations in the rulemaking process. The EPA defended its regulations, stating that they were necessary to ensure compliance with renewable fuel standards and to prevent fraud and double counting.The Court of Appeals found that the EPA acted within its authority under the Clean Air Act to regulate biogas producers and that the new rules were reasonable and supported by substantial evidence. The court also held that the EPA had followed proper procedures in adopting the rule. The court denied the Coalition's petition for review, upholding the EPA's updated regulations. The main holding was that the EPA's modifications to the biogas-derived renewable fuel regulations were reasonable and necessary to ensure compliance with renewable fuel standards and to prevent fraud. View "Coalition for Renewable Natural Gas v. EPA" on Justia Law

by
Healthy Gulf and other environmental groups challenged the Federal Energy Regulatory Commission's (FERC) decision to authorize the construction and operation of liquefied natural gas (LNG) facilities in southwestern Louisiana. They argued that FERC did not properly address certain requirements under the National Environmental Policy Act (NEPA) and the Natural Gas Act (NGA). Specifically, they contended that FERC inadequately explained its failure to determine the environmental significance of the project's greenhouse gas (GHG) emissions and failed to adequately assess the cumulative effects of the project's nitrogen dioxide (NO2) emissions. However, they acknowledged that FERC did consider alternatives to the project.The Commission had issued a final Environmental Impact Statement (FEIS) and authorized the project, finding it environmentally acceptable and consistent with the public interest. Petitioners requested a rehearing, which was deemed denied by operation of law when FERC did not respond timely. They then sought review from the United States Court of Appeals for the District of Columbia Circuit.The United States Court of Appeals for the District of Columbia Circuit found that FERC inadequately explained its failure to determine the significance of the project's GHG emissions and failed to properly assess the cumulative effects of the project's NO2 emissions. The court noted that FERC's reliance on the Significant Impact Levels (SILs) to assess cumulative effects was insufficient and that FERC did not adequately consider the significance of GHG emissions using available methodologies. However, the court upheld FERC's consideration of alternatives to the project, finding that FERC had provided sufficient reasoning for rejecting the proposed alternatives.The court granted the petitions in part, denied them in part, and remanded the case to FERC for further consideration without vacating the authorization order. The court instructed FERC to provide a more thorough explanation of its GHG emissions analysis and to properly assess the cumulative effects of NO2 emissions. View "Healthy Gulf v. FERC" on Justia Law

by
Range Resources-Appalachia, LLC (Range) and Columbia Gulf Transmission, LLC (Columbia Gulf) filed administrative complaints against Texas Eastern Transmission, LP (Texas Eastern) with the Federal Energy Regulatory Commission (FERC). Range, a natural gas producer, has long-term agreements with Texas Eastern and Columbia Gulf to transport gas through the Adair Interconnect. During two periods in 2019 and 2021, Texas Eastern's pipeline pressure was too low to move gas into Columbia Gulf's system, causing significant financial losses for Range. Petitioners sought FERC's intervention to require Texas Eastern to maintain higher pipeline pressures.FERC dismissed the complaints, finding that Texas Eastern had no minimum delivery pressure obligation. FERC also denied rehearing requests, stating that the complaints did not sufficiently demonstrate a violation of any pressure obligations. Petitioners argued that Texas Eastern failed to comply with its tariff and the Adair Interconnection Agreement, but FERC found these arguments procedurally and substantively insufficient. Additionally, FERC concluded that Texas Eastern's force majeure declaration in 2021 was irrelevant to the issue of reservation charge credits, as Columbia Gulf's refusal to accept gas was outside Texas Eastern's control.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. The court upheld FERC's dismissal, agreeing that the complaints did not adequately plead violations of the Texas Eastern Tariff or the Adair Interconnection Agreement. The court also found that FERC did not need to hold an evidentiary hearing on the issues of equal service and the force majeure declaration, as the written record was sufficient. The court denied the petitions for review, affirming FERC's orders. View "Columbia Gulf Transmission, LLC v. Federal Energy Regulatory Commission" on Justia Law

by
This case involves Duke Energy Progress, LLC, a grid operator, and two energy generation companies, American Beech Solar, LLC, and Edgecombe Solar LLC. The dispute centers around two orders by the Federal Energy Regulatory Commission (FERC). The first order rejected Duke Energy's agreement with American Beech Solar, which did not require Duke Energy to reimburse the cost of network upgrades. The second order accepted Duke Energy's agreement with Edgecombe Solar, which Duke Energy filed unsigned and under protest, and required Duke Energy to reimburse the cost of network upgrades.In the lower courts, FERC rejected the agreement with American Beech Solar, arguing that it was not just and reasonable because Duke Energy had threatened to delay construction of the upgrades, preventing American Beech from connecting to the grid, unless American Beech agreed to forego reimbursement. FERC also approved the agreement with Edgecombe Solar, despite Duke Energy's protest that it should not be required to pay reimbursements.In the United States Court of Appeals for the District of Columbia Circuit, the court denied Duke Energy's petitions for review. The court held that FERC's orders were not arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law. The court found that FERC's interpretation of its own regulation, Order 2003, was reasonable and entitled to deference. The court also found that FERC reasonably rejected Duke Energy's request for a deviation from the reimbursement requirement. Finally, the court held that FERC's orders did not violate the principle of treating similarly situated utilities differently without a reasonable justification. View "Duke Energy Progress, LLC v. Federal Energy Regulatory Commission" on Justia Law

by
The case involves Transcontinental Gas Pipe Line Company, LLC (Transco), a natural gas company that sought to abandon and expand its pipeline facilities in Pennsylvania and New Jersey. To do so, Transco needed a Certificate of Public Convenience and Necessity from the Federal Energy Regulatory Commission (FERC), which it obtained. However, the certificate was subject to conditions, including that Transco receive three additional permits from the Pennsylvania Department of Environmental Protection (PADEP). After receiving these permits, Transco began its pipeline project. However, three environmental advocates filed an administrative appeal with the Environmental Hearing Board (EHB) challenging PADEP's issuance of the permits. In response, Transco initiated a lawsuit in the District Court seeking to enjoin the administrative appeal, arguing that the Natural Gas Act preempts the state law allowing the appeal.The District Court rejected Transco's preemption arguments and denied its motion for a preliminary injunction. Transco appealed this decision to the United States Court of Appeals for the Third Circuit. The Court of Appeals affirmed the District Court's decision, finding that none of the theories of preemption advanced by Transco or the state agency applied in this case. The Court held that the Natural Gas Act does not expressly preempt administrative appeals to the EHB, nor does it field preempt such appeals. The Court also found that the possibility of multiple challenges in different fora to PADEP permitting decisions under the Clean Water Act for interstate natural gas pipelines does not impose an obstacle to the purposes of the Natural Gas Act. Therefore, the Court concluded that Transco's motion for a preliminary injunction was correctly denied. View "Transcontinental Gas Pipe Line Co LLC v. Pennsylvania Environmental Hearing Board" on Justia Law

by
The case involves a dispute over the award of black lung benefits to the surviving wife of the late Bruce E. Goode, who worked for American Energy as a coal miner and suffered from a severe chronic obstructive pulmonary disability. American Energy disputed the cause of his impairment, arguing that it was due to his long-term cigarette smoking, not his coal mine employment. An administrative law judge (ALJ) found that Mr. Goode’s disability arose from his coal mine employment and awarded black lung benefits. The Benefits Review Board affirmed the award.American Energy appealed, arguing that the ALJ applied an incorrect legal standard. The company contended that the Black Lung Benefits Act and its implementing regulations require a miner to prove that coal dust caused the lung disease or made it worse. American Energy argued that the ALJ reversed the burden of proof by finding that the company had not proven why Mr. Goode’s lung disease was not at least partially due to coal dust exposure.The United States Court of Appeals for the Fourth Circuit agreed that the ALJ applied the wrong legal standard in determining that Mr. Goode had legal pneumoconiosis. However, the court noted that the ALJ also concluded that Mr. Goode’s clinical pneumoconiosis entitled him to benefits. The court granted American Energy’s petition and vacated and remanded the Board’s order for further proceedings. View "American Energy, LLC v. Director, Office of Workers' Compensation Programs" on Justia Law

by
The case involves Ammonite Oil & Gas Corporation (Ammonite) and the Railroad Commission of Texas and EOG Resources, Inc. (EOG). Ammonite leases mineral rights beneath a riverbed from the State of Texas. EOG leases the minerals on the land adjoining the river on both sides. All the minerals in the area lie in a common subsurface reservoir. EOG's wells, however, do not reach the minerals beneath the riverbed. Ammonite argued that without pooling, its minerals are left stranded. Ammonite applied to the Railroad Commission for forced pooling under the Texas Mineral Interest Pooling Act (MIPA).The Railroad Commission rejected Ammonite's applications to force-pool the minerals beneath the river—which are not being produced—with those beside it—which are. The lower courts affirmed the Commission’s order. The Supreme Court of Texas also affirmed the lower courts' decisions but for different reasons than the court of appeals gave.The Supreme Court of Texas held that the Commission’s conclusion that “Ammonite failed to make a fair and reasonable offer to voluntarily pool as required by [MIPA Section] 102.013” is reasonable. The court also held that Ammonite has failed to show that forced pooling of its acreage with EOG’s wells is necessary to prevent its minerals from ultimately being lost. The court concluded that Ammonite applied for a share of EOG’s revenue without contributing to it and that the Commission’s conclusion that forced pooling would not prevent waste or protect correlative rights is not unreasonable. View "AMMONITE OIL & GAS CORPORATION v. RAILROAD COMMISSION OF TEXAS" on Justia Law

by
The case involves Husky Marketing & Supply Company and Phillips 66 Company, two customers of a crude-oil pipeline, who petitioned for review of orders issued by the Federal Energy Regulatory Commission (FERC) approving the pipeline’s application to charge market-based rates for its shipping services. The petitioners argued that the Commission adopted an arbitrary and capricious definition of the relevant geographic destination market for the pipeline’s services when analyzing whether it had market power.Previously, the matter was referred to an administrative law judge (ALJ) who, after an evidentiary hearing, found the correct destination market was the narrower Wood River market advanced by Husky and Phillips, rather than the broader St. Louis BEA Economic Area advanced by Marathon. Both Marathon and the Petitioners filed exceptions to the ALJ’s decision. The Commission unanimously reversed the ALJ’s decision and concluded the correct geographical destination market was Wood River together with Patoka, Illinois.The United States Court of Appeals for the District of Columbia Circuit reviewed the FERC’s orders under the “arbitrary and capricious” standard. The court held that the FERC did not act arbitrarily or capriciously when it concluded Wood River and Patoka together, rather than Wood River alone, represent the area in which a shipper may rationally look for transportation service. The court also held that the FERC was not required to perform any additional empirical analysis in this case. Therefore, the petitions for review were denied. View "Husky Marketing and Supply Company v. FERC" on Justia Law

by
The case involves an appeal by Marmen Inc., Marmen Énergie Inc., Marmen Energy Co., the Government of Québec, and the Government of Canada against a decision by the U.S. Department of Commerce. The Department of Commerce had imposed countervailing duties on imports of certain utility scale wind towers from Canada, arguing that the Canadian government had provided illegal subsidies to the producers and exporters of these towers.The case was initially reviewed by the United States Court of International Trade, which upheld the Department of Commerce's decision. The appellants then appealed to the United States Court of Appeals for the Federal Circuit.The appellants argued that the Department of Commerce had erred in its assessment of three government programs and its computation of the sales denominator used to calculate the subsidy rate. They contended that the subsidy rate should have been de minimis, meaning it was too trivial or minor to merit consideration.The Court of Appeals for the Federal Circuit affirmed the judgment of the U.S. Court of International Trade, ruling that the Department of Commerce's determination was supported by substantial evidence and was in accordance with the law. The court rejected the appellants' arguments, finding that the Department of Commerce had reasonably determined that the auditor's adjustment was unreliable, and that the three subsidy programs at issue did provide countervailable subsidies. View "GOVERNMENT OF QUEBEC v. US " on Justia Law