Rocky Mountain Farmers Union v. Corey
Plaintiffs challenged California Air Resources Board regulations regarding the first Low Carbon Fuel Standard (LCFS), which went into effect in 2011; the LCFS as amended in 2012; and the LCFS which replaced the first LCFS in 2015. The Ninth Circuit held that plaintiffs' challenges to previous versions of the LCFS have been made moot by their repeal. The panel affirmed the dismissal of plaintiffs' remaining claims against the present version of the LCFS as largely precluded by the panel's decision in Rocky Mountain Farmers Union v. Corey, 730 F.3d 1070 (9th Cir. 2013). The panel also held that plaintiffs' extraterritoriality claims against the 2015 LCFS were precluded by the law of the case and by recent circuit precedent in Am. Fuel & Petrochemical Mfrs. v. O'Keeffe, 903 F.3d 903 (9th Cir. 2018). Finally, the LCFS did not facially discriminate against interstate commerce in its treatment of ethanol and crude oil, and did not purposefully discriminate against out-of-state ethanol. View "Rocky Mountain Farmers Union v. Corey" on Justia Law
North Carolina v. FERC
The DC Circuit denied North Carolina's petition for review of FERC's orders involving the relicensing of the Yadkin Hydroelectric Project No. 2197. North Carolina alleged that the license applicant, Alcoa, misrepresented its plans to discontinue the use of project power for industrial production at Badin Works, a major source of employment in the state.The court held that substantial evidence supported FERC's decision and contradicted the existence of any deficiencies or deception in Alcoa's application. In this case, Alcoa disclosed the curtailment of industrial production at Badin Works every step of the way, from its initial filing of intent to relicense, through its various correspondences with FERC, to the license application itself. Furthermore, nothing in the record demonstrated that Alcoa had any nefarious intent to deceive FERC or the public at large. The court also held that North Carolina's recapture proposal lacked any basis in the law. Finally, the court held that, while the loss of jobs caused by the permanent closure of Badin Works did affect public interest, FERC had already accounted for its impact. View "North Carolina v. FERC" on Justia Law
San Diego Gas & Electric Co v. FERC
The DC Circuit denied SDG&E's petition for review of FERC's declaratory order applying FERC's cancelled or abandoned electricity transmission facilities incentive, 18 C.F.R. 35.35(d)(1)(vi) (Abandonment Incentive), only prospectively, to investments that had yet to occur. Determining that it had jurisdiction over the appeal, the court agreed with the Commission's finding that SDG&E failed to establish the requisite nexus between the Abandonment Incentive and costs it already incurred before it obtained the declaratory order. The court held that the Commission's finding was supported by substantial evidence and its approach comported with both the Federal Power Act and the Incentive Rule. Furthermore, the court found SDG&E's several objections unpersuasive. View "San Diego Gas & Electric Co v. FERC" on Justia Law
Colorado Oil & Gas Conservation Commission v. Martinez
The issue this case presented for the Colorado Supreme Court's review centered on whether the Colorado Oil and Gas Conservation Commission properly declined to engage in rulemaking to consider a rule by Respondents, a group of youth activists who proposed a rule that, among other things, would have precluded the Commission from issuing any permits for drilling oil and gas wells “unless the best available science demonstrates, and an independent, third-party organization confirms, that drilling can occur in a manner that does not cumulatively, with other actions, impair Colorado’s atmosphere, water, wildlife, and land resources, does not adversely impact human health, and does not contribute to climate change.” The Commission declined to engage in rulemaking to consider this proposed rule because, among other things: (1) the rule would have required the Commission to readjust the balance purportedly crafted by the General Assembly under the Act and conditioned new oil and gas drilling on a finding of no cumulative adverse impacts, both of which the Commission believed to be beyond its statutory authority; and (2) the Commission was already working with the Colorado Department of Public Health and Environment (“CDPHE”) to address the concerns to which the rule was directed and other Commission priorities took precedence over the proposed rulemaking at this time. Respondents challenged the Commission’s ruling in the Denver District Court, but that court ultimately upheld the Commission’s decision. Respondents appealed, and, in a split, published decision, a division of the court of appeals reversed the district court’s order. The Supreme Court concluded the Commission properly declined to engage in rulemaking to consider Respondents' proposed rule: (1) deferring to the agency's decision; (2) finding the Commission correctly determined that, under the applicable language of the Act, it could not properly adopt the rule proposed by Respondents; and (3) the Commission reasonably relied on the facts that it was already working with the CDPHE to address the concerns underlying Respondents’ proposed rule and that other Commission priorities took precedence at this time. View "Colorado Oil & Gas Conservation Commission v. Martinez" on Justia Law
Ex parte Alabama Surface Mining Commission.
The Alabama Surface Mining Commission ("the Commission") and Black Warrior Minerals, Inc. ("Black Warrior"), separately petitioned the Alabama Supreme Court for a writ of mandamus to direct the Jefferson Circuit Court to dismiss the underlying action seeking judicial review of the Commission's issuance of a surface-coal-mining permit to Black Warrior, or, in the alternative, to transfer the action to the Walker Circuit Court. The underlying action was filed by respondents, John Crane, Dan Jett, and Linda Jett ("the property owners"), who owned property near the location that was the subject of the permit. The Supreme Court found that when originally enacted, the Alabama Surface Mining Act did not include a venue provision. Alabama law was amended to specify that the proper venue for judicial review of a final Commission decision was "in the circuit court of the county in which the commission maintains its principal office." Under the plain language of the applicable statute, the only proper venue for the property owners' action was the Walker County circuit court. The property owners contended that, at the time they commenced their appeal with the Jefferson Circuit Court, the 2015 amendment to the applicable statute was not effective and the earlier version applied. Finding that the 2015 statute was properly enacted, the Supreme Court held "the effective date for such a change in state law should be the date determined by the Alabama Legislature, not the date of approval by the [Office of Surface Mining Reclamation and Enforcement]," thus the Commission and Black Warrior demonstrated a clear legal right to have their underlying action transferred to the Walker Circuit Court. View "Ex parte Alabama Surface Mining Commission." on Justia Law
Exelon Corp. v. FERC
Petitioner, owner of a number of electric generation resources in New England, challenged FERC's adoption of changes to the Transmission, Markets, and Services Tariff proposed by the Independent System Operator for New England (ISO-NE). The DC Circuit held that the parties' dispute may be illusory and thus remanded the record for the agency to sort out what it really means. In this case, at oral argument, counsel for FERC suggested that FERC interpreted the tariff rules in a way that largely squares with Exelon's view of its rights. View "Exelon Corp. v. FERC" on Justia Law
PA Independent Oil & Gas Assoc. v. PUC
The issue presented to the Pennsylvania Supreme Court in this appeal centered on whether producers of natural gas from certain vertical wells were subject to assessment of a yearly impact fee established by Chapter 23 of the Pennsylvania Oil and Gas Act (“Act 13”). The vertical wells that at issue used the hydraulic fracturing process ("fracking") to extract natural gas through a vertical well bore from Marcellus Shale. Specifically, the issue centered on whether an impact fee would be assessed whenever a vertical well’s production exceeded an average of 90,000 cubic feet of natural gas per day for even one month of the year, or whether the well must exceed this production threshold in every month of the year, for the fee to be imposed. After careful review, the Supreme Court concluded that, under the relevant provisions of Act 13, the impact fee would be imposed on such wells if their production exceeds 90,000 cubic feet of natural gas per day for even one month of the year, as found by the Public Utility Commission (“PUC”). Therefore, the Court reversed the Commonwealth Court’s order, which had reversed the PUC; the PUC's order was reinstated. View "PA Independent Oil & Gas Assoc. v. PUC" on Justia Law
County of Butte v. Dept. of Water Resources
The Department of Water Resources (DWR) applied to the Federal Energy Regulatory Commission (FERC or Commission) to extend its federal license to operate Oroville Dam and its facilities as a hydroelectric dam (referred to as the Oroville Facilities Project, Project, Settlement Agreement or "SA"). The plaintiffs brought this action in the superior court to stay the license procedure on the premise the environmental effects of relicensing the dam concern the operation of the dam and that jurisdiction to review the matter lies in the state courts pursuant to the California Environmental Quality Act. They claimed that a CEQA document offered to support the DWR’s application to FERC failed to consider the impact of climate change on the operation of the dam for all the purposes served by the dam. The superior court dismissed the complaint on the ground that predicting the impact of climate change is speculative. The plaintiffs appealed. A federal license is required by the Federal Power Act for the construction and operation of a hydroelectric dam. The license is issued by FERC. With one relevant exception, the FPA occupies the field of licensing a hydroelectric dam and bars review in the state courts of matters subject to review by FERC. Plaintiffs did not seek federal review as required by 18 C.F.R part 4.34(i)(6)(vii)(2003). The Court of Appeal concluded it lacked jurisdiction to hear this case. It returned the case to the trial court with an order to dismiss. View "County of Butte v. Dept. of Water Resources" on Justia Law
In re Application of Ohio Power Co.
The Supreme Court dismissed the appeal brought by the Office of Ohio Consumers’ Counsel (OCC) and the Ohio Manufacturers’ Association Energy Group (OMAEG) challenging the Public Utility Commission’s decision to approve the third electric-security plan (ESP) of Ohio Power Company, holding that OCC and OMAEG failed to demonstrate prejudice or harm caused by the ESP order.On appeal, OCC and OMAEG argued that the Commission’s approval of the Power Purchase Agreement Ride as a component of the ESP was reversible error. The Supreme Court dismissed the appeal, holding (1) OCC failed to demonstrate that ratepayers suffered actual harm or prejudice from the ESP order; and (2) this Court declines to address the claims that ratepayers were at risk of imminent or future harm rising from the ESP order. View "In re Application of Ohio Power Co." on Justia Law
In re Application of Ohio Power Co.
The Supreme Court affirmed the order of the Public Utilities Commission that approved a charge referred to as the Power Purchase Agreement (PPA) Rider as a component of Ohio Power Company’s third electric-security plan (ESP), holding that the order was not unlawful or unreasonable.Specifically, the Court held (1) the PPA Rider did not recover unlawful transition revenue; (2) the challenges to the Commission’s approval of the PPA Rider under the ESP statute, Ohio Rev. Code 4928.143, were without merit; (3) the challenges to the Commission’s approval of the joint stipulation to resolve the issues in the PPA Rider case failed; and (4) the Commission complied with Ohio Rev. Code 4903.09 when it approved the Ohio Valley Electric Corporation-only PPA Rider. View "In re Application of Ohio Power Co." on Justia Law