Justia Energy, Oil & Gas Law Opinion Summaries

Articles Posted in U.S. Court of Appeals for the District of Columbia Circuit
by
Energy Harbor, LLC, the owner and operator of the W.H. Sammis power plant, was assessed $12 million in penalties by PJM Interconnection, L.L.C. for failing to comply with PJM’s Tariff during a major winter storm in December 2022. Energy Harbor contested these penalties, arguing that the penalties were inconsistent with the terms of the Tariff, particularly the exception for maintenance outages. The Federal Energy Regulatory Commission (FERC) denied Energy Harbor’s complaint, leading Energy Harbor to petition for judicial review.The Federal Energy Regulatory Commission (FERC) reviewed Energy Harbor’s complaint and found that PJM had correctly interpreted the Tariff and calculated the penalties. FERC concluded that the maintenance outage at the Sammis Plant was not the sole cause of the performance shortfall, as the plant had sufficient capacity to meet its commitments but failed due to forced outages. Energy Harbor’s request for rehearing was denied by operation of law.The United States Court of Appeals for the District of Columbia Circuit reviewed the case and upheld FERC’s decision. The court agreed with FERC’s interpretation of the Tariff, stating that PJM correctly evaluated whether the maintenance outage was the sole cause of the performance shortfall. The court found that the Sammis Plant had enough installed capacity to meet its expected performance during the emergency, and the forced outages were also causes of the shortfall. The court also rejected Energy Harbor’s argument that the penalty exception should be assessed for each generating unit, affirming that the entire Sammis Plant was the resource at issue. Consequently, the court denied Energy Harbor’s petition for review. View "Energy Harbor, LLC v. FERC" on Justia Law

by
A regional transmission organization, Southwest Power Pool, sought to integrate the City of Nixa's transmission assets into its Zone 10 infrastructure. This integration would spread the costs of the Nixa Assets across all Zone 10 customers. Several nearby cities and utilities objected, arguing that they would bear unjustified costs without receiving corresponding benefits. They took their objections to the Federal Energy Regulatory Commission (FERC).FERC initially found insufficient evidence to determine whether the cost shift was justified and remanded the case for further proceedings. After a second hearing, an administrative law judge concluded that the integration was just and reasonable, providing incremental benefits such as improved reliability and power support for all Zone 10 customers. FERC affirmed this decision, finding that the integration's benefits justified the cost shift and denied the non-Nixa parties' request for rehearing.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. The court held that FERC's decision to analyze costs and benefits at the zonal level, rather than on a customer-by-customer basis, was reasonable. The court noted that requiring a hyper-granular approach would undermine the zonal system. The court also upheld FERC's consideration of unquantifiable systemwide benefits, such as improved integration and reliability, as sufficient to justify the cost shift. Finally, the court found that FERC's decision was supported by substantial evidence, including testimony and records indicating that the integration would benefit all Zone 10 customers.The court denied the petition for review, affirming FERC's decision to approve the integration and the associated cost allocation. View "Paragould Light & Water Commission v. FERC" on Justia Law

by
Michigan Electric Transmission Company (METC) owns a high-voltage transmission line with Michigan Public Power Agency (MPPA) and Wolverine Power Supply Cooperative. The case concerns the ownership of new transmission facilities, or "network upgrades," connecting a new solar generation park to the transmission line. METC claims exclusive ownership based on existing agreements, while MPPA and Wolverine disagree.The Federal Energy Regulatory Commission (FERC) reviewed the case and found that no agreement conclusively determined ownership rights. FERC declined to decide the ownership question, leading METC to petition for review.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. The court agreed with FERC's interpretation that the relevant agreements did not grant METC exclusive ownership of the network upgrades. The court found that the Styx-Murphy line qualifies as a "system" under the Transmission Owners Agreement (TOA), and since METC is not the sole owner, it cannot claim exclusive ownership. The court also found that the Styx-Murphy Agreements did not preclude MPPA and Wolverine from owning network upgrades.The court denied METC's petitions for review, upholding FERC's decision. View "Michigan Electric Transmission Company, LLC v. FERC" on Justia Law

by
Kimball Wind, LLC operates a wind facility in Nebraska, generating electricity transmitted on a network owned by the Western Area Power Administration (WAPA). Before operations began, WAPA determined that a substation expansion was necessary to safely transmit the facility's electricity. WAPA offered to cover part of the expansion costs, requiring Kimball Wind to pay the rest. Kimball Wind agreed under protest, believing WAPA wrongfully made it responsible for most of the costs. Kimball Wind petitioned the Federal Energy Regulatory Commission (FERC) for an order directing WAPA to reimburse its contribution to the substation expansion.The Federal Energy Regulatory Commission determined that section 211A of the Federal Power Act does not provide for the relief sought by Kimball Wind. The Commission found that Kimball Wind did not seek an order for transmission services, which is the sole form of relief provided by section 211A. Kimball Wind then filed a request for rehearing, arguing that the order was internally inconsistent and unsupported by substantial evidence. The Commission denied the request for rehearing.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. The court agreed with the Commission that section 211A does not authorize the Commission to issue an order directing WAPA to reimburse Kimball Wind for its contribution to the substation expansion. The court found that Kimball Wind did not seek an order for transmission services, the only type of order the Commission may issue under section 211A. Consequently, the court denied the petition for review. View "Kimball Wind, LLC v. FERC" on Justia Law

by
The case involves the Federal Energy Regulatory Commission (FERC) extending the construction deadline for the Mountain Valley Pipeline, LLC (MVP) Southgate Project. Initially, FERC issued a certificate of public convenience and necessity for the Southgate Project in June 2020, setting a construction completion deadline of June 18, 2023. However, due to unresolved permitting issues for the Mainline, which Southgate extends from, the construction could not proceed as planned. MVP requested an extension shortly before the deadline, citing delays in Mainline permitting as the reason for not meeting the original deadline.The Commission granted MVP's extension request, finding that MVP had demonstrated good cause due to unavoidable circumstances, specifically the Mainline permitting delays. FERC also maintained that its previous assessments of market need and environmental impacts for the Southgate Project remained valid and did not require reevaluation.Eight environmental organizations petitioned for review, arguing that FERC's decision to extend the construction deadline and its refusal to revisit prior assessments were arbitrary and capricious. They contended that MVP had not made reasonable efforts to advance the Southgate Project and that the market need and environmental impact analyses were outdated.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. The court held that FERC reasonably found that MVP had satisfied the good cause standard for the extension, given the permitting and litigation delays with the Mainline. The court also upheld FERC's decision not to revisit its prior findings on market need and environmental impacts, concluding that the information presented by the petitioners did not constitute significant changes in circumstances. Consequently, the court denied the petitions for review. View "Appalachian Voices v. Federal Energy Regulatory Commission" on Justia Law

by
Entergy companies petitioned for review of three orders by the Federal Energy Regulatory Commission (FERC). FERC had rejected tariff changes proposed by Midcontinent Independent System Operator (MISO), arguing that the new tariff would grant Entergy excessive market power. Entergy contended that FERC’s decisions were arbitrary and capricious.The case was reviewed by the United States Court of Appeals for the District of Columbia Circuit. Entergy’s opening brief did not address the issue of standing, which is a jurisdictional prerequisite. This omission violated Circuit Rule 28(a)(7), which requires petitioners to set forth the basis for their claim of standing in their opening brief. As a result, Entergy forfeited any arguments in support of standing.The D.C. Circuit Court dismissed the petitions for review, stating that Entergy lacked standing. The court emphasized that Entergy’s failure to discuss standing in its opening brief constituted a forfeiture of the argument. Even if the court were to consider the standing arguments Entergy later advanced, the company did not demonstrate the necessary concrete, imminent, and redressable injury. The court concluded that dismissal was the appropriate consequence for Entergy’s failure to establish standing. View "Entergy Arkansas, LLC v. FERC" on Justia Law

by
The Alaska LNG Project sought authorization from the Department of Energy to export up to twenty million metric tons of liquefied natural gas (LNG) per year for thirty years. The Department initially authorized the Project to export LNG to free-trade countries in 2014 and later to non-free trade countries in 2015, subject to environmental review. In 2023, the Department issued a final order approving the Project’s export application, concluding that the approval was consistent with the public interest despite uncertainties regarding environmental impacts.The Federal Energy Regulatory Commission (FERC) had previously authorized the construction and operation of the Project’s facilities, including an 800-mile pipeline and associated infrastructure, after preparing an extensive environmental impact statement. The U.S. Court of Appeals for the District of Columbia Circuit upheld FERC’s compliance with the National Environmental Policy Act (NEPA) in Center for Biological Diversity v. FERC. The Department of Energy adopted FERC’s impact statement and issued its own supplemental environmental impact statement in response to Executive Order 13990.The United States Court of Appeals for the District of Columbia Circuit reviewed the Department of Energy’s final order. The court found that the Department had properly adopted FERC’s environmental impact statement and complied with NEPA. The court also upheld the Department’s finding of substantial uncertainty regarding the magnitude of environmental impacts, particularly greenhouse gas emissions and climate impacts, associated with the Project’s exports. The court concluded that the impacts of downstream emissions in foreign countries were not reasonably foreseeable and that the Department’s analysis was supported by substantial evidence.The court denied the petitions for review, affirming the Department of Energy’s authorization for the Alaska LNG Project to export LNG. View "Sierra Club v. DOE" on Justia Law

by
Driftwood Pipeline LLC sought approval from the Federal Energy Regulatory Commission (FERC) to build two new natural gas pipelines in southwestern Louisiana. FERC granted the approval, concluding that the project would serve a market need and that its benefits outweighed its adverse environmental impacts. Healthy Gulf and Sierra Club challenged this decision, arguing that FERC failed to comply with the National Environmental Policy Act (NEPA) and the Natural Gas Act.The Federal Energy Regulatory Commission (FERC) issued a Section 7 certificate to Driftwood Pipeline LLC, determining that the project was required by public convenience and necessity. FERC also published an environmental impact statement, concluding that the project would have some adverse environmental impacts but none that were significant. Healthy Gulf and Sierra Club requested a rehearing, which was deemed denied when FERC did not act on it. They then petitioned for review, raising challenges under NEPA and the Natural Gas Act.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. The court held that FERC adequately considered the environmental effects of the project, including its impact on greenhouse gas emissions, and found that FERC's refusal to characterize the significance of these emissions was reasonable. The court also found that FERC's determination of market need was supported by substantial evidence, including precedent agreements and an independent market study. The court concluded that FERC had properly balanced the project's benefits against its adverse effects and denied the petition for review. View "Healthy Gulf v. FERC" on Justia Law

by
Hecate Energy, LLC, a developer and operator of renewable power facilities, petitioned for review of two orders by the Federal Energy Regulatory Commission (FERC). These orders approved reforms proposed by PJM Interconnection, LLC, a regional transmission grid operator, to the criteria used for processing requests to connect new electricity sources to the grid. Hecate challenged the approval of a specific aspect of these reforms: the expedited processing of interconnection requests projected to incur upgrade costs of $5 million or less. Hecate argued that this cap was arbitrary and unduly discriminatory.The Federal Energy Regulatory Commission (FERC) approved PJM's proposed reforms, including the $5 million cap, and denied Hecate's request for rehearing. FERC justified the cap by stating that projects with upgrade costs of $5 million or less were simpler and quicker to process. Hecate then petitioned the United States Court of Appeals for the District of Columbia Circuit for review, arguing that the cap was not supported by substantial evidence and that FERC failed to consider alternative eligibility rules.The United States Court of Appeals for the District of Columbia Circuit dismissed Hecate's petitions for lack of standing. The court held that Hecate's injury was not redressable because vacating FERC's approval of the $5 million cap would not likely lead to the expediting of Hecate's project. The court reasoned that PJM had multiple options to address the alleged defect without necessarily including Hecate's project in the expedited process. Therefore, Hecate failed to demonstrate that its injury would be alleviated by the court's intervention. View "Hecate Energy LLC v. FERC" on Justia Law

by
Aclara Meters LLC owned the license for the Somersworth Hydroelectric Project on the Salmon Falls River between New Hampshire and Maine from 2016 to 2023. In 2019, Aclara sought to surrender its license to the Federal Energy Regulatory Commission (FERC). After conducting an environmental assessment, FERC authorized the surrender in 2023. American Whitewater, a conservation organization, requested a rehearing, arguing that two dams from the Project should be removed as a condition of surrender. FERC denied the request, leading Whitewater to petition the United States Court of Appeals for the District of Columbia Circuit for relief, claiming that FERC acted arbitrarily and capriciously under the Federal Power Act (FPA) and the National Environmental Policy Act (NEPA).The Commission's environmental assessment concluded that approving the surrender as proposed would not significantly affect the environment, thus an Environmental Impact Statement (EIS) was unnecessary. FERC found that removing the dams was unfeasible due to the local municipalities' reliance on the reservoir for water supply and other needs. The Commission also determined that the benefits of keeping the dams outweighed the environmental and recreational benefits of their removal. FERC's decision was based on the public interest, considering the water supply, firefighting needs, and potential impacts on local infrastructure.The United States Court of Appeals for the District of Columbia Circuit reviewed the case and denied Whitewater's petition for review. The court held that FERC's analysis was neither arbitrary nor capricious. The Commission reasonably determined that dam removal was unfeasible and appropriately assessed the public interest. The court found that FERC's decision to approve the license surrender without dam removal was supported by substantial evidence and consistent with its policies and precedents. View "American Whitewater v. FERC" on Justia Law