Justia Energy, Oil & Gas Law Opinion Summaries

Articles Posted in U.S. Court of Appeals for the District of Columbia Circuit
by
Entergy companies petitioned for review of three orders by the Federal Energy Regulatory Commission (FERC). FERC had rejected tariff changes proposed by Midcontinent Independent System Operator (MISO), arguing that the new tariff would grant Entergy excessive market power. Entergy contended that FERC’s decisions were arbitrary and capricious.The case was reviewed by the United States Court of Appeals for the District of Columbia Circuit. Entergy’s opening brief did not address the issue of standing, which is a jurisdictional prerequisite. This omission violated Circuit Rule 28(a)(7), which requires petitioners to set forth the basis for their claim of standing in their opening brief. As a result, Entergy forfeited any arguments in support of standing.The D.C. Circuit Court dismissed the petitions for review, stating that Entergy lacked standing. The court emphasized that Entergy’s failure to discuss standing in its opening brief constituted a forfeiture of the argument. Even if the court were to consider the standing arguments Entergy later advanced, the company did not demonstrate the necessary concrete, imminent, and redressable injury. The court concluded that dismissal was the appropriate consequence for Entergy’s failure to establish standing. View "Entergy Arkansas, LLC v. FERC" on Justia Law

by
Driftwood Pipeline LLC sought approval from the Federal Energy Regulatory Commission (FERC) to build two new natural gas pipelines in southwestern Louisiana. FERC granted the approval, concluding that the project would serve a market need and that its benefits outweighed its adverse environmental impacts. Healthy Gulf and Sierra Club challenged this decision, arguing that FERC failed to comply with the National Environmental Policy Act (NEPA) and the Natural Gas Act.The Federal Energy Regulatory Commission (FERC) issued a Section 7 certificate to Driftwood Pipeline LLC, determining that the project was required by public convenience and necessity. FERC also published an environmental impact statement, concluding that the project would have some adverse environmental impacts but none that were significant. Healthy Gulf and Sierra Club requested a rehearing, which was deemed denied when FERC did not act on it. They then petitioned for review, raising challenges under NEPA and the Natural Gas Act.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. The court held that FERC adequately considered the environmental effects of the project, including its impact on greenhouse gas emissions, and found that FERC's refusal to characterize the significance of these emissions was reasonable. The court also found that FERC's determination of market need was supported by substantial evidence, including precedent agreements and an independent market study. The court concluded that FERC had properly balanced the project's benefits against its adverse effects and denied the petition for review. View "Healthy Gulf v. FERC" on Justia Law

by
Hecate Energy, LLC, a developer and operator of renewable power facilities, petitioned for review of two orders by the Federal Energy Regulatory Commission (FERC). These orders approved reforms proposed by PJM Interconnection, LLC, a regional transmission grid operator, to the criteria used for processing requests to connect new electricity sources to the grid. Hecate challenged the approval of a specific aspect of these reforms: the expedited processing of interconnection requests projected to incur upgrade costs of $5 million or less. Hecate argued that this cap was arbitrary and unduly discriminatory.The Federal Energy Regulatory Commission (FERC) approved PJM's proposed reforms, including the $5 million cap, and denied Hecate's request for rehearing. FERC justified the cap by stating that projects with upgrade costs of $5 million or less were simpler and quicker to process. Hecate then petitioned the United States Court of Appeals for the District of Columbia Circuit for review, arguing that the cap was not supported by substantial evidence and that FERC failed to consider alternative eligibility rules.The United States Court of Appeals for the District of Columbia Circuit dismissed Hecate's petitions for lack of standing. The court held that Hecate's injury was not redressable because vacating FERC's approval of the $5 million cap would not likely lead to the expediting of Hecate's project. The court reasoned that PJM had multiple options to address the alleged defect without necessarily including Hecate's project in the expedited process. Therefore, Hecate failed to demonstrate that its injury would be alleviated by the court's intervention. View "Hecate Energy LLC v. FERC" on Justia Law

by
Aclara Meters LLC owned the license for the Somersworth Hydroelectric Project on the Salmon Falls River between New Hampshire and Maine from 2016 to 2023. In 2019, Aclara sought to surrender its license to the Federal Energy Regulatory Commission (FERC). After conducting an environmental assessment, FERC authorized the surrender in 2023. American Whitewater, a conservation organization, requested a rehearing, arguing that two dams from the Project should be removed as a condition of surrender. FERC denied the request, leading Whitewater to petition the United States Court of Appeals for the District of Columbia Circuit for relief, claiming that FERC acted arbitrarily and capriciously under the Federal Power Act (FPA) and the National Environmental Policy Act (NEPA).The Commission's environmental assessment concluded that approving the surrender as proposed would not significantly affect the environment, thus an Environmental Impact Statement (EIS) was unnecessary. FERC found that removing the dams was unfeasible due to the local municipalities' reliance on the reservoir for water supply and other needs. The Commission also determined that the benefits of keeping the dams outweighed the environmental and recreational benefits of their removal. FERC's decision was based on the public interest, considering the water supply, firefighting needs, and potential impacts on local infrastructure.The United States Court of Appeals for the District of Columbia Circuit reviewed the case and denied Whitewater's petition for review. The court held that FERC's analysis was neither arbitrary nor capricious. The Commission reasonably determined that dam removal was unfeasible and appropriately assessed the public interest. The court found that FERC's decision to approve the license surrender without dam removal was supported by substantial evidence and consistent with its policies and precedents. View "American Whitewater v. FERC" on Justia Law

by
Petitioners sought review of the Federal Energy Regulatory Commission's (FERC) grant of an abandonment incentive to ITC Midwest, LLC (ITC). This incentive allows ITC to recover 100% of its prudently incurred costs if a planned transmission project is abandoned for reasons beyond its control. Petitioners, a group of organizations whose members purchase electricity, argued that ITC's ownership of the project was uncertain due to ongoing litigation challenging the Iowa Right of First Refusal statute.The Federal Energy Regulatory Commission approved ITC's request for the abandonment incentive, finding that the project met the necessary criteria, including enhancing reliability and reducing congestion. Petitioners filed a protest, which FERC rejected, stating that regulatory or litigation uncertainty does not preclude granting an abandonment incentive. Petitioners then sought rehearing, which FERC also denied, reiterating that the approval was consistent with its precedent.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. The court determined that petitioners lacked Article III standing because they failed to show imminent injury from FERC's orders. The court noted that petitioners' claims of potential future higher rates were speculative and not concrete or imminent. The court also found that petitioners' interest in the proper application of the law and potential collateral estoppel effects did not constitute a cognizable injury. Consequently, the court dismissed the petition for lack of jurisdiction. View "Industrial Energy Consumers of America v. FERC" on Justia Law

by
Riverkeeper petitioned for review of FERC's Certificate of Public Convenience and Necessity conditionally approving the Leidy Project. The DC Circuit denied the petition and held that it had jurisdiction to consider Riverkeeper's challenge to the Certificate Order on the ground that FERC violated the sequencing requirement of the Clean Water Act (CWA) by issuing its Certificate Order before Pennsylvania issued its section 401 certification; the sequencing requirement of section 401 was not triggered because the Commission's conditional approval of the Leidy Project construction did not authorize any activity which might result in a discharge in navigable waters; the court need not decide whether the letter orders impermissibly approved activity that might have resulted in a discharge before Pennsylvania issued its section 401 certification; FERC did not violate the National Environmental Policy Act (NEPA) by misclassifying wetlands; even if FERC technically erred in some of its classifications, Riverkeeper has not shown any prejudice; and FERC's NEPA review of the Leidy Project's proposed gas flow velocities appeared to be fully informed and well-considered. View "Delaware Riverkeeper Network v. FERC" on Justia Law

by
Section 309 of the Federal Power Act (FPA), 16 U.S.C. 825h, vests the Commission with broad remedial authority, including the authority to grant recoupment when it is justified; Section 201(f) does not limit the authority of the Commission to grant relief under Section 309 with respect to matters that are beyond the strictures of Sections 201(f) and 205; and an order of recoupment, as distinguished from an order to refund under Section 205, is beyond the strictures of Sections 201(f) and 205. In this case, Chehalis sought relief from the Commission by filing a Motion for an Order Requiring Recoupment of Payments, but the Commission concluded that it could not order recoupment because the Commission's refund authority does not extend to exempt public utilities such as the Intervenor Bonneville. The DC Circuit held that the Commission erred when it held that it lacked the authority to grant the Order Requiring Recoupment where the Commission clearly had jurisdiction over the subject of this dispute and the Commission retained the authority to order Bonneville to return the funds when the agency acknowledged that its initial order was mistaken. The court granted in part and denied in part Chehalis's petitions for review, and remanded for further proceedings. View "TNA Merchant Projects v. FERC" on Justia Law

by
A district court has broad discretion to decide whether and when to grant an agency's request for a voluntary remand. But a voluntary remand is typically appropriate only when the agency intends to revisit the challenged agency decision on review. After the Department rejected Limnia's two loan applications, Limnia filed suit alleging that the Department's rejection of Limnia's applications was unlawful under the Administrative Procedure Act. The district court then granted the Department's voluntary remand request. The DC Circuit held that the district court erred by granting the Department's request for a voluntary remand in this case because the Department did not intend to revisit the original application decisions under review. Therefore, the DC Circuit reversed and remanded for further proceedings. View "Limnia, Inc. v. DOE" on Justia Law

by
Section 210 of the Public Utility Regulatory Policies Act of 1978 (PURPA), 16 U.S.C. 824a-3, seeks to reduce reliance on fossil fuels by increasing the number of energy-efficient cogeneration and small power-production facilities. Oregon implements its PURPA responsibilities largely through its Public Utility Commission (OPUC), which has directed utilities subject to its jurisdiction to draft off-the-shelf, standard-form power-purchase agreements that OPUC then reviews for compliance with PURPA. OPUC has approved two standard-form power-purchase agreements submitted by petitioner Portland General Electric. Petitioner PáTu Wind Farm, a six-turbine, nine-megawatt generator in rural Oregon, is classified under PURPA as a small power producer. This appeal stems from the parties' dispute over the nature of Portland General's purchase obligation. The Commission ruled that under PURPA, Portland General must purchase all of PáTu’s power, though it rejected PáTu’s insistence that Portland General do so by utilizing a technology known as dynamic scheduling. The court concluded that PáTu’s petition dealing exclusively with Portland's refusal to utilize dynamic scheduling is without merit. Accordingly, the court denied PáTu’s petition. The court dismissed Portland's petition challenging the Commission's ruling that it must purchase all of PáTu’s power for lack of jurisdiction because FERC's orders were advisory. View "Portland General Electric Comp v. FERC" on Justia Law

by
Transmissions Owners provide transmission services for customers in New England. Consumers, Massachusetts and various consumer-side stakeholders, filed suit under section 206 of the Federal Power Act (FPA), 16 U.S.C. 824e(a), alleging that Transmission Owners' base return on equity (ROE) had become unjust and unreasonable. At issue are FERC's orders in the section 206 proceeding. Both Transmission Owners and Customers filed petitions for review challenging whether FERC satisfied the statutory requirements under section 206 in setting a new ROE. The court explained that, to satisfy its dual burden under section 206, FERC was required to do more than show that its single ROE analysis generated a new just and reasonable ROE and conclusively declare that, consequently, the existing ROE was per se unjust and unreasonable. Therefore, the court concluded that, because FERC's single ROE analysis failed to include an actual finding as to the lawfulness of Transmission Owners' existing base ROE, FERC acted arbitrarily and outside of its statutory authority in setting a new base ROE for Transmission Owners. The court also concluded that FERC failed to provide any reasoned basis for selecting 10.57 percent as the new base ROE. Accordingly, the court granted the petitions for review, vacated FERC's orders, and remanded for further proceedings. View "Maine v. FERC" on Justia Law