Justia Energy, Oil & Gas Law Opinion Summaries

Articles Posted in Zoning, Planning & Land Use
by
Sunpin Energy Services, LLC and Ralph P. Lapinkas, Jr. sought to construct a large-scale ground-mounted solar energy system on a parcel of undeveloped, mostly forested land in Petersham, Massachusetts. Because the proposed site was outside the town’s designated solar electric overlay district, Sunpin applied for a special permit from the Zoning Board of Appeals. The project would require clearing trees from approximately 14.3 acres, and Sunpin secured an order of conditions from the town conservation commission under the Wetlands Protection Act. The permit application was denied after one of three board members voted against it, citing concerns about deforestation and referencing the town’s bylaw goals of maintaining the town’s beauty and proper land use.The plaintiffs challenged the board’s denial in the Land Court Department. The Land Court judge granted summary judgment in favor of the board, concluding that the board member properly applied the zoning bylaw criteria, including the protection of public health, safety, and welfare, and concerns about tree removal. The plaintiffs appealed, and the Massachusetts Appeals Court vacated the judgment, holding that the board’s decision was arbitrary and capricious, improperly favoring forest preservation over solar energy siting and relying on speculation about future development.The Supreme Judicial Court of Massachusetts reviewed the case and held that, under the Dover Amendment’s solar provision (G. L. c. 40A, § 3, ninth paragraph), municipalities must provide reasonable opportunities for solar energy systems and may not deny a special permit unless it is necessary to protect public health, safety, or welfare. The Court found that the denial, based on general concerns about tree cutting, amounted to a blanket prohibition in a town that is ninety-seven percent forested, which was improper. The Court vacated the Land Court’s judgment and remanded for further proceedings consistent with its opinion. View "Sunpin Energy Services, LLC v. Zoning Board of Appeals of Petersham" on Justia Law

by
A resident of Treasure County, Montana, submitted a petition for a citizen initiative proposing a county ordinance to establish a permitting process and regulatory standards for wind energy conversion systems (WECS) exceeding certain size thresholds. The ordinance sought to regulate various aspects of WECS, including setbacks, noise, wildlife impacts, and penalties for non-compliance, and would have required the county commissioners to administer and enforce the permitting regime. After the petition’s form was approved, the petitioner made minor revisions and resubmitted it.Following these events, the Board of County Commissioners of Treasure County filed a complaint in the Montana Sixteenth Judicial District Court, seeking a declaratory judgment that the proposed ordinance was invalid and unconstitutional. The County argued that specific Montana statutes—namely, Title 76, chapter 2—set forth exclusive processes and requirements for county land-use and zoning regulation, with which the proposed ordinance did not comply. The petitioner responded, generally denying the allegations and seeking a declaration that the ordinance was valid, or that invalid provisions could be severed.The District Court construed the parties’ motions for summary judgment as addressing the validity and constitutionality of the ordinance. It concluded that the ordinance was invalid under § 7-5-135, MCA, because it purported to regulate land use under the county’s general powers when specific statutes governed such regulations, and its provisions exceeded the county’s legislative authority. The court did not reach the constitutional question.On appeal, the Supreme Court of the State of Montana affirmed, holding that this particular proposed ordinance was invalid because it created a permitting and enforcement regime outside the authority delegated to the county by the Legislature. The court clarified that its holding was narrow and did not foreclose all citizen initiatives affecting land use, but only invalidated this ordinance as drafted. View "Treasure County v. Edlund" on Justia Law

by
SWN Production Company, LLC sought to drill multiple horizontal natural gas wells on a 301-acre tract within the City of Weirton, West Virginia. The City required a conditional use permit for oil and gas extraction under its zoning ordinance. SWN applied for such a permit, and the City’s Board of Zoning Appeals (BZA) held hearings where community members raised concerns about traffic, noise, and the effect on local development. The BZA denied SWN’s application, citing incompatibility with the City’s comprehensive development plan and other adverse impacts. Afterward, SWN obtained a drilling permit from the West Virginia Department of Environmental Protection (DEP).SWN filed two actions in the Circuit Court of Brooke County: a petition for a writ of certiorari challenging the BZA’s decision and a complaint seeking a declaration that the City’s zoning ordinance was preempted by state law, especially the Natural Gas Horizontal Well Control Act. The circuit court rejected SWN’s preemption argument and affirmed the BZA’s denial of the permit. SWN appealed both rulings to the Intermediate Court of Appeals of West Virginia (ICA). The ICA reversed the circuit court on the preemption issue, finding the City’s ordinance conflicted with state law, but dismissed SWN’s appeal of the certiorari ruling for lack of jurisdiction.The Supreme Court of Appeals of West Virginia reviewed both appeals. It held that there was no irreconcilable conflict between the City’s zoning ordinance and the state’s environmental statutes; rather, any overlap was incidental and not preempted. The Court reversed the ICA’s decision on preemption and reinstated the circuit court’s order dismissing SWN’s facial preemption challenge. Regarding the certiorari appeal, the Court affirmed the ICA’s dismissal, holding that the ICA lacked subject-matter jurisdiction to review extraordinary remedies such as certiorari. View "City of Weirton v. SWN Production Company, LLC" on Justia Law

by
A renewable energy developer was awarded a standard-offer contract in 2014 to build a solar facility in Bennington, Vermont, with a requirement to commission the project by 2016. The developer repeatedly sought and received extensions to this deadline, while simultaneously pursuing a certificate of public good (CPG), which is also required for construction. The Public Utility Commission (PUC) granted the CPG in 2018, but it was appealed, reversed, and ultimately denied on remand due to violations of local land conservation measures and adverse impacts on aesthetics. The Vermont Supreme Court affirmed the final CPG denial in 2023.While litigation over the CPG was ongoing, the developer continued to seek extensions of its standard-offer contract’s commissioning milestone. The fifth extension request, filed in 2021, asked for a deadline twelve months after the Supreme Court’s mandate in the CPG appeal. The hearing officer recommended granting it, but the PUC did not act on the request until 2024, by which time the developer’s CPG had been finally denied. The PUC dismissed the fifth extension request as moot, finding the contract had expired by its own terms. The PUC also denied the developer’s motion for reconsideration and a sixth extension request, on the same grounds.On appeal, the Vermont Supreme Court reviewed the PUC’s actions with deference, upholding its factual findings unless clearly erroneous and its discretionary decisions unless there was an abuse of discretion. The Court held that the PUC properly concluded the requested extension was moot, the contract was null and void by its terms, and there was no abuse of discretion. The Court also rejected arguments that the PUC’s actions were inconsistent with other cases or violated constitutional rights. The orders of the PUC were affirmed. View "In re Petition of Apple Hill Solar LLC" on Justia Law

by
South Branch Solar, L.L.C. sought approval to build a 130-megawatt solar-powered electric generation facility in Hancock County, Ohio, on approximately 700 acres of agricultural land. The project included solar panels, related equipment, and infrastructure. Local government officials and residents had varied reactions, with some supporting the facility for its economic and environmental benefits and others expressing concerns about impacts on land use, aesthetics, property values, wildlife, and local drainage systems. Travis Bohn, who lives near the project site, opposed the project and intervened in the proceedings.The Ohio Power Siting Board reviewed South Branch’s application, which included environmental studies and mitigation plans. After a public hearing and extensive opportunity for public input, the board staff recommended approval subject to 50 conditions. A joint stipulation was agreed to by South Branch, the board staff, the county commissioners, and the Ohio Farm Bureau Federation, but not by Bohn. Following an adjudicatory hearing, the Board issued an order granting the certificate. Bohn unsuccessfully sought rehearing, arguing that the Board misapplied statutory criteria, failed to require adequate wildlife and flood analysis, and improperly weighed local opposition and economic impacts.The Supreme Court of Ohio reviewed the Board’s order using a standard that allows reversal only if the order was unlawful or unreasonable. The court held that the Board’s determinations under R.C. 4906.10(A)(2), (A)(3), and (A)(6)—concerning environmental impact, minimum adverse impact, and public interest—were supported by sufficient probative evidence and complied with statutory and regulatory requirements. The court found no reversible error in the Board’s approval of South Branch’s application and affirmed the order granting the certificate. View "In re Application of S. Branch Solar, L.L.C." on Justia Law

by
Several individuals and organizations, including landowners and agricultural groups, challenged North Dakota statutes governing the underground storage of carbon dioxide and oil or gas, as well as laws permitting pre-condemnation surveys on private property. The plaintiffs own or represent owners of “pore space” in underground geological formations, which is used for carbon dioxide sequestration projects overseen by the North Dakota Industrial Commission (NDIC). The plaintiffs argued that the statutes authorizing amalgamation of pore space and pre-condemnation surveys violate constitutional protections against uncompensated takings and due process, and that certain statutory provisions constitute an improper delegation of legislative power.The District Court of Bottineau County granted summary judgment for the defendants, holding that most of the plaintiffs’ claims were barred by a six-year statute of limitations, as the claims were facial challenges to statutes enacted more than six years prior. The court also found that the plaintiffs’ challenge to the oil and gas storage law was not viable as a facial challenge because it depended on future actions and factual circumstances. The court did not reach the merits of the constitutional claims.The Supreme Court of North Dakota reviewed the case and held that the plaintiffs lacked standing to challenge the constitutionality of the provision allowing the NDIC to grant exceptions (N.D.C.C. § 38-22-03(7)) and the oil and gas storage amalgamation law (N.D.C.C. ch. 38-25), as they had not shown actual or threatened injury. However, the court found that the plaintiffs did have standing to challenge the carbon dioxide storage amalgamation provisions (N.D.C.C. ch. 38-22). The court ruled that the district court erred in dismissing these claims as time-barred, as the claims accrued when the NDIC acted under the statutes, not when the statutes were enacted. The court affirmed dismissal of the pre-condemnation survey law claims, but on the basis of binding precedent, not the statute of limitations. The case was affirmed in part, reversed in part, and remanded for further proceedings. View "Northwest Landowners Association v. State" on Justia Law

by
The case involves a dispute over the approval of a site certificate for the construction of a wind energy facility in Umatilla County, Oregon. The Energy Facility Siting Council granted the certificate to Nolin Hills Wind, LLC, despite the proposed facility not complying with a local siting criterion requiring a two-mile setback between any turbine and a rural residence. Umatilla County sought judicial review of the council's decision, arguing that the council should have required Nolin Hills to comply with the two-mile setback rule.The case was reviewed by the Supreme Court of the State of Oregon. The court noted that the council had the authority to approve the proposed energy facility despite its failure to comply with the two-mile setback rule. The court also noted that the council had the authority to approve the proposed facility even if it did not pass through more than three land use zones and even if it did not comply with all of the county’s recommended substantive criteria.The Supreme Court of the State of Oregon affirmed the council's decision, concluding that the council was authorized to issue a site certificate for the proposed wind facility notwithstanding the failure of the proposed facility to comply with the two-mile setback rule. The court found that the council was not required to reject a proposed facility simply because it did not comply with a local criterion. The court also rejected the county's argument that the council erred in concluding that the proposed facility "does otherwise comply with the applicable statewide planning goals." View "Umatilla County v. Dept. of Energy" on Justia Law

by
The case involves Mojalaki Holdings, LLC and GSSG New Hampshire, LLC (the plaintiffs) who appealed a decision by the City of Franklin Planning Board (the Board) that denied their site plan application to install a solar panel array on a piece of land owned by Mojalaki. The proposed solar panel array required the installation of new utility poles and the removal of mature trees to ensure sufficient sunlight. The land, which was mostly open space and was once a golf course, did not have any specific ordinance language addressing solar panel arrays. The Board, after multiple hearings and a site visit, denied the application based on concerns raised by neighbors about the project's potential impact on the scenery, property values, and previous negative experiences with other solar projects in the city.The Board's decision was upheld by the Superior Court, which agreed with the Board's first and third reasons for denial, namely that the installation of new utility poles would create an industrial look out of place in the neighborhood, and that cutting down mature trees contradicted the purpose provisions. However, the Superior Court did not uphold the Board's second basis, that the solar panel array endangered or adversely impacted the residents, due to lack of supporting facts.The Supreme Court of New Hampshire reversed the lower court's decision, ruling that the Board could not rely solely on the purpose provisions to deny the application. The court found that the purpose provisions lacked sufficient specificity for site plan review and left the proposed project to be judged by the subjective views of the Board through ad hoc decision making. The court granted the plaintiffs a builder's remedy, allowing them to proceed with their development provided they comply with all other applicable regulations. View "Mojalaki Holdings v. City of Franklin" on Justia Law

by
Alliance Pipeline L.P. (“Alliance”) entered into contracts with four states (“State Agreements”) as well as contracts with individual landowners in order to build a natural gas pipeline. The contracts with landowners provide easements for the pipeline right-of-way. In 2018, some landowners on the pipeline right-of-way filed a class-action lawsuit against Alliance. After the class was certified, Alliance moved to compel arbitration for the approximately 73 percent of plaintiffs whose easements contain arbitration provisions. Alliance appealed, arguing the district court erred by not sending all issues to arbitration for the plaintiffs whose easements contain arbitration provisions.   The Eighth Circuit affirmed in part and reversed in part. The court explained that the district court that the damages issues are subject to arbitration for the plaintiffs whose easements contain an arbitration provision. Plaintiffs make two arguments against sending any issues to arbitration: (1) Plaintiffs’ claims cannot be within the scope of the arbitration provisions because the claims allege lack of compensation for “ongoing yield losses,” not “damages to crops” and (2) Plaintiffs’ claims arise under the State Agreements, which do not have arbitration provisions. The court found the arbitration agreements to be enforceable and to cover all issues. The court held that as to the arbitration class members, the claims should be dismissed without prejudice. As to the members of the class without arbitration provisions, the court saw no reason why these class members cannot proceed with the lawsuit in the normal course at the district court. View "H&T Fair Hills, Ltd. v. Alliance Pipeline L.P." on Justia Law

by
Three conservation groups challenged the U.S. Bureau of Land Management’s approval of Jonah Energy’s development project on state and federal land in Wyoming. The project was designed to drill exploratory wells on land for which Jonah possessed development rights. The conservation groups argued the district court erred in upholding the BLM’s approval under the National Environmental Protection Act and the Federal Land Polocy and Management Act. Specifically, they contended the BLM inadequately considered the impact of the project on the sage-grouse and pronghorn antelope migration and grazing patterns. The Tenth Circuit concluded the BLM adequately collected and considered information on the sage-grouse and pronghorn, and selected a development plan that met statutory requirements. View "Western Watersheds Project, et al. v. United States Bureau of Land Management, et al." on Justia Law