Justia Energy, Oil & Gas Law Opinion Summaries
Idaho Power v. New Energy Two
In 2010, Idaho Power entered into two Firm Energy Sales Agreements, one with New Energy Two, LLC, and the other with New Energy Three, LLC, under which Idaho Power agreed to purchase electricity from them that was to be generated by the use of biogas. The agreement with New Energy Two stated that the project would be operational on October 1, 2012, and the agreement with New Energy Three stated that the project would be operational on December 1, 2012. Both contracts were submitted for approval to the Idaho Public Utilities Commission, and were both approved on July 1, 2010. Each of the agreements contained a force majeure clause. By written notice, New Energy Two and New Energy Three informed Idaho Power that they were claiming the occurrence of a force majeure event, which was ongoing proceedings before the Public Utilities Commission. New Energy asserted that until those proceedings were finally resolved "the entire circumstance of continued viability of all renewable energy projects in Idaho is undecided"and that as a consequence "renewable energy project lenders are unwilling to lend in Idaho pending the outcome of these proceedings."Idaho Power filed petitions with the Commission against New Energy Two and New Energy Three seeking declaratory judgments that no force majeure event, as that term was defined in the agreements, had occurred and that Idaho Power could terminate both agreements for the failure of the projects to be operational by the specified dates. New Energy filed a motion to dismiss both petitions on the ground that the Commission lacked subject matter jurisdiction to interpret or enforce contracts. After briefing from both parties, the Commission denied New Energy's motion to dismiss. The Commission's order was an interlocutory order that is not appealable as a matter of right. New Energy filed a motion with the Supreme Court requesting a permissive appeal pursuant to Idaho Appellate Rule 12, and the Court granted the motion. New Energy then appealed. Finding no reversible error, the Supreme Court affirmed the Commission's order. View "Idaho Power v. New Energy Two" on Justia Law
Entergy Mississippi, Inc. v. Acey
A.A. was electrocuted while playing on the farmland of David and Sherry Melton. Riley Berry, who worked for the Meltons, had parked a cotton picker under an allegedly sagging power line, which was owned by Entergy Mississippi, Inc. Ultimately, A.A. climbed onto the cotton picker, touched the power line, and was electrocuted. At the time of the accident, A.A.'s mother, Mary Bethanne Acey, was en route to Moon Lake, in Coahoma County with her son and Charles Graves. A 911 dispatcher called Graves to inform him of the accident. Graves immediately turned the car around to proceed to the Meltons' home. Acey then spoke with the dispatcher, who explained the gravity of the situation to Acey and informed her that A.A. had been "shocked." Emergency medical responders arrived shortly after Acey's arrival. A.A. suffered severe burns to both of her arms and her hip. A.A. subsequently was airlifted to Le Bonheur Children's Hospital in Memphis, Tennessee, and was later transferred to Shriners Hospitals for Children in Cincinnati, Ohio, which specializes in treating burn patients. Thereafter, Acey commenced legal action on behalf of A.A., and individually, against defendants Entergy, David and Sherry Melton, Melton Farms, Mary Mac, Inc., and Norfleet Investments, LP. Defendants settled all claims on behalf of A.A. Regarding Acey's individual bystander claims for emotional distress, Entergy moved for summary judgment and moved to strike the affidavits of Acey and Dr. William Hickerson. The trial court subsequently denied each motion. According to the trial court, based on the nature of A.A.'s injuries, this case "cries out for the expansion of" the factors provided by the California Supreme Court in "Dillon [v. Legg," 441 P. 2d 912, 920 (Cal. 1968)], adopted by the Mississippi Supreme Court in "Entex, Inc. v. McGuire,"(414 So. 2d 437 (Miss. 1982)). Thereafter, Entergy was granted interlocutory appeal. Because the Mississippi Court found that Entergy's motion for summary judgment should have been granted, the Court reversed and remanded the case for further proceedings. View "Entergy Mississippi, Inc. v. Acey" on Justia Law
SC Energy Users Committee v. SCE&G
Appellants the South Carolina Energy Users Committee (the SCEUC) and the Sierra Club appealed orders of the Public Service Commission that approved Respondent South Carolina Electric & Gas's (SCE&G) application for updated capital cost and construction schedules, pursuant to the Base Load Review Act, (the BLRA). The issues this case presented for the Supreme Court's review was whether the Commission applied the correct section of the BLRA, and whether the Commission had to also consider the prudence of project completion at the update stage. Finding no reversible error in the Commission's orders, the Supreme Court affirmed. View "SC Energy Users Committee v. SCE&G" on Justia Law
Posted in:
Energy, Oil & Gas Law, Government & Administrative Law
Passadumkeag Mountain Friends v. Bd. of Envtl. Prot.
Passadumkeag Windpark, LLC (PW) sought approval to construct a wind farm on property owned by Penobscot Forest, LLC (PF) located in Grand Falls Township. The Department of Environmental Protection denied the requested permit. On review, the Board of Environmental Protection (Board) granted the permit. Passadumkeag Mountain Friends (PMF), a Maine nonprofit corporation, and Alexander and Rhonda Cuprak appealed. The Supreme Court affirmed the decision of the Board, holding (1) the decision of the Board was operative for purposes of appellate review; (2) the Board’s findings and conclusion were supported by substantial evidence in the record; and (3) certain communications between the Board, PW, and PF during the application process did not affect the Cupraks’ due process rights. View "Passadumkeag Mountain Friends v. Bd. of Envtl. Prot." on Justia Law
Posted in:
Energy, Oil & Gas Law, Environmental Law
Olympia Minerals, LLC v. HS Resources, Inc.
The issue this case presented to the Supreme Court centered on the lower courts’ interpretation of portions of a written mineral agreement. The agreement was prepared by a mineral leaseholder and ostensibly conveyed to an exploration company an “exclusive option to sublease” at least 15 percent of the leaseholder’s mineral rights. The lower courts interpreted the agreement as imposing an obligation on the exploration company to execute the sublease rather than simply allowing the exploration company the right to execute the sublease. Because the exploration company did not execute such a sublease, the lower courts awarded damages to the leaseholder for breach of contract. When the Court granted certiorari review, the lower courts had awarded to the leaseholder other damages, related to the exploration company’s obligation to execute a mineral sublease. The Supreme Court determined that the lower courts erred in ruling that the exploration company was obligated by the agreement to sublease mineral rights. Instead, the Court found the agreement afforded the exploration company a non-binding option to sublease (for which the exploration company paid $1.4 million), but that if the exploration company exercised the non-binding option, it was then obligated to sublease at least 15 percent of the leaseholder’s rights described in the agreement. Accordingly, the damage award on the breach of contract claim for failing to sublease at least 15 percent of the leaseholder’s mineral rights was reversed. However, the Court also found the exploration company breached its obligation to complete a seismic survey, and the Court affirmed the corresponding award of damage. Because the record did not support a finding that the exploration company acted in bad faith, we examine the effects of a contractual prohibition against consequential damages that the lower courts refused to apply based on those courts’ findings of bad faith. Because of the court of appeal's error, any meaningful review of the merits of the exploration company’s argument that its reconventional demand for improper use and sharing of its seismic data was improperly dismissed. The case was therefore remanded to the court of appeal the question of the propriety of that dismissal and, as that court then deems necessary, the question of whether the record supports the exploration company’s request for relief, or whether remanding to the district court for the taking of additional evidence is required. View "Olympia Minerals, LLC v. HS Resources, Inc." on Justia Law
Shieldalloy Metallurgical Corp. v. NRC
Shieldalloy, manufacturer of metal alloys in New Jersey, petitioned for review of the NRC's order reinstating the transfer of regulatory authority to the State of New Jersey under the Atomic Energy Act, 42 U.S.C. 2021. The order at issue addressed concerns raised by this Court in Shieldalloy II. The court concluded that the NRC's transfer of regulatory authority to New Jersey under section 2021 was not arbitrary or capricious because New Jersey's regulations are compatible with the NRC's regulations and its reading of 10 C.F.R. 20.1403(a). The NRC has rationally addressed concerns when it provided a textual analysis of section 20.1403 and explained how New Jersey's regulatory regime is adequate and compatible with the NRC's regulatory program. The order does not conflict with the NRC's prior interpretations or amount to a convenient, post hoc litigation position. Accordingly, the court denied the petition for review. View "Shieldalloy Metallurgical Corp. v. NRC" on Justia Law
Posted in:
Energy, Oil & Gas Law, Government & Administrative Law
Guerrero v. Pacific Gas & Elec. Co.
In 2010, a PG&E natural gas pipeline exploded in San Bruno, CA, causing death, great physical injuries, and extensive property damage. Governmental entities investigated the incident and PG&E’s business practices. The Public Utilities Commission retained an independent firm, Overland, to review PG&E’s gas transmission safety-related activities from a financial and regulatory audit prospective. Plaintiffs sued, seeking redress for PG&E’s alleged misappropriation of over $100 million in authorized rates that it should have used for safety-related projects. According to the complaint, PG&E misrepresented and concealed material facts when it used money collected from ratepayers to pay shareholders and provide bonuses to its executives instead of spending the money on infrastructure and safety measures. The complaint alleged that PG&E’s negligent handling of the pipe that exploded in San Bruno was unlawful and arose from PG&E’s corporate culture that valued profits over safety and that PG&E’s actions constituted an unlawful business practice under California Business and Professions Code section 17200. The superior court dismissed without leave to amend, finding the action barred by Public Utility Code section 1759 because it would interfere with the California Public Utilities Commission’s jurisdiction.” The appeals court affirmed. View "Guerrero v. Pacific Gas & Elec. Co." on Justia Law
Posted in:
Energy, Oil & Gas Law, Utilities Law
In re Application of Ohio Power Co.
Reporting that it suffered underrecovered transmission costs of $36 million during the period under review, the Ohio Power Company filed an application to recover the underrecovered transmission costs associated with providing transmission service to its standard-service-offer customers. The Public Utilities Commission approved the application, determining that Ohio Power could collect the underrecovered costs from both shopping and nonshopping customers. Industrial Energy Users-Ohio (IEU) appealed, arguing that the Commission abused its discretion by allowing Ohio Power to recover the underrecovered transmission costs from shopping customers. The Supreme Court affirmed, holding that the IEU did not meet its burden of demonstrating that the Commission’s orders were unjust, unreasonable, or unlawful. View "In re Application of Ohio Power Co." on Justia Law
Posted in:
Energy, Oil & Gas Law
Hiser v. XTO Energy, Inc.
Plaintiff filed suit against XTO, an oil and natural gas producer, for damages caused by vibrations from drilling operations. The jury returned a verdict for plaintiff and XTO moved for a new trial. The district court denied the motion and XTO appealed. The court concluded that, even assuming the jury's fracking and earthquake discussions included any extraneous matters under Federal Rule of Evidence 606(b)(2)(A), XTO has not shown a reasonable possibility that the discussions prejudiced it or altered the verdict. Therefore, the district court did not abuse its discretion in denying XTO's motion for a new trial. Further, the district court did not abuse its discretion in declining to subpoena the jury foreman under Moore v. Am. Family Mut. Ins. Co. Accordingly, the court affirmed the judgment. View "Hiser v. XTO Energy, Inc." on Justia Law
Posted in:
Civil Procedure, Energy, Oil & Gas Law
Mississippi Power Company v. Mississippi Public Service Comm’n
Mississippi Power Company filed documents asserting confidentiality with the Mississippi Public Service Commission related to a certificate-of-public-convenience-and-necessity proceeding in January 2009. In July 2012, Bigger Pie Forum (BPF) requested three of those documents from the Commission, and Mississippi Power sought a protective order. Following a hearing, the Chancery Court ordered that the documents be produced. Mississippi Power appealed. The Supreme Court affirmed the judgment of the Chancery Court to the extent that it ordered disclosure of the January 2009 gas price forecasts and CO2 cost assumptions that were similar in kind to those already published (by news media). However, the Court remanded this case to the Chancery Court to should consider the documents under seal and order that information pertaining to natural gas price forecasts and CO2 costs assumptions be produced by Mississippi Power. View "Mississippi Power Company v. Mississippi Public Service Comm'n" on Justia Law
Posted in:
Energy, Oil and Gas, Government Law