Justia Energy, Oil & Gas Law Opinion Summaries
Appalachian Power Co. v. State Corp. Comm’n
In this appeal, Appalachian Power Company (APCO) sought rate adjustment clause recovery of $33.3 million in environmental compliance costs that the State Corporation Commission denied. The Supreme Court reversed in part, affirmed in part, and remanded, holding (1) APCO was entitled to a rate adjustment clause for recovery of actual costs it directly incurred for environmental compliance in 2009 and 2010 but did not recover through its base rates, and the portion of the Commission's decision denying recovery of environmental compliance costs on the basis that those costs were connected with projects included in APCO's base rates which APCO had the opportunity to recover was reversed; and (2) the portion of the Commission's decision denying APCO recovery of environmental compliance costs alleged to be embedded in the capacity equalization charges APCO paid to its affiliates in 2009 and 2010 was affirmed. Remanded. View "Appalachian Power Co. v. State Corp. Comm'n" on Justia Law
Sierra Club v. Bd. of Oil, Gas, & Mining
The Board of Oil, Gas and Mining (Board) affirmed the approval by the Division of Oil, Gas and Mining (Division) of Alton Coal Development's (ACD) mining permit, which allowed ACD to conduct surface coal mining operations at the Coal Hollow Mine. Petitioners appealed, arguing that the Board erred in affirming ACD's permit because the permit application was deficient in several respects. The Supreme Court affirmed the Board's decision, holding (1) the Board properly concluded that the Division gave adequate consideration to cultural and historic resources in the adjacent area; (2) the Board properly concluded that the Division's cumulative hydrological Impact Assessment satisfied Utah's requirements; (3) the Board properly concluded that the hydrologic monitoring plan was adequate; and (4) therefore, the Board acted within its discretion in affirming the Division's conclusions that ACD's mining permit application satisfied all of the statutory and regulatory requirements. View "Sierra Club v. Bd. of Oil, Gas, & Mining" on Justia Law
W. Hardin County Consol. Indep. Sch. Dist. v. Poole
A school district (District) obtained an in rem delinquent property tax judgment against an oil and gas lease that Respondent owned and operated. Respondent did not appeal, and the District foreclosed its judgment lien on the leasehold, taking ownership. The Railroad Commission ordered Respondent to plug a well on the lease. Respondent did not comply, and the Commission plugged the well and brought an enforcement action in court to recover the costs of the operation and the penalty. Respondent and the Commission settled. Respondent then sued the District, alleging in part that the District's actions had resulted in a taking of his property requiring compensation. The trial court dismissed Respondent's action for want of jurisdiction, but the court of appeals reversed and remanded with respect to the takings claim. The Supreme Court reversed and dismissed the case, holding that the trial court correctly dismissed Respondent's case, as Respondent did not assert on appeal that the District took his property without compensation. View "W. Hardin County Consol. Indep. Sch. Dist. v. Poole" on Justia Law
Driver Pipeline Company, Inc., Buckley Equipment Services, Inc. v. Williams Transport, LLC
This interlocutory appeal stemmed from litigation concerning a contract dispute among Williams Transport, LLC (Williams Transport), Driver Pipeline Company, Inc. (Driver Pipeline), Buckley Equipment Services, Inc. (Buckley Equipment), and other unnamed defendants. Based on an arbitration clause in the contract, Driver Pipeline filed a motion to compel arbitration. The trial court denied the motion to compel arbitration as well as a subsequent motion for reconsideration. Driver Pipeline filed a petition for interlocutory appeal, which the Supreme Court accepted as a notice of appeal. Finding no error by the trial court in denying Driver Pipeline's motion to compel arbitration, the Supreme Court affirmed.
View "Driver Pipeline Company, Inc., Buckley Equipment Services, Inc. v. Williams Transport, LLC" on Justia Law
Vulcan Constr. Materials, L.P. v. Fed. Mine Safety & Health Review Comm’n
In 2010, Dunne filed a discrimination complaint under 30 U.S.C. 815(c)(2), with the Mine Safety and Health Administration, a division of the Department of Labor, claiming that had terminated his employment for engaging in protected safety-related. The Secretary of Labor determined that the complaint was not frivolously brought, and Vulcan agreed to a temporary (economic) reinstatement pending a determination on the merits. The Secretary later determined not to prosecute Dunne’s complaint before the Federal Mine Safety and Health Review Commission and Vulcan moved to dissolve the reinstatement order. The Commission denied Vulcan’s motion. The Seventh Circuit reversed, in favor of Vulcan, which argued that the term “complaint” in the statutory phrase “final order on the complaint,” refers only to the complaint brought by the Secretary after she determines that section 815(c) has been violated. Placement of the temporary reinstatement provision in the same subsection that describes the Secretary’s investigation, merits determination, and complaint, suggests that Congress meant for temporary reinstatement to continue only during the Secretary’s involvement. View "Vulcan Constr. Materials, L.P. v. Fed. Mine Safety & Health Review Comm'n" on Justia Law
Wenco v. EOG Resources, Inc.
Wenco, a North Dakota limited partnership, appealed a judgment quieting title to certain Mountrail County royalty and mineral interests in EOG Resources, Inc. ("EOG"), and QEP Energy Company ("QEP"), and dismissing Wenco's claims for conversion and unjust enrichment against EOG and QEP. Upon review, the Supreme Court concluded that the district court did not err in ruling as a matter of law that Wenco's interest bore the entire burden of a prior royalty interest conveyance in the subject property, that EOG and QEP did not waive their rights to claim the prior royalty interest conveyance burdened only Wenco's interest, and consequently, that Wenco had no viable claims against EOG and QEP for conversion and unjust enrichment.
View "Wenco v. EOG Resources, Inc." on Justia Law
In re Green Mountain Power Corp.
In consolidated appeals, the Lowell Mountains Group, Inc. (LMG), and the Towns of Albany and Craftsbury, challenged several Public Service Board orders related to the construction of a wind-electric-generation facility and associated facilities on Lowell Mountain in Lowell, Vermont. In May 2010, petitioners Green Mountain Power Corporation (GMP), Vermont Electric Cooperative, Inc. (VEC), and Vermont Electric Power Company, Inc. and Vermont Transco LLC (VELCO) requested a certificate of public good (CPG) to construct a wind-electric-generation facility on Lowell Mountain. On May 31, 2011, following testimony, site visits, a public hearing, and hearings, the Board issued a final order granting a CPG subject to forty-five conditions. Appellants and several other parties moved for reconsideration. On July 12, 2011, the Board modified its final order in certain respects. The Towns and LMG appealed that final order with modifications. The parties also raised compliance issues with the final order that the Board ultimately overruled. Upon review of the Board's orders, the Supreme Court found no abuse of discretion, and deferred to the Board's decisions with regard to the final order. Accordingly, the Court affirmed the Board.
View "In re Green Mountain Power Corp." on Justia Law
Northern Natural Gas Company v. L.D. Drilling, Inc., et al
In consolidated interlocutory appeals, Defendants-Appellants, natural gas producers with wells in south central Kansas, challenged a preliminary injunction enjoining them from further gas production from those wells. The district court entered the preliminary injunction after concluding there was a substantial likelihood that Plaintiff-Appellee Northern Natural Gas Co. would prevail on its state-law claim alleging that Defendants' natural gas production from these wells was an actionable nuisance because it was disrupting Northern's nearby underground storage of natural gas. The parties agreed that, to prevail on its nuisance claim, Northern needed to establish four things: 1) Defendants acted with the intent to interfere with Northern's use and enjoyment of the storage field; 2) there was some interference with the use and enjoyment of the Field of the kind Defendants intended; 3) that interference was substantial; and 4) the interference was of a such a nature, duration or amount as to constitute unreasonable interference with the use and enjoyment of the Field. Upon review, the Tenth Circuit affirmed, concluding that district court did not abuse its discretion in determining that there was a substantial likelihood that Northern could prove all four of those elements of its nuisance claim.
View "Northern Natural Gas Company v. L.D. Drilling, Inc., et al" on Justia Law
Alcoa Inc. v. BPA, et al
These consolidated petitions for review challenged a contract between the BPA and one of its long-time customers, Alcoa. BPA's preference customers and others filed this petition for review, requesting that the court hold that the contract was unlawful because it was inconsistent with the agency's statutory mandate to act in accordance with sound business principles. Petitioners claimed, among other things, that instead of entering into a contract to sell power to Alcoa at the statutorily required Industrial Firm power (IP) rate, BPA should sell to other buyers at the market rate. The court denied the petitions for review insofar as they pertained to the Initial Period. Because the potential for BPA and Alcoa to enter into the Second Period of the contract was no longer before the court, the court dismissed those portions of the petitions. Finally, the court held that because BPA relied on a categorical exclusion to the National Environmental Policy Act's (NEPA), 42 U.S.C. 4321-4347, requirements, declining to complete an Environmental Impact Statement was not arbitrary and capricious. Accordingly, the court denied petitioner's NEPA claim. View "Alcoa Inc. v. BPA, et al" on Justia Law
Kimzey, et al v. Flamingo Seismic
Plaintiffs brought a trespass action for damages to their land caused by Defendant's seismic exploration activities. Plaintiffs originally filed their action in Oklahoma state court, but Defendant removed it to federal district court based on diversity of citizenship. Defendant moved for summary judgment, arguing that it had permission to enter the property and conduct seismic testing from owners of the mineral rights and/or oil and gas leasehold rights, which lie under the surface estate of Plaintiffs' properties. The district court agreed and granted summary judgment for Defendant. Defendant then sought an award of attorney's fees pursuant to title 12, section 940(A) of the Oklahoma Code. The district court awarded Defendant $71,560 in attorney's fees as the prevailing party. Plaintiffs appealed both the summary judgment and the award of attorney's fees. Upon review, and "in the face of […] clear Oklahoma precedent," the Tenth Circuit concluded there was no merit to Plaintiffs' challenge to the grant of summary judgment, or their argument that section 940(A) did not apply to the facts of the case. Furthermore, the Court concluded the district court did not abuse its discretion in arriving at the final amount of the fees. Accordingly, the Court affirmed the district court's judgment.
View "Kimzey, et al v. Flamingo Seismic" on Justia Law