Public Citizen, Inc. v. Federal Energy Regulatory Commission
A 2015 auction for electrical capacity (commitments by power plants to provide electricity to utilities in the future) in Illinois produced a striking result. Capacity in neighboring regions uniformly sold for less than $3.50 per megawatt-day; in a region covering much of Illinois, the auction resulted in capacity prices of $150 per megawatt-day, a nearly ninefold increase from the prior year’s price of $16.75. The Federal Energy Regulatory Commission identified numerous problems with the existing auction rules and ordered that the rules be changed prospectively. FERC also launched an investigation into potential market manipulation in the 2015 Auction but later ruled that the identified flaws in the auction rules and the high price range those rules established, plus the allegations of market manipulation, did not call into question the 2015 Auction or the price it produced.The D.C. Circuit granted a petition for review in part. Under the Federal Power Act, 16 U.S.C. 791, FERC need not approve every auction price before it goes into effect. That is not what the market-based rate scheme requires. However, FERC’s analysis of the 2015 Auction, was arbitrary and capricious; it failed to adequately explain why the problems it identified in the existing auction rules affecting pricing— problems it ordered fixed going forward—did not also affect the fairness of the 2015 Auction. View "Public Citizen, Inc. v. Federal Energy Regulatory Commission" on Justia Law
Petro Harvester Oil & Gas Co., LLC, et al. v. Baucum
The crux of this interlocutory appeal was whether Plaintiffs, complaining of personal injury and property damage as a result of the alleged improper use of an oil-disposal well, had to exhaust their administrative remedies before the Mississippi State Oil and Gas Board (MSOGB) prior to proceeding on their common-law claims in the circuit court. Because the Mississippi Supreme Court determined the MSOGB could provide no adequate remedy for the Baucums’ personal-injury and property-damage claims, the Baucums were not required to exhaust administrative remedies before proceeding in the circuit court. View "Petro Harvester Oil & Gas Co., LLC, et al. v. Baucum" on Justia Law
Bearce v. Yellowstone Energy Development
Daniel and Debra Bearce appealed the district court’s grant of summary judgment in favor of Yellowstone Energy Development, LLC. In June 2006, representatives of a business entity that would eventually become Yellowstone went to the home of Daniel and Debra Bearce seeking to purchase 170 acres of land owned by the Bearces. Yellowstone successfully secured an exclusive option to purchase the land. In 2008, Yellowstone exercised its option to purchase the land, and the parties entered into a contract for deed. In 2009, Yellowstone and the Bearces modified the contract for deed to alter some of the payment terms. Both the original contract for deed and the 2009 modified contract for deed included the following term providing for the payment of a portion of the purchase price with “shares” of a contemplated ethanol plant. Yellowstone subsequently abandoned its plan to build an ethanol plant on the Bearces’ land. Yellowstone then negotiated a long-term lease with a third party to build an oil train loading facility on the Bearces’ land. In July 2010, Yellowstone sent a letter to the Bearces advising them $100,000 in “value” would be issued despite Yellowstone’s abandonment of the plan to build an ethanol plant. In December 2011, the Yellowstone Board of Directors approved a multiplier of three units per $1 invested for individuals who had provided initial cash investment in Yellowstone. The Bearces’ interest in Yellowstone was not given the 3:1 multiplier. Units representing ownership interest in Yellowstone were allocated and placed on a ledger sometime after December 4, 2012. After receiving a “unit ledger” indicating their interest in Yellowstone would not receive the 3:1 multiplier, the Bearces objected. Despite the objection, Yellowstone refused to apply the 3:1 multiplier to the Bearces’ interest in Yellowstone. The Bearces sued Yellowstone, asserting claims for breach of fiduciary duty, fraudulent inducement, and breach of contract. On appeal, the Bearces argued the district court erred in concluding Yellowstone did not owe them a fiduciary duty and that, if a duty was owed, the Yellowstone Board of Directors did not breach its fiduciary duty. Finding no reversible error, the North Dakota Supreme Court affirmed the district court. View "Bearce v. Yellowstone Energy Development" on Justia Law
Shell Oil Co. v. United States
In 1942-1943, the government contracted with the Oil Companies to rapidly expand aviation gas (avgas) production facilities and sell vast quantities of avgas to the government with an artificially low profit margin. The government assumed certain risks, agreeing to reimburse “any new or additional taxes, fees, or charges” which the Companies “may be required by any municipal, state, or federal law ... to collect or pay by reason of the production, manufacture, sale or delivery of the [avgas].” The increased production led to increased amounts of acid waste that overwhelmed existing reprocessing facilities. The Companies contracted to dispose of the acid waste at the McColl site in Fullerton, California.In 1991, the United States and California sued under the Comprehensive Environmental Response, Compensation, and Liability Act, 42 U.S.C. 9601, seeking to require the Companies to pay cleanup costs. The Ninth Circuit held that the government was 100% liable for the cost of cleaning up the benzol waste (about 5.5% of the waste) at the McColl site. The Companies have borne nearly all of the clean-up costs incurred since 1994; they submitted a contract termination claim, seeking reimbursement. The Claims Court ultimately found the government liable for all cleanup costs at the McColl site and awarded the Companies $99,509,847.32 for costs incurred through November 2015. The government paid. Remediation at McColl remains ongoing. The Companies sought damages incurred after November 2015. The Federal Circuit affirmed that the government is liable for those costs plus interest, rejecting arguments that res judicata bars the claims and that the Claims Court did not have jurisdiction under the Contract Settlement Act of 1944. View "Shell Oil Co. v. United States" on Justia Law
Vecinos para el Bienestar de la Comunidad Costera v. Federal Energy Regulatory Commission
The Federal Energy Regulatory Commission authorized the construction and operation of three liquified natural gas (LNG) export terminals on the shores of the Brownsville Shipping Channel in Cameron County, Texas, and the construction and operation of two 135-mile pipelines that will carry LNG to one of those terminals. Objectors filed challenges under the National Environmental Policy Act (NEPA), 42 U.S.C. 4332(2)(C); the Administrative Procedure Act (APA), and the Natural Gas Act (NGA), 15 U.S.C. 717b(a).The D.C. Circuit dismissed the petition concerning the Annova Terminal as moot, and granted the petitions with respect to the Rio Grande and Texas Terminals, without vacatur. The Commission’s analyses of the projects’ impacts on climate change and environmental justice communities were deficient under NEPA and the APA, and the Commission failed to justify its determinations of public interest and convenience under Sections 3 and 7 of the NGA. On remand, the Commission must explain whether 40 C.F.R. 1502.21(c) requires it to apply the social cost of carbon protocol or some other analytical framework, as “generally accepted in the scientific community” within the meaning of the regulation, and if not, why not. View "Vecinos para el Bienestar de la Comunidad Costera v. Federal Energy Regulatory Commission" on Justia Law
National Parks Conservation Ass’n v. Federal Energy Regulatory Commission
The Ninth Circuit concluded that the Commission did not act arbitrarily or capriciously, or abused its discretion, in denying the Association's motion to intervene in post-licensing deadline extension proceedings pertaining to the Eagle Mountain Pumped Storage Hydroelectric Project in California. The panel concluded that the Commission's interpretation of its Rule 214 deserves deference, and thus it may properly limit intervention in post-licensing proceedings. The panel further concluded that the Commission did not abuse its discretion in denying the Association's motion to intervene, where the only change sought by the licensee was an extension of time to commence construction.The panel also concluded that the Commission did not violate the Federal Power Act (FPA) in failing to provide public notice. In this case, based on longstanding interpretative precedent, the Commission determined that Eagle Crest's request was not a significant alteration of the License because the requested extensions were not inconsistent with the Project's plan of development or terms of the License. The panel concluded that the Commission's interpretation of Section 6 of the FPA is sufficiently persuasive as applied to deadline extension requests. Accordingly, the panel denied the petition for review. View "National Parks Conservation Ass'n v. Federal Energy Regulatory Commission" on Justia Law
PA. Environ. Defense Fd. v. Pennsylvania
The Pennsylvania Environmental Defense Foundation (“PEDF”) challenged amendments the Pennsylvania General Assembly made to the state Fiscal Code that diverted to the General Fund revenues generated from oil and gas leases on state forest and game lands. PEDF claimed the legislation was unconstitutional, violating the Environmental Rights Amendment (the “ERA”). When this case returned to the Commonwealth Court, the Pennsylvania Supreme Court held that the ERA created a constitutional public trust subject to private trust principles. Applying trust law, the Supreme Court determined that royalty revenue streams generated by the sale of gas extracted from Commonwealth lands represented the sale of trust assets and had to be returned to the corpus of the trust. To the extent that 72 P.S. sections 1602-E and 1603-E diverted royalties to the General Fund, the Court found the provisions violated the ERA. The Court lacked sufficient advocacy to determine if the remaining three revenue streams, consisting of large upfront bonus payments, yearly rental fees, and interest penalties for late payments that were allocated to the General Fund under Sections 1604-E and 1605-E, as well as Section 1912 of the Supplemental General Appropriations Act of 2009, also constituted the sale of trust assets. Thus the case was remanded to the Commonwealth Court for further proceedings. On remand, the Commonwealth Court, sitting en banc, determined that the three revenue streams did not constitute the sale of trust assets. On return to the Supreme Court, it was determined the Commonwealth Court's holding was at odds with the Supreme Court's holding before remand. Another remand was unnecessary; the Supreme Court determined the record was sufficiently developed, and based upon that record it held the incomes generated under these oil and gas leases had to be returned to the corpus. As a result, the decision of the Commonwealth Court was reversed. View "PA. Environ. Defense Fd. v. Pennsylvania" on Justia Law
Phelps Oil and Gas v. Noble Energy
Phelps Gas & Oil brought a class action in Colorado state court against Noble Energy and DCP Midstream for underpayments on oil and gas royalties Noble allegedly owed Phelps and other owners of royalty interests. DCP Midstream removed the class action to federal district court. Phelps then moved to remand the case to state court, arguing the case failed to meet the federal $75,000 amount-in-controversy requirement. The district court denied the motion, and later entered summary judgment, dismissing all of Phelps’s claims. The Tenth Circuit concluded the district court erred in denying Phelps’s motion to remand, thus dismissing the appeal for lack of jurisdiction. "[N]either the value to Phelps nor the cost to either defendant in this case would result in more than $75,000 at controversy. Though the contracts between Noble and DCP are worth millions of dollars, we cannot base federal jurisdiction on potential future litigation involving the defendants." View "Phelps Oil and Gas v. Noble Energy" on Justia Law
Growth Energy v. Environmental Protection Agency
The Clean Air Act’s Renewable Fuel Standard Program (42 U.S.C. 7547(o)(2)(A)(i)) calls for annual increases in the amount of renewable fuel introduced into the U.S. fuel supply and sets annual targets for renewable fuel volumes. Each year, EPA implements those targets but has certain waiver authorities to reduce the annual targets below the statutory levels. Companies that produce renewable fuels argued that EPA’s 2019 volume levels (83 Fed. Reg. 63,704) were too low; fuel refiners and retailers argued that the 2019 volumes were too high. Environmental organizations challenged various aspects of the 2019 Rule relating to environmental considerations.The D.C. Circuit denied their petitions for review except for the environmental organizations’ challenges concerning whether the 2019 Rule would affect listed species, which it remanded without vacatur. The court upheld EPA’s 2019 continuation of its practice of granting exemptions to small refineries after promulgating the annual percentage standards; EPA’s decision to exclude electricity generated from renewable biomass (a form of cellulosic biofuel) from its cellulosic biofuel projection in the 2019 Rule; EPA’s determination that the 2019 volumes would not cause severe economic harm; and EPA’s decision not to obligate ethanol blenders under the RFS Program. EPA adequately explained its refusal to exercise the inadequate domestic supply waiver. EPA did not act arbitrarily in estimating that 100 million gallons of sugarcane ethanol were “reasonably attainable” for 2019. View "Growth Energy v. Environmental Protection Agency" on Justia Law
Virginia Electric & Power Co. v. State Corporation Commission
The Supreme Court affirmed the decision of the State Corporation Commission finding that a pumped storage hydroelectric facility (or pumped storage) generates "renewable energy" under the former definition in Va. Code 56-576 and that the amended definition would not apply to contracts executed before the amendment's effective date, holding that there was no error.The Commission concluded that pumped storage satisfied the statutory definition of renewable energy in effect at the time that the service provider executed its contracts and declined to find that the amended definition would apply retroactively to contracts executed before the amendment's effective date. The Supreme Court affirmed, holding (1) the Commission did not err in its interpretation of the statute or its finding that pumped storage satisfied the former definition of renewable energy; and (2) the Commission did not err in refusing retroactively to apply the amended statutory definition of renewable energy to the service provider's contracts that were executed before the amendment took effect. View "Virginia Electric & Power Co. v. State Corporation Commission" on Justia Law