The Supreme Court vacated the decision of the circuit court affirming the decision of the South Dakota Public Utilities Commission issuing an order accepting the certification of TransCanada Keystone Pipeline LP that it continued to meet permit conditions, holding that the circuit court lacked jurisdiction to hear Appellants’ appeals.The Commission granted a permit to TransCanada to construct the Keystone XL Pipeline in South Dakota. None of the parties in that proceeding appealed the order issuing a permit. Because TransCanada was unable to commence construction within four years, it certified that it continued to meet the permit conditions, as required by S.D. Codified Laws 49-41B-27. After conducting an evidentiary hearing, the Commission accepted the certification. Appellants - the Cheyenne River Sioux Tribe, the Yankton Sioux Tribe, and Dakota Rural Action - each appealed. The circuit court affirmed. The Supreme Court consolidated the appeals, vacated the circuit court’s decision, and dismissed the appeal, holding that the circuit court lacked jurisdiction to hear the appeals. View "In re Keystone XL Pipeline" on Justia Law

by
At issue in this case are the ramifications of a utility filing more than one rate with FERC during the time in which the utility negotiates an agreement with a prospective customer. The DC Circuit denied the petition for review and upheld FERC's determination that the governing rate was the rate in effect at the time the agreement was completed. Because the court found that FERC properly considered the court's findings on remand, adequately explained its decision, and properly considered the evidence, FERC did not act arbitrarily and capriciously in interpreting the new rate. View "ESI Energy, LLC v. FERC" on Justia Law

by
The Supreme Court affirmed the decision of the Board of Oil, Gas, and Mining to impose a joint operating agreement (JOA) on J.P. Furlong Company’s relationship with the party operating a drilling unit that included Furlong’s mineral lease.Furlong complained that the Board accepted, without making any of the changes to the JOA that Furlong wanted, the JOA the operator proposed. On appeal, Furlong argued that the Board erroneously applied the law to conclude that the JOA was just and reasonable and that there was not substantial evidence to support the Board’s decision. The Supreme Court affirmed, holding that the Board correctly applied the law and rendered a decision supported by substantial evidence. View "J.P. Furlong Co. v. Board of Oil & Gas Mining" on Justia Law

by
The Fifth Circuit granted Nevada's motion to dismiss Texas' petitions for declaratory and injunctive relief in a dispute arising out of the government's struggle with nuclear waste disposal under the Nuclear Waste Policy Act of 1982. Texas sought equitable relief prohibiting the Department of Energy from conducting any other consent-based siting activity and ordering defendants to finish the Yucca licensure proceedings. The court held that the deadline in 42 U.S.C. 10139(c) was not jurisdictional, and thus proceeded to consider whether the continuing violations doctrine may apply to Texas' claims; applying either versions of the continuing violations doctrine, whether as a tolling mechanism or as an apparent shorthand for an exercise in statutory interpretation, Texas' claims were still untimely; the court lacked jurisdiction to consider the Department of Energy's 2017 consent-based siting activities because they were not sufficiently final under the statute; and thus Texas' claims did not satisfy the statutory requirements of timeliness or finality. View "Texas v. United States" on Justia Law

by
The DC Circuit denied the Arkansas Commission's petition for review of a final FERC order. The FERC order held that an operating company withdrawing from a multi-state energy system must continue to share the proceeds of a pre-departure settlement with the other member companies. The court held that FERC had a lawful basis to order the sharing of the benefits of the settlement and was reasoned in its allocation methodology. Therefore, FERC's order for Entergy Arkansas to share the Union Pacific Settlement benefits and its method for allocating the settlement was not arbitrary, capricious, or contrary to law. View "Arkansas Public Service Comm. v. FERC" on Justia Law

by
In this dispute over an offset provision in an oil and gas lease the Supreme Court reversed the judgment of the court of appeals reversing the trial court’s summary judgment in the lessee’s favor on the grounds that the lessee did not conclusively demonstrate compliance with the provision.On appeal, the court of appeals determined that the lessee did not conclusively prove that it complied with the offset provision and thus was not entitled to summary judgment. In reversing, the Supreme Court held (1) the offset provision contained specific requirements, and the lessee met those requirements; and (2) the court of appeals read a requirement into the lease that its unambiguous language did not support. View "Murphy Exploration & Production Co. v. Adams" on Justia Law

by
Appellee, the Marcellus Shale Coalition (“MSC”), filed in the Commonwealth Court’s original jurisdiction a petition for review in the nature of a complaint seeking declaratory and injunctive relief (the “Petition”), on behalf of itself and its members. MSC challenged the validity of several regulations relating to unconventional gas well operations as governed by Pennsylvania’s Oil and Gas Act of 2012 (known as Act 13). MSC alleged that certain provisions were void and unenforceable for multiple reasons, including that they were vague, lacked statutory authorization, and conflicted with other regulations and statutes applicable to the industry. Furthermore, MSC averred that the rulemaking process did not comply with the Regulatory Review Act, and that the Pennsylvania Environmental Quality Board (the “EQB”) failed to develop criteria for the Pennsylvania Department of Environmental Protection (“DEP”) to use in conditioning a drilling permit on relevant factors. The Commonwealth Court issued a single-judge, unpublished opinion and order, granting in part and denying in part preliminary injunctive relief. The Commonwealth Court also issued an order granting in part and denying in part MSC's Application for Expedited Special Relief. The order preliminarily enjoined DEP from implementing and enforcing certain sections of the Act. After its review of the parties' arguments on appeal of the Commonwealth Court order, the Pennsylvania Supreme Court affirmed in part and reversed in part. The Supreme Court affirmed the grant of preliminary injunctive relief as to Counts I and II. As for Count IV, the Court affirmed the grant of relief as to Section 78a.59c, but reversed the grant of relief as to Section 78a.59b(b). Finally, the Court reversed the grant of preliminary injunctive relief as to Count V. View "Marcellus Shale Coalition v. Dept. Environmental Protection" on Justia Law

by
In a discretionary appeal, the issue reviewed by the Pennsylvania Supreme Court centered on whether the Commonwealth Court erred in reversing the decision of the Lycoming County Court of Common Pleas, which, in turn, had reversed the decision of the Fairfield Township Board of Supervisors (the “Board”) to allow for the drilling, construction, development and operation of unconventional natural gas wells as a conditional use in a district zoned Residential-Agricultural (“R-A”). The Supreme Court determined after review of the evidentiary record, the Board's decision was not supported by the evidence, and because the proposed use was not similar to any permitted use in the R-A district as required under the Fairfield Township Zoning Ordinance (the “Ordinance”), the Court reversed the decision of the Commonwealth Court. View "Gorsline v Bd. of Sup. of Fairfield Twp." on Justia Law

by
The Parker County Appraisal District did not employ a facially unlawful means of appraising Taxpayers’ property, which appeared to derive much of its market value from saltwater disposal wells in which wastewater from oil and gas operations could be injected and permanently stored underground.When valuing for tax purposes Taxpayers’ tracts of land in Parker County, the Parker County Appraisal District assigned one appraised value to the wells and another appraised value to the land itself. Taxpayers argued before the trial court that the Tax Code did not permit the County to appraise the wells separately from the land itself where both interests are owned by the same person and have not been severed into discrete estates. The trial court granted summary judgment for Taxpayers. The court of appeals reversed. The Supreme Court affirmed, holding (1) there was nothing improper in the District’s decision to separately assigned and appraise the surface and the disposal wells, which were part of Taxpayers’ real property and contributed to its value; and (2) the Tax Code does not prohibit the use of different appraisal methods for different components of a property. View "Bosque Disposal Systems, LLC v. Parker County Appraisal District" on Justia Law

by
The Supreme Court affirmed the judgment of the court of appeals reversing the trial court’s ruling that TRO-X, LP was entitled to a back-in percentage of the working interest in five mineral leases under which Anadarko Petroleum was lessee.TRO-X sued Anadarko, asserting claims for breach of contract and trespass to try title and seeking a declaratory judgment that the leases were top leases and therefore subject to TRO-X’s back-in interest. The trial court concluded that the leases were top leases, in which TRO-X retained a back-in interest, rather than new leases, which washed out TRO-X’s interest. In reversing, the court of appeals concluded that the leases were not top leases. The Supreme Court agreed, holding that the leases at issue were not top leases subject to TRO-X’s back-in interest. View "TRO-X, L.P. v. Anadarko Petroleum Corp." on Justia Law