Justia Energy, Oil & Gas Law Opinion Summaries

Articles Posted in Government & Administrative Law
by
The Supreme Judicial Court affirmed the order of the Maine Public Utilities Commission approving a stipulation regarding Efficiency Maine Trust’s Third Triennial Plan for energy efficiency, holding that the Commission did not err in interpreting and applying the relevant statutes.The Conservation Law Foundation appealed from the Commission’s order approving the stipulation, arguing that the order and the terms of the stipulation disregarded statutory mandates set forth in the Efficiency Maine Trust Act. See Me. Rev. Stat. Ann. tit. 35-A, 10101-10123. The Supreme Judicial Court held that the Commission’s order and the stipulation did not violate statutory mandates for electric energy efficiency or the statutory mandate to assess each natural gas utility an amount to capture all maximum achievable cost-effective energy efficiency savings. View "Conservation Law Foundation v. Public Utilities Commission" on Justia Law

by
Riverkeeper petitioned for review of FERC's Certificate of Public Convenience and Necessity conditionally approving the Leidy Project. The DC Circuit denied the petition and held that it had jurisdiction to consider Riverkeeper's challenge to the Certificate Order on the ground that FERC violated the sequencing requirement of the Clean Water Act (CWA) by issuing its Certificate Order before Pennsylvania issued its section 401 certification; the sequencing requirement of section 401 was not triggered because the Commission's conditional approval of the Leidy Project construction did not authorize any activity which might result in a discharge in navigable waters; the court need not decide whether the letter orders impermissibly approved activity that might have resulted in a discharge before Pennsylvania issued its section 401 certification; FERC did not violate the National Environmental Policy Act (NEPA) by misclassifying wetlands; even if FERC technically erred in some of its classifications, Riverkeeper has not shown any prejudice; and FERC's NEPA review of the Leidy Project's proposed gas flow velocities appeared to be fully informed and well-considered. View "Delaware Riverkeeper Network v. FERC" on Justia Law

by
Section 309 of the Federal Power Act (FPA), 16 U.S.C. 825h, vests the Commission with broad remedial authority, including the authority to grant recoupment when it is justified; Section 201(f) does not limit the authority of the Commission to grant relief under Section 309 with respect to matters that are beyond the strictures of Sections 201(f) and 205; and an order of recoupment, as distinguished from an order to refund under Section 205, is beyond the strictures of Sections 201(f) and 205. In this case, Chehalis sought relief from the Commission by filing a Motion for an Order Requiring Recoupment of Payments, but the Commission concluded that it could not order recoupment because the Commission's refund authority does not extend to exempt public utilities such as the Intervenor Bonneville. The DC Circuit held that the Commission erred when it held that it lacked the authority to grant the Order Requiring Recoupment where the Commission clearly had jurisdiction over the subject of this dispute and the Commission retained the authority to order Bonneville to return the funds when the agency acknowledged that its initial order was mistaken. The court granted in part and denied in part Chehalis's petitions for review, and remanded for further proceedings. View "TNA Merchant Projects v. FERC" on Justia Law

by
A district court has broad discretion to decide whether and when to grant an agency's request for a voluntary remand. But a voluntary remand is typically appropriate only when the agency intends to revisit the challenged agency decision on review. After the Department rejected Limnia's two loan applications, Limnia filed suit alleging that the Department's rejection of Limnia's applications was unlawful under the Administrative Procedure Act. The district court then granted the Department's voluntary remand request. The DC Circuit held that the district court erred by granting the Department's request for a voluntary remand in this case because the Department did not intend to revisit the original application decisions under review. Therefore, the DC Circuit reversed and remanded for further proceedings. View "Limnia, Inc. v. DOE" on Justia Law

by
In consolidated cases, two municipalities sought to provide electric service through municipal electric utilities. Central to both cases was the applicability Michigan Administrative Code Rule 411 (sometimes referred to as a utility’s right to first entitlement). Rule 460.3411 (Rule 411) was inapplicable when a municipal utility is involved and has not consented to the jurisdiction of the Michigan Public Service Commission (PSC). Additionally, under the circumstances of each case, the Michigan Supreme Court found there was not a customer already receiving service from another utility; accordingly, MCL 124.3 did not prevent either plaintiff from providing electric service. View "City of Holland v. Consumers Energy Co." on Justia Law

by
Substantively, in three somewhat interconnected claims, Joe and Yvette Hardesty (collectively, Hardesty) attacked State Mining and Geology Board (Board) findings, contending the trial court misunderstood the legal force of his 19th century federal mining patents. He asserted he had a vested right to surface mine after the passage of SMARA without the need to prove he was surface mining on SMARA’s operative date of January 1, 1976. He argued the Board and trial court misapplied the law of nonconforming uses in finding Hardesty had no vested right, and separately misapplied the law in finding that his predecessors abandoned any right to mine. These contentions turned on legal disputes about the SMARA grandfather clause and the force of federal mining patents. Procedurally, Hardesty alleged the Board’s findings did not “bridge the gap” between the raw evidence and the administrative findings. Hardesty also challenged the fairness of the administrative process itself, alleging that purported ex parte communications by the Board’s executive director, Stephen Testa, tainted the proceedings. The Court of Appeal reviewed the facts, and found they undermined Hardesty’s claims: the fact that mines were worked on the property years ago does not necessarily mean any surface or other mining existed when SMARA took effect, such that any right to surface mine was grandfathered. However, the Court agreed with the trial court’s conclusions that, on this record, neither of these procedural claims proved persuasive. Accordingly, the Court affirmed the judgment denying the mandamus petition. View "Hardesty v. State Mining & Geology Board" on Justia Law

by
Louisville Gas and Electric Company (LG&E) sought a permit authorizing it to discharge certain pollutants into the Ohio River in conjunction with the operation of its recently expended generating facility. The Commonwealth of Kentucky, Energy and Environment Cabinet’s Division of Water issued the permit. The circuit court vacated the permit. The Court of Appeals affirmed. The Supreme Court reversed and reinstated LG&E’s permit, holding (1) in vacating the permit, the circuit court and Court of Appeals misapplied controlling federal law; and (2) the Cabinet’s determination that the LG&E permit should proceed under 40 C.F.R. 125.3(c)(1) was a reasonable interpretation of the regulation. View "Louisville Gas & Electric Co. v. Kentucky Waterways Alliance" on Justia Law

by
Section 210 of the Public Utility Regulatory Policies Act of 1978 (PURPA), 16 U.S.C. 824a-3, seeks to reduce reliance on fossil fuels by increasing the number of energy-efficient cogeneration and small power-production facilities. Oregon implements its PURPA responsibilities largely through its Public Utility Commission (OPUC), which has directed utilities subject to its jurisdiction to draft off-the-shelf, standard-form power-purchase agreements that OPUC then reviews for compliance with PURPA. OPUC has approved two standard-form power-purchase agreements submitted by petitioner Portland General Electric. Petitioner PáTu Wind Farm, a six-turbine, nine-megawatt generator in rural Oregon, is classified under PURPA as a small power producer. This appeal stems from the parties' dispute over the nature of Portland General's purchase obligation. The Commission ruled that under PURPA, Portland General must purchase all of PáTu’s power, though it rejected PáTu’s insistence that Portland General do so by utilizing a technology known as dynamic scheduling. The court concluded that PáTu’s petition dealing exclusively with Portland's refusal to utilize dynamic scheduling is without merit. Accordingly, the court denied PáTu’s petition. The court dismissed Portland's petition challenging the Commission's ruling that it must purchase all of PáTu’s power for lack of jurisdiction because FERC's orders were advisory. View "Portland General Electric Comp v. FERC" on Justia Law

by
Plaintiffs-Appellants, a certified class of Osage tribal members who owned headrights, appealed the district court’s accounting order. Plaintiffs alleged that the government was improperly distributing royalties to non-Osage tribal members, which diluted the royalties for the Osage tribal members, the rightful headright owners. The complaint attributed this misdistribution to the government’s mismanagement of the trust assets and the government’s failure to perform an accounting. Thus, Plaintiffs sought to compel the government to perform an accounting and to prospectively restrict royalty payments to Osage tribal members and their heirs. The district court dismissed Plaintiffs’ accounting claim because it found that the applicable statute only required the government to account for deposits, not withdrawals, and that such an accounting would not support Plaintiffs’ misdistribution claim. After review, the Tenth Circuit could not say the district court abused its discretion. "The accounting the district court fashioned will certainly inform Plaintiffs of the trust receipts and disbursements and to whom those disbursements were made." View "Fletcher v. United States" on Justia Law

by
This petition for review returned to a long series of administrative cases arising out of the California energy crisis of 2000 and 2001 all centering on whether the Federal Energy Regulatory Commission (“FERC” or “Commission”) acted arbitrarily or capriciously in calculating certain refunds. FERC that FERC had acted outside its jurisdiction when ordering governmental entities/non-public utilities to pay refunds, the Commission vacated each of its orders in the California refund proceeding to the extent that they ordered governmental entities/nonpublic utilities to pay refunds. In sum, although the tariffs were not specific, the Ninth Circuit could not concluded FERC acted arbitrarily or capriciously in its construction of the tariffs. View "California Pub. Util. Comm'n v. Federal Energy Reg. Comm'n" on Justia Law